This document is a solicitation from the State of Missouri for the procurement of ready-mix concrete, admixtures, and accessories to be used for construction projects at the Johnson Shut-Ins State Park. The solicitation outlines specific requirements for the concrete, including compressive strength, water-cementitious materials ratio, slump, air entrainment, and temperature tolerances for both hot and cold weather conditions. Vendors are required to provide pricing per cubic yard and indicate the minimum standard load size and maximum short load size. The concrete must be delivered free on board to the destination, with payment terms of net 45 days. The solicitation has a response period open from May 25, 2023, to June 22, 2023.

The solicitation does not specify a total estimated value for the contract, nor does it indicate any set-aside requirements, incumbent contractors, or specific funding sources. It also does not impose any restrictions on the types of organizations that can respond, nor does it list any existing infrastructure or technology that requires integration.

View the file

Other files

File Type Posted
RFPC30034902302355_Sep_16_24_solicitation_doc.pdf PDF
RFPC30034902302355_Aug_30_24_solicitation_doc.pdf PDF
RFPC30034902302355_Oct_7_24_solicitation_doc.pdf PDF
RFPC30034902302355_Feb_24_25_solicitation_doc.pdf PDF
RFPC30034902302355_Sep_23_24_solicitation_doc.pdf PDF
RFPC30034902302355_Mar_31_25_solicitation_doc.pdf PDF
RFPC30034902302355_Sep_2_24_solicitation_doc.pdf PDF
RFPC30034902302355_Aug_23_24_solicitation_doc.pdf PDF
RFPC30034902302355_Sep_30_24_solicitation_doc.pdf PDF
RFPC30034902302355_Nov_4_24_solicitation_doc.pdf PDF
RFPC30034902302355_Mar_10_25_solicitation_doc.pdf PDF
RFPC30034902302355_Nov_25_24_solicitation_doc.pdf PDF
RFPC30034902302355_May_12_25_solicitation_doc.pdf PDF
RFPC30034902302355_Nov_11_24_solicitation_doc.pdf PDF
RFPC30034902302355_Apr_7_25_solicitation_doc.pdf PDF
RFPC30034902302355_Sep_9_24_solicitation_doc.pdf PDF
RFPC30034902302355_Oct_21_24_solicitation_doc.pdf PDF
RFPC30034902302355_Jan_20_25_solicitation_doc.pdf PDF
RFPC30034902302355_Apr_14_25_solicitation_doc.pdf PDF
RFPC30034902302355_Jun_23_25_solicitation_doc.pdf PDF
RFPC30034902302355_Jan_27_25_solicitation_doc.pdf PDF
RFPC30034902302355_Oct_28_24_solicitation_doc.pdf PDF
RFPC30034902302355_May_19_25_solicitation_doc.pdf PDF
RFPC30034902302355_Jan_13_25_solicitation_doc.pdf PDF
RFPC30034902302355_Mar_17_25_solicitation_doc.pdf PDF
RFPC30034902302355_Dec_2_24_solicitation_doc.pdf PDF
RFPC30034902302355_Oct_14_24_solicitation_doc.pdf PDF
RFPC30034902302355_Jun_9_25_solicitation_doc.pdf PDF
RFPC30034902302355_Feb_3_25_solicitation_doc.pdf PDF
RFPC30034902302355_Apr_28_25_solicitation_doc.pdf PDF
RFPC30034902302355_Aug_26_24_solicitation_doc.pdf PDF
RFPC30034902302355_Apr_21_25_solicitation_doc.pdf PDF
RFPC30034902302355_Jan_6_25_solicitation_doc.pdf PDF
solicitation_summary.pdf PDF
RFPC30034902302355_Dec_9_24_solicitation_doc.pdf PDF
RFPC30034902302355_Dec_30_24_solicitation_doc.pdf PDF
RFPC30034902302355_May_5_25_solicitation_doc.pdf PDF
RFPC30034902302355_Jun_2_25_solicitation_doc.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: RFPC30034902302355

Concrete for Johnson Shut-Ins State Park

Request for Proposal - Commodity (RFPC)

State of Missouri

May 25, 2023 - June 22, 2023

Page:2

General Header Information

RFPC30034902302355

No. RFPC30034902302355 Title: Concrete for Johnson Shut-Ins State Park Start Date: May 25, 2023 at 9:00:00 AM CDT End Date: June 22, 2023 at 2:00:00 PM CDT Vendor Q&A Start Date:

Vendor Q&A End Date:

Estimated Total Value:

Who can respond to this bid? : All Vendors Description:

Delivery Terms: Free On Board Destination Payment Terms: Net 45 Days Contact Information: State of Missouri

Jennie Rees Tel: 573-751-6442 jennie.rees@oa.mo.gov

Contact Details: If you have any questions, please contact:

Jennie Rees Tel: 573-751-6442 jennie.rees@oa.mo.gov

Selected Categories:

Page:3

Header Custom Fields:

RFPC30034902302355

NOTICE

Vendor Responsibility

The vendor is solely responsible for ensuring timely submission of their solicitation response. Failure to allow adequate time prior to the solicitation end date to complete and submit a response to a solicitation, particularly in the event technical support assistance is required, places the vendor and their response at risk of not being accepted on time.

