This document is Addendum Number 2 to Request for Proposal (RFP) SC-25-637 for the Ames Infrastructure Modernization Project. The addendum modifies the RFP timeline, including extending the question submission due date, the addendum issuance date, and the proposal due date. It also includes a question and answer log as Attachment 1, which addresses topics such as tax exemption, onsite personnel requirements, commissioning, BIM coordination, and generator specifications. The federal contract opportunity is being solicited by the Department of Energy's Ames Laboratory for general construction services to support infrastructure modernization at their facility in Ames, Iowa. The RFP seeks to award one or more subcontracts to the offeror(s) whose proposals are most advantageous to the government.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NUMBER 2 ADDENDUM DATE: 10/17/2024

PROJECT: RFP SC-25-637 Ames Infrastructure Modernization Project

PROPOSAL DUE DATE: 11/20/2024 at 4:00 p.m. CST

ADDENDUM ISSUED DATE: 10/17/2024

The information contained in this Addendum 2 modifies, supplements, or replaces information contained in the Bidding Documents dated 9/26/2024.

Acknowledge receipt of this and all RFP Addendums with your proposal submission.

Addendum consists of 1 page and the attachments listed below.

ADDENDUM INDEX

GENERAL ITEMS: 0

APPLICABLE TO THE RFP DOCUMENT: 2

APPLICABLE TO THE PROJECT SPECIFICATIONS: 2

ATTACHMENTS: 1

APPLICABLE TO THE RFP DOCUMENT:

1. RFP Timeline has been adjusted as follows:

- The question submission due date has been moved from 10/18/2024 by 4:00 p.m. CST to

10/23/2024 by 4:00 p.m. CST to allow more time for questions.

- The RFP Addendum to provide answers to all questions submitted and any other addendum items issuing date has been changed from 10/25/2024 to 10/29/2024.

- The RFP Proposal Due Date has been changed from 11/15/2024 by 4:00 p.m. CST to 11/20/2024 by 4:00 p.m. CST

2. Questions submitted to date and answers to all questions submitted are included as Attachment 1 to this Addendum 2.

APPLICABLE TO THE PROJECT SPECIFICATIONS:

1. The changes to the RFP timeline also apply to the project milestone dates in the Appendix B – Specifications and Drawings dated 09/26/2024 Rev. 0 under Special Conditions 00 30 00 – 2.

2. Some answers provided to questions submitted to date are directly related to information included in the Appendix B Specifications and Drawings dated 09/26/2024.

ATTACHMENT 1 - QUESTION / ANSWER LOG RFP SC-25-637 Addendum 2 10/17/2024 Ames National Laboratory - AIM

QUESTION ANSWER

1 We would like to request the deadline for questions be extended to 10/25/2024 by 4:00 PM CST. This additional time will allow us to generate the necessary questions to address any discrepancies or clarifications encountered when comparing the project documents to the existing conditions.

Question period has been extended to 23 October 2024 at 4:00pm CST.

The date for the Addendum issued with answers to questions submitted has been extended to 10/29/2024.

The proposal due date has been extended to 11/20/2024 at 4:00pm CST.

2 Please confirm this project is tax exempt Yes, this project is tax exempt, and The Laboratory Procurement Representative will provide tax exemption certs for the GC and any subs which require them.

3 Please confirm a dedicated onsite superintendent is required for this project.

Yes, this is required 100% of the time.

4 Is a dedicated onsite safety officer required for this project?

As part of each subcontractor's proposal, they will have to present qualified persons for the superintendent and safety representative roles and show that they have the experience and training necessary to manage safety. A safety lead/ abatement crew leader must be on-site during any abatement or high-risk work. This could include work related to legacy contamination abatement, asbestos removal, critical lifts, confined space entries, major hot work, or any other high-risk safety-related items that the Ames Lab ESH team find necessary. The onsite superintendent may qualify for parts of this if they have expertise and proper training in any specific hazardous work tasks.

5 Is a dedicated on-site quality control manager required for this project?

Not dedicated on-site but the Quality Management Plan should outline the role of the quality control manager.

6 Please confirm the commissioning agent is provided by Ames National Laboratory.

Confirmed

7 Please confirm BIM Coordination is required on this project.

Confirmed. The drawings have been developed in Revit but not all existing infrastructure is modeled.

8 What approved project management software can be used on this project?

Ames Lab prefers Procore

9 Clarification on enclosure/tank accessories. Will the following items be needed?

See a. – d. below.

a. Motor/gravity operated automatic air-inlet/air-outlet dampers.

To be addressed in addendum 3.

b. AC or DC enclosure lighting (interior). Non-walk in enclosure, no lighting to be provided.

c. Exterior enclosure lighting. To be addressed in addendum 3.

d. Digital fuel monitoring. To be addressed in addendum 3.

10 2.3 H states the gensets are 4 wire systems. Please confirm.

Confirmed

11 U1.10 shows a load bank between the gensets. Is a permanent load bank needed? If so, please provide specifications and details on connection to the electrical system.

No, a permanent load bank is not desired. One should be provided by the contractor for commissioning.

12 2.8 2. The diesel genset is specified as a “walk-in” style enclosure but the NG genset is not. Please advise.

Both gensets shall be level 2 sound attuned manufacturer enclosures. No walk in is desired.

13 2.8 G. Working platforms are specified for the diesel genset but not for the NG genset. Please advise.

No working platforms needed, provide level 2 sound attenuated manufacturer enclosure.

14 3.7 A maintenance contract is specified on the NG genset but not the diesel genset. Please advise.

Please provide a maintenance contract for both generators.

15 No circuit breakers or load break switches are shown on the 5kV generators. Please confirm none are required.

Confirmed, generator breaker located within switchgear.

Generators to be provided with CTs.

16 No load bank test is specified. Please confirm the building load is sufficient for onsite testing.

Yes, the building load is sufficient and expected for routine onsite testing.

17 Spec refers only to Eaton / Cutler-Hammer breakers.

Are other mfgs acceptable?

Specification manufacturer list will be updated with addendum 3. Contractors can submit alternates for approval prior to bid using the alternate request forms provided in the project manual.

18 Are SWGR 1 and SWGR 2 manually controlled or is there supposed to be any type of automated control of the SWGR lineups.

Individual breakers are controlled by protective relays.

Relays to be programmed by the SWGR Vendor.

Generators to also be automatically controlled by programming from Generator Vendor.

19 Is a sequence of operations available? Sequence shall be provided with Addendum 3.

20 The One-line shows draw out single phase PT on 52-

M1, M2, G1, M3, M4 & G2. These will not fit within the gear layout as shown unless they are fixed mount in the cable compartment (not optimal) or top hat mounted on the roof of the swgr. Is this acceptable?

PT locations will be addressed in Addendum 3.

21 Typically, 3 phase PTs are furnished on all incoming sources. Drawings reflect single phase.

For value engineering, the three-phase measurement is on the bus while line side is used for syncing.

22 Are the furnished schematics an accurate as to how the equipment is intended to be wired?

Olsson schematics describe the minimum performance requirements of functionality and do not indicate all internal wiring. Olsson schematics may include place holder terminal blocks that are desired in the terminal cabinet for convenience.

23 Please advise if AMP Manufacturing will be approved for supplying the PDC

Specification manufacturer list will be updated with addendum 3.

24 Please provide details or spec section on battery station system for the PDC.

To be included in Addendum 3.