RFP936800-01 Addendum #1.pdf

PDF 121 KB Posted

Attached to
IMHI Reynolds Bldg North Annex Roof Replacement
Solicitation number
RFP 936800-01
Issued by
Buchanan County, Iowa

About this file

This is an Addendum #1 to a Request for Proposal issued by the State of Iowa Department of Administrative Services for professional design services related to the Reynolds Building North Annex Roof Replacement project at the Independence Mental Health Institute. The addendum, dated February 29, 2024, clarifies key project coordination procedures and does not change the original proposal due date of March 6, 2024. The addendum confirms that a hazardous materials survey will be performed by an environmental consultant and can be coordinated with the consultant's kickoff meeting and initial field evaluation to verify roof assembly composition simultaneously. Additionally, the addendum confirms that DAS or the Construction Manager will contract with a roofing contractor to perform core cuts and patch them to ensure watertight conditions following the hazardous materials survey. The addendum also confirms that facility staff have a ladder available for the design consultant to access the lower north roof area during site evaluations.

The addendum supersedes and supplements any conflicting portions of the original Request for Proposal documents. Acknowledging receipt of this addendum in the proposal submission is mandatory, and failure to do so may result in disqualification. The addendum does not address pricing terms, set-asides, incumbents, or funding sources, as these matters are addressed in the primary RFP documents and related contract opportunity materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #1

Project Name:

HHS IMHI Reynolds Bldg North Annex Roof Replacement

DAS#9368.00

RFP936800-01

Addendum #1

Dated: February 29, 2024

This Addendum forms a part of the Request For Proposal documents. This Addendum supersedes and supplements all portions of the original Request For Proposal for which it conflicts.

ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE REQUEST FOR PROPOSAL. FAILURE TO

DO SO MAY SUBJECT TO DISQUALIFICATION.

1. Proposal Schedule – Proposal due date does not change.

2. Questions:

a. Q. Assume a hazardous materials survey will be performed by an environmental consultant. Can the hazardous materials survey be coordinated with the consultant’s kickoff meeting/initial field evaluation so consultant can verify roof assembly composition during the same time? A. Yes, we can work with the environmental consultant and the design team awarded the project to verify the roof assembly composition.

b. Q. Assume DAS/Construction Manager will also employ a roofing contractor to do core cuts and patch the cuts to be watertight after the hazardous materials survey? A. Yes, a roofing contractor will be contracted to patch any core cuts or patch cuts at the time of the survey.

c. Does the facility staff have a ladder that consultant can use to access the lower north roof area? A.

Yes, the facility does have a ladder that the design consultant can use to access the lower roof area.

Attachments: NONE

END OF ADDENDUM