This is Appendix F of a federal contract solicitation for Hazardous & Flammable Gas Cabinet Installation (Project PRJ0012938 SPH R218) at Ames National Laboratory, containing safety requirements and deliverables.
Ames National Laboratory requires contractors to follow an "OSHA+" approach, implementing more stringent safety standards than OSHA minimums as outlined in 10 CFR 851. Contractors must develop hazard mitigation and work plans reviewed by the laboratory's Environment, Safety and Health (ESH) department before performing work involving hazardous energy, lasers, noise, fire protection, pressure safety, silica, chemical exposure, respirators, and welding. All training records, medical clearances, Standard Operating Procedures (SOPs), and Safety Data Sheets (SDSs) must be provided upon request. Contractors may encounter mercury compounds, asbestos, beryllium, lead, and radiation in laboratory spaces; Ames will identify these hazards, and mitigation plans will be developed collaboratively. Subcontractors cannot access interstitial spaces without approval due to contamination concerns. For crystalline silica exposure, contractors must comply with the more stringent ACGIH TLV-TWA (0.025 mg/m³) rather than OSHA's PEL (0.050 mg/m³).
Additional mandatory requirements include confined space entry approval per CFR 1910.146 and 1926 Subpart AA with documentation of trained personnel, electrical work performed only by qualified workers per NFPA 70E with an electrical assessment and work plan reviewed by the Authority Having Jurisdiction (AHJ), mechanical lockout tagout (LOTO) per CFR 1910.147 for all hazardous energies, fall protection programs for elevated work and scaffolding per 29 CFR 1926 Subpart L, ladder compliance per 29 CFR 1910.23 or 1926.1053, standard PPE including safety glasses and hard hats, hot work permits and fire watches for 60 minutes post-completion, machine guards for rotating parts, and a Subcontractor Affirmation Form signed by all contractor tiers acknowledging compliance with all safety rules and regulations.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix F - PRJ0012938 SPH R218 Hazardous & Flammable Gas Cabinet Installation
Safety Requirements and Deliverables
This appendix is intended to raise awareness of hazards initially identified by Ames National Laboratory and provide guidance for mitigating those hazards. It is not intended to be a comprehensive list of all potential hazards or to replace the requirement to perform appropriate hazard assessments and develop hazard mitigation plans in accordance with the requirements and regulations identified in the Appendix titled "ENVIRONMENT, SAFETY AND HEALTH (ESH) REQUIREMENTS, September 5, 2024”. Additional documentation and requirements may be identified as the project progresses.
i. Ames National Laboratory follows an “OSHA+” approach to construction-based activities. The “+” references more stringent safety requirements and planning than is required strictly by OSHA. The regulation requirements are listed in 10 CFR 851
Worker Safety and Health Program.
1. Work scheduled to be performed that deals with Hazardous energy (electrical, plumbing, mechanical, etc.), Lasers, Noise, Fire Protection/Prevention, Pressure Safety, Silica, Worker Exposure to Chemical Substances, Respirators, and Welding will require further mitigation and work plans to be developed and reviewed by Ames National
Laboratory ESH department before work can be performed.
ii. All documentation must be available to Ames National Laboratory upon request including, but not limited to: training records, medical clearance, SOPs, and SDSs shall be provided in conjunction with the hazard evaluation and hazard management statements.
iii. Copies of SDS for all chemicals, compounds, coatings, paints, etc. which will be brought on-site must be submitted in conjunction with the hazard evaluation documentation, or as soon as it is determined it will be used.
iv. Contractors may encounter mercury compounds while working in laboratory space, elemental mercury when removing drain traps, or mercury vapor via broken fluorescent lamps.
v. Subcontractors are not to access interstitial spaces due to potential contamination unless approved by Ames National
Laboratory ESH. (Beryllium, Radiological, Asbestos, etc. concerns)
vi. Asbestos hazards or Potential Asbestos Containing Materials (PACM) will be identified by Ames National Laboratory. If asbestos is positively identified, or is a PACM that could not be tested, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
1. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
vii. Beryllium hazards will be identified by Ames National Laboratory. If Beryllium contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
1. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
viii. Lead hazards will be identified by Ames National Laboratory. If Lead contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
1. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
ix. Radiation hazards will be identified by Ames National Laboratory. If Radiation contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
1. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
x. Crystalline Silica Exposures- Note that the Department of Energy requires that their contractors comply with the ACGIH TLV-
TWA for respirable crystalline silica (RCS) as the exposure limit. This is a more stringent standard than the OSHA PEL
(TLV=0.025 mg/m3 RCS; PEL=0.050 mg/m3 RCS).
1. Work pause and the reassessment of work practices and personal protection with the Industrial Hygiene department are required if visible dust is observed in an operation.
xi. Nuisance dust may be generated during work activities, if visible dust is observed, a reassessment of work practices and personal protection by Ames National Laboratory is required.
xii. Confined Spaces shall not be entered until there has been approval by Ames National Laboratory ESH. All confined space entries will comply with CFR1910.146 and CFR1926 Subpart AA.
