This document is an Addendum to a Request for Proposal (RFP) for the Ames Infrastructure Modernization Project at Ames National Laboratory, a Department of Energy facility.
The key details are:
- Addendum Number 5 modifies information in the original RFP documents dated 9/26/2024.
- The deadline to submit questions has been extended from 11/8/2024 to 11/15/2024 by 4:00 p.m. CDT.
- The date for the next addendum to be issued has been moved from 11/13/2024 to 11/20/2024.
- The overall RFP is seeking general construction services for the Ames Infrastructure Modernization Project at the Ames National Laboratory in Ames, Iowa. Proposals are due on 1/3/2025 at 4:00 p.m. CST.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ames Laboratory RFP SC-25-637 ADDENDUM NUMBER 5
ADDENDUM NUMBER 5
ADDENDUM DATE: 11/7/2024
PROJECT: RFP SC-25-637 Ames Infrastructure Modernization Project
PROPOSAL DUE DATE: 1/3/2025 at 4:00 p.m. CST
ADDENDUM ISSUED DATE: 11/7/2024
The information contained in this Addendum 4 modifies, supplements, or replaces information contained in the Bidding Documents dated 9/26/2024.
Acknowledge receipt of this and all RFP Addendums with your proposal submission.
Addendum consists of 1 page.
ADDENDUM INDEX
GENERAL ITEMS: 0
APPLICABLE TO THE RFP DOCUMENT: 2
APPLICABLE TO THE PROJECT SPECIFICATIONS AND DRAWINGS: 0
ATTACHMENTS: 0
GENERAL ITEMS: None
APPLICABLE TO THE RFP DOCUMENT:
1. The current question submission deadline is moved from 11/08/2024 to 11/15 by 4:00 p.m. CDT.
2. The next addendum issuing date is moved from 11/13/2024 to 11/20/2024.
APPLICABLE TO THE PROJECT SPECIFICATIONS AND DRAWINGS: None