The State of Missouri's Privacy Policy can be accessed here.

VENDOR'S INSTRUCTIONS

Submission of Bids Vendors should be aware there are exhibits attached to the documentation of the attached

IFB. Vendors should fill out and sign exhibit A and any others that apply. Vendors should attach the exhibits to their bid.

http://www.mo.gov/privacy-policy/

Page:4

Solicitation Requirements:

This bid has no questions defined.

RFPC30034902302355

REQUIREMENTS

Requirements:

To access the official solicitation document, which includes all applicable requirements, detailed specifications, and terms and conditions, the vendor must click on the Overview tab to view the solicitation. Under the Overview tab, the vendor must either: 1) print the solicitation document in order to submit a hard copy, if allowed by the solicitation, or 2) review and accept the solicitation documents under the Overview tab, and submit an electronic response to the solicitation through the MissouriBUYS system.

ATTACHMENT INSTRUCTIONS

Uploading Attachments Uploading Attachments To A Bid Response: The vendor is solely responsible for downloading and reviewing the complete solicitation document and, if any, all solicitation attachments. The vendor shall further understand and agree that in order for the state to be able to conduct a complete evaluation of the vendor's response, the vendor is strongly advised to attach and upload completed

RFP exhibits (e.g., Exhibit A through Exhibit F). Please be advised that Exhibits A and B are mandatory Exhibits that must be filled out and returned with the RFP response.

Page:5

Documents:

RFPC30034902302355 Concrete Johnson ShutIns State Park.docx

Attachment 2 Contract Compliance Required Documentation.pdf

Attachment 3 Federal Contract Provisions Federal Aid Construction Contracts.pdf

Page:6

Item Specifications

No. Item Alternative Supplier Part No Mfr.

Name

Mfr. No Del

Date

Unit Unit Bid Qty. Total

1 Ready Mix Concrete -

Standard Loads cubic yard

718.00

Additional Item Fields

1. State standard load size minimum cubic yards:(required):-

Item Specification for Ready Mix Concrete - Standard Loads

Description: C/S Code: 30110000 Concrete and cement and plaster Ready Mix Concrete – Standard Loads • 4000 PSI @ 28 days • Water-Cementitious Materials Ratio: .50 • Slump Limit: 4” for concrete with verified slump of 2-4” before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1” • Air Entrainment: 5 ½% (+/- 1 ½% at point of delivery for 1” nominal maximum aggregate size) • ASTM C 260 • Concrete Temperature: 1) Hot Weather: 90 Degrees F Maximum 2) Cold Weather: 50 Degrees F Minimum • Environmental and/or fuel charges must be included in the price per cubic yard of concrete. State standard load size minimum cubic yards: _______________

Allow Vendor to Enter Negative Value : No

Exclude Line Item from Bid Total : No

2 Ready Mix Concrete -

Short Loads cubic yard

718.00

Additional Item Fields

1. State short load size maximum cubic yards:(required):-

Item Specification for Ready Mix Concrete - Short Loads

Description: C/S Code: 30110000 Concrete and cement and plaster Ready Mix Concrete – Short Loads • 4000 PSI @ 28 days • Water-Cementitious Materials Ratio: .50 • Slump Limit: 4” for concrete with verified slump of 2-4” before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1” • Air Entrainment: 5 ½% (+/- 1 ½% at point of delivery for 1” nominal maximum aggregate size) • ASTM C 260 • Concrete Temperature: 1) Hot Weather: 90 Degrees F Maximum 2) Cold Weather: 50 Degrees F Minimum • Environmental and/or fuel charges must be included in the price per cubic yard of concrete. State short load size maximum cubic yards: ___________________

3 Water-Reducing Admixture cubic yard

350.00

Item Specification for Water-Reducing Admixture

Description: C/S Code: 12162305 Concrete Additive Water-Reducing Admixture • ASTM C 494/C 494M, Type A

4 Retarding Admixture cubic yard

350.00

Item Specification for Retarding Admixture

Description: C/S Code: 12162305 Concrete Additive Retarding Admixture • ASTM C 494/C 494M, Type B

5 Plasticizing Retarding

Admixture cubic yard

350.00

Item Specification for Plasticizing Retarding Admixture

Description: C/S Code: 12162305 Concrete Additive Plasticizing Retarding Admixture • ASTM C 1017/C 1017M, Type II

6 Polypropylene Fiber

Reinforcement cubic yard

350.00

Page:7

No. Item Alternative Supplier Part No Mfr.

Name

Mfr. No Del

Date

Unit Unit Bid Qty. Total

Item Specification for Polypropylene Fiber Reinforcement

Description: C/S Code: 12162305 Concrete Additive POLYPROPYLENE FIBER REINFORCEMENT Pounds per cubic yard: ________________________

7 Hot Water for Cold

Weather gallon 350.00

Item Specification for Hot Water for Cold Weather

Description: C/S Code: 12162305 Concrete Additive HOT WATER FOR COLD WEATHER

8 Iced or Cold Water for Hot

Weather gallon 350.00

Item Specification for Iced or Cold Water for Hot Weather

Description: C/S Code: 12162305 Concrete Additive ICED OR COLD WATER FOR HOT WEATHER