RFP937400-01 - Addendum #01.pdf

PDF 315 KB Posted

Attached to
CHMHI Gym Conditioning & Ceiling Repair
Solicitation number
RFP937400-01
Issued by
Cherokee County, Iowa

About this file

Addendum 1 for RFP937400-01 is issued by the State of Iowa Department of Administrative Services (DAS) for the HHS CHMHI Gym Ceiling Repair project. The addendum covers a pre-proposal meeting held on May 8, 2024, detailing the project scope which includes complete design for gym ceiling renovations and air conditioning installation at the Cherokee Mental Health Institution. The design services require evaluation of existing air conditioning units manufactured in 2011 and 2012, comprehensive design across electrical, mechanical, plumbing, and architectural disciplines, and ceiling plaster repairs. Key dates include proposal submissions due by May 21, 2024 at 2:00 PM, addendum issuance by May 17, 2024, designer selection on May 24, 2024, and a project timeline spanning design development through January 2025, with construction anticipated from August to December 2024.

The RFP requires a project-specific proposal including a detailed schedule, staff resumes, anticipated hours and rates, and a lump sum fee breakdown. DAS mandates a Professional Liability insurance policy of $2,000,000 with a $25,000 deductible and will use Procore for project management at no cost to the designer. The contract will be a modified ConsensusDocs 803 Form of Agreement. Notably, the air conditioning units were originally purchased to spend excess funds, and there are currently no known issues with them. The project will require coordination with state agencies, building code reviews, and development of hazardous materials identification documentation.

View the file

Other files

File Type Posted
RFP937400-01 - Addendum #01.pdf PDF
RFP937400-01 Final.pdf PDF
1229263-event.pdf PDF
RFP937400-01 Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: HHS CHMHI Gym Ceiling Repair

DAS RFP #: 937400-01

DAS Project #: 9374.00

Date: 5/10/2024

Addendum 1:

• Cover Page – Clarifications (1 Pages)

• Meeting Minutes & Sign-In (4 Pages)

1 CLARIFICATIONS

There are no known issues with the existing AC unit at this time.

State of Iowa - Department of Administrative Services 109 SE 13th St.

Des Moines, Iowa 50319 P: (515) 281-7260

Project: 9374.00 HHS CHMHI Gym Ceiling Repair 1251 W Cedar Loop

Cherokee, Iowa 51012 P: 712-225-2594

RFP Pre-Proposal Minutes: Meeting #1

Meeting Date May 8, 2024 Meeting Time 11:00 AM - 12:00 PM Central Time (US & Canada)

Meeting Location

Overview Meeting to allow prospective design firms to visit the project site, when possible, and learn more about the scope.

Notes

Attachments RFP937400-01 Final.pdf

Scheduled Attendees

Name Company Phone Number Email Attendance

Jeff Miller Cherokee Mental Health Institution jmiller2@dhs.state.ia.us Present

Jason Pigott Cherokee Mental Health Institution P: (712) 225-6949 jpigott@dhs.state.ia.us Absent

Travis Hoyle DCI Group P: (515) 244-5043 travish@dcigroup-us.com Present

Jennie Elliott State of Iowa - Department of Administrative Services jennie.elliott@iowa.gov Present

Introduction

No. Mtg Origin Title Assignment Due Date Priority Status

1.1 1 Introductions Open

Description Attendance

Official Documented Meeting Minutes Ed Matt - Genesis Jake Cunliffe - KCL Engineering Dan Strain - KPE Leslie Whitehill - KPE

Project Overview

2.1 1 Scope Review Open

Description Complete design for renovations including all design disciplines necessary to complete the scope of work below.

Anticipated scope of services:

See Exhibit B for an existing report conducted by Genisis Architecture, evaluating the plaster ceiling deterioration.

Evaluation of existing Owner provided air-conditioning unit and condensing unit for

State of Iowa - Department of Administrative Services Page 1 of 3 Printed On: May 10, 2024 10:10 AM CDT https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/42578/01HXA4SCJPWSQS85RSG1CMPZS3?sig=237abfcfea8e5a24c224a8aa97b270b730e3899a221f3c50193d27a35b9d3e47 use on this project. Units were manufactured in 2011 and 2012 but have never been installed. Model numbers are as follows and pictures can be found in Exhibit C.

Air Conditioner:

Thermal Zone Model Number TZHGL240ZL 208/230/460 Volts, 3-Phase, 60 Hertz

Condensing Unit:

Thermal Zone Model Number TZAL-240CA 208/230 Volts, 3-Phase, 60 Hertz

Design shall include all electrical, mechanical, plumbing, and controls installations.

Design shall include architectural and structural construction as needed to accommodate placement of air conditioning and condensing units.

Includes architectural modifications to interior and exterior walls as necessary for ducting and piping of units.

The existing ceiling plaster has begun to deteriorate. It is assumed this deterioration is due to lack of cooling and humidity control within the space. Design shall include repairs to ceiling plaster. See Exhibit B for existing report with recommendations.

Designer shall review the existing conditions and provide a recommendation based on best value.

Field examination of the existing buildings.

Design for scope of work. Provide material recommendations based on experience, quality, and price. Recommendations for replacements and upgrades shall include non-proprietary equipment and systems.

Provide minor drawing work to assist the Construction Manager in the development of hazardous materials bid package. This shall include providing PDF backgrounds for identification, by others, of hazardous materials removal.

Designer shall include any and all survey work required for completion of project.

Coordinate with State agencies to confirm utilities that may be abandoned as well as shut down requirements where required.

Provide detailed input of design schedule to Construction Manager for overall incorporation into master schedule.

Designer shall assist Construction Manager in the evaluation of long lead times.

Review with the Department of Inspections, Appeals, and Licensing’s (DIAL) Building Code Bureau for approval of plans or exemption from review. All fees associated with the Bureau are the responsibility of the designer.

Official Documented Meeting Minutes

• AC unit was bought to spend excess money, there are no known issues with it.

2.2 1 Schedule Review Open

Description

• Questions Due to construction.procurement@iowa.gov: by 2:00 PM on 5/9/24

• Addendum Issued: by 5/17/24

• Proposals Due: 5/21/24 at 2:00 pm

• Selection of Designer/Issue NOI: 5/24/24

Meeting #1 - RFP Pre-Proposal Project: 9374.00 HHS CHMHI Gym Ceiling Repair

State of Iowa - Department of Administrative Services Page 2 of 3 Printed On: May 10, 2024 10:10 AM CDT mailto:construction.procurement@iowa.gov:

• Execution of 803 Contract: Week of 6/3/24

• Tentative Design Kickoff Meeting: Week of 6/3/24

• 100% DD: TBD by design firm

• 50% CD and budget: TBD by design firm

• 95% CD: July 9th, 2024

• 100% CD and budget: July 23, 2024

• Contractor Bidding: July-August 2024

• Execution of Contractor's Contract(s): August 2024

• Submittals, Procurement and Construction: August 2024 - December 2024

• Closeout: January, 2025

RFP Overview

3.1 1 RFP Requirements Review Open

Description

• All questions to be directed to construction.procurement@iowa.gov

• Proposals must be submitted on the Iowa IMPACS Electronic Procurement System before 2:00 pm on 5/21/24.

Prospective companies are solely responsible for timely submission.

• DAS uses Procore online project management system for all projects, at no cost to the designer.

• DAS uses a modified ConsensusDocs 803 Form of Agreement

• DAS requires a project-specific Certificate of Insurance and specifies a Professional Liability policy of $2,000,000 with a deductible of $25,000 o Must note in proposal if deductible is different and provide a letter of financial stability from bank o Must provide COI prior to contract execution

• Ensure the following items are included in the proposal:

o Project-specific schedule o Resumes for all technical staff that will be assigned to the project o Anticipated hours and rates for each person on the design team o Lump sum broken down by schedule of values

Conclusion

4.1 1 Designer Questions Open

Description Any questions?

Official Documented Meeting Minutes

• There are not any existing drawings

Meeting #1 - RFP Pre-Proposal Project: 9374.00 HHS CHMHI Gym Ceiling Repair

These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.

Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.

State of Iowa - Department of Administrative Services Page 3 of 3 Printed On: May 10, 2024 10:10 AM CDT mailto:construction.procurement@iowa.gov

END OF ADDENDUM 1