1. A form is required to be completed by all entrants for non-permit entrances or permit required entrances.
2. Documentation of individuals who are Confined Space trained, when training occurred, and when it expires will be required before confined space work can be performed.
xiii. Identification of hazardous environments, including thermal stress such as extreme cold, heat or high humidity, shall be identified and accounted for in the work planning and control procedures. (Hazard Management Statements)
xiv. Activities that produce noise above 85 dBA using ACGIH standards shall be accounted for using engineering control, or using
PPE such as earplugs, earmuffs or a combination of.
xv. Traffic interruptions, foot traffic, vehicle traffic, etc., are prohibited without a Traffic Control Plan developed, reviewed and approved by Ames National Laboratory and Iowa State Department of Public Safety.
xvi. Lifting of objects over 50 pounds shall be completed using a two person lift or using a lifting device.
xvii. Subcontractor Affirmation Form needs to be completed and signed by all subcontractor’s and sub-tier subcontractor’s company representatives to acknowledge that all rules and regulations listed in the Terms and Conditions, along with any other safety related documents and or conversations, are being communicated and adhered to through all tiers of subcontractors. It is the responsibility of the subcontractor awarded the contract to make sure all sub-tier subcontractors are following all rules and regulations at all times, and enforce proper escalation protocols if rules and regulations are not being followed.
xviii. All construction debris will be surveyed before being removed from work area.
xix. Electrical work must be performed, per NFPA 70E, only by qualified and approved electrical workers, with approved equipment and PPE, using the electrical safe work practices.
1. An electrical assessment and work plan must be reviewed by AHJ before work can be performed.
xx. Electrical work must be performed only by qualified and approved electrical workers, with approved equipment and PPE, using the electrical safe work practices
xxi. Project planners, supervisors, and workers must consider electrical hazards when performing excavations and penetrations.
Reference the Penetration Permit Procedure (Form 10200.256).
1. Failure to understand what may lie behind a penetration may lead to contact and exposure to hazardous materials, electrical and other utilities. Contact may result in serious injury, death and/or property damage.
2. Wall/ceiling/floor penetrations necessitate a review of historical records, engineering plans, and as-built drawings that pertain to the area/location where the penetration is planned.
3. If the penetration risk assessment does not exclude the likelihood of contact with buried hazards, voltage-rated gloves with leather protectors shall be used to protect the worker while performing the penetration. The class of the gloves shall reflect the highest voltage of any circuit known to be in the vicinity of the penetration. Double insulated tools may be used to provide an additional level of safety.
4. Scan for hidden utilities per the penetration permit process (Form No. 10200.256).
xxii. Application of a mechanical lockout device and a tag on an energy isolation by a LOTO authorized person in accordance with established procedures to control hazardous energies and prevent the equipment from being operated until the lockout device is removed.
xxiii. A Fall Protection Program must be submitted and reviewed before any work is allowed to be performed in the proximity of floor openings, on elevated work platforms, or on scaffolds.
1. For any leading-edge work, barriers and warning flags must be installed during the duration of the project.
2. All scaffolding usage will comply with 29 CFR part 1926, subpart L.
a. Scaffolding must be erected and inspected by a trained competent person.
i. That competent person is to be on-site any time scaffolding is in use.
ii. Certification must be made available when requested.
3. Usage of portable manlifts will comply with 29 CFR 1910 Subpart F or 29 CFR 1926.451 and 1926.452 as applicable.
xxiv. All ladder usage will comply with 29 CFR 1910.23 or 29 CFR 1926.1053 as applicable.
1. All ladders will be visually inspected daily prior to use.
xxv. Standard PPE must be worn by persons performing or assisting with performing the work. This includes but is not limited to safety glasses with side shields/safety goggles and hard hats where overhead hazards exist.
1. Additional PPE may be required depending on hazard and mitigation requirements.
xxvi. Respirators may be required where:
1. Airborne concentrations are elevated and ventilation/engineering controls cannot sufficiently reduce airborne exposures
2. Large surface areas and substantial hand work are involved
3. When respirators are used a respiratory protection program must be developed and implemented which complies with 29 CFR 1910.134 or CFR 1926.103 as applicable.
4. Note that the Department of Energy requires that their contractors comply with the ACGIH TLVs (time-weighted averages, short-term exposure limits, ceilings).
xxvii. Before performing hot work (torch use, grinding, cutting, etc.) coordination must be conducted with Ames National Laboratory
Plant Protection and a Hot Work Permit needs to be filled out and approved.
1. A designated fire watch, with the properly rated fire extinguisher, must be in place during work and 60 minutes after the hot work has been completed.
2. Proper ventilation/Air quality plan must be provided, reviewed, and approved before any hot work to be approved.
xxviii. All machine guards must be installed to protect against rotating parts.
xxix. Potential pinch points shall be identified before work is to proceed and all parties are to be notified and given clear instructions on how to avoid being in or around pinch points before work is to be performed.
xxx. Subcontractors will utilize Lockout Tagout per CFR1910.147 to control all hazardous energies. This includes but is not limited to: mechanical, hydraulic, pneumatic, chemical, thermal, electrical, and stored energy.