RFP936100-01 MPCF Building 20 (MWU) Elevator Replacement.pdf
PDF 95 KB Posted
- Attached to
- DOC MPCF Building 20 (MWU) Elevator Replacement
- Solicitation number
- RFP936100-01
- Issued by
- Henry County, Iowa
About this file
This document is a Request for Proposals (RFP) issued by the Iowa Department of Administrative Services (DAS) seeking professional design services for a project to remove and replace the (MWU) Elevator "A" in building 20 at the Mount Pleasant Correctional Facility (MPCF) in Mount Pleasant, Iowa. The scope of work includes all necessary design disciplines, field examinations, design review meetings, construction cost opinions, construction drawings and specifications, bid assistance, and construction administration services. The RFP provides a detailed project schedule, with design milestones and a tentative construction timeline from April 2024 to June 2024. A pre-proposal conference is scheduled for November 2, 2023, and proposals are due by November 21, 2023. The contract will be a modified ConsensusDoc 803 agreement, and the Department is seeking lump sum pricing broken down by design phase.
The Department requests that respondents provide pricing for the design development documents, construction documents, bidding/negotiation assistance, and construction phase services, including a unit price for additional construction site visits beyond the nine specified in the RFP. Respondents must guarantee that all proposal terms, including price, will remain firm for a minimum of 120 days following the proposal submission deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF IOWA
REQUEST FOR PROPOSALS
PROFESSIONAL DESIGN SERVICES
RFP COVER SHEET
Administrative Information
RFP Number RFP936100-01 Title of RFP DOC MPCF Building 20 (MWU) Elevator Replacement
Agency Iowa Department of Administrative Services (DAS)
Project
Description
The State of Iowa Department of Administrative Services (DAS) is seeking professional design services from qualified firms for a project consisting of removal and replacement of the (MWU) Elevator “A” in building 20 at the MPCF in Mount Pleasant, Iowa.
State Issuing Officer:
Michael Bradbury
Issuing Officer
Iowa Department of Administrative Services
Hoover State Office Building, Level 3
1305 East Walnut, Des Moines, IA 50319-0105 Phone: 515-823-9327
Email: construction.procurement@iowa.gov
PROCUREMENT TIMETABLE—Event or Action Date/Time (Central Time)
State Posts Notice of RFP on TSB website October 18, 2023
State Issues RFP October 20, 2023
Pre-Proposal Conference Location and Address: MPCF, 1200 East Washington Street, Mt. Pleasant, IA 52641
Is Pre-Proposal Conference mandatory? No
If a map is needed, contact the Issuing Officer.
Thursday, 11-2-23 @ 10:00 am
Questions, requests for clarification, and suggested changes from Respondents due to Construction Procurement
11-7-23 by 2:00 pm
Proposals Due 11-21-23 by 2:00 pm
Relevant Websites
Website where Addenda to this RFP will be posted http://bidopportunities.iowa.gov
Website where contract terms and conditions are posted https://das.iowa.gov/sites/default/files/procurement/pdf/ConsensusDoc803.pdf
Number of Copies of Proposals Required to be Submitted: 1 Digital
Firm Proposal Terms
The minimum number of days following the deadline for submitting Proposals that the firm guarantees all proposal terms, including price, will remain firm is 120 Days.
1.2 SCHEDULE
DAS is seeking a firm that can commence work upon execution of a contract. Time is of the essence.
Execution of Designer’s Contract Week of November 27, 2023
Tentative Design Kick-Off Meeting Week of December 4, 2023
100% Design Development Documents and Cost Opinion By January 11, 2024
50% Construction Documents and Cost Opinion By February 1, 2024
95% Construction Documents and Cost Opinion By February 15, 2024
100% Construction Documents and Cost Opinion By February 22, 2024
Contractor Bidding February / March 2024
Execution of Contractor’s Contract(s) Week of March 25, 2024
Submittals, Procurement and Construction April 2024 to June 2024
Close out July 2024
1.3 PROJECT DESCRIPTION
Construction Manager (The Samuels Group) has been engaged for this Project to serve as advisor to DAS and to provide assistance in administrating the Contract for Design between DAS and the
Designer according to separate contract between DAS and Construction Manager. DAS is currently seeking proposals from qualified firms for a project consisting of removal and replacement of the
(MWU