g-swift Typewritten Text Attachment 1 Monthly Status Report Format

ConservationSpace Monthly Status Report – Month Year Scope Schedule Budget

G G G

Key Complete On Schedule/Budget Minor Issues Major Issues

Project Schedule Accomplishments (as of August, 2012) Upcoming Activities (next two months)

• Brief summary of first accomplishment

• Brief summary of second accomplishment

• Brief summary of third accomplishment

• Brief summary of first upcoming activity

• Brief summary of second upcoming activity

Work Product & Deliverable Status Current Focus: Milestone/Deliverable Name/Number Comments Status

• Title of first deliverable or work product

• Title of second deliverable or work product

• Title of third deliverable or work product

• Completed

• Ongoing

• Date expected

Project Budget Current Focus: Budgeted Invoiced Remaining Funds Status

Budget Item 1 Budget Item 2 Budget Item 3

Project Total:

$0,000 $00,000

$000,000

$0 $0

G

G

ConservationSpace Monthly Status Report – Month Year Scope Schedule Budget

G G G

Key Complete On Schedule/Budget Minor Issues Major Issues

Issues & Risks Risk Description Owner Status Updates Deadline

• First issue or risk • Brief summary • NGA lead Completed Success mm/dd/yy

• Second issue or risk • Brief summary • NGA lead Pending Outlook Good mm/dd/yy

• Third issue or risk • Brief summary • NGA lead Pending Outlook Good mm/dd/yy

Outstanding Action items and Steps to Resolve Action Steps to Resolve Owner Status Updates Deadline

• First action item • Brief summary of steps to resolve NGA, Partners Completed Completed mm/dd/yy

• Second action item • Brief summary of steps to resolve NGA, Partners Completed Completed mm/dd/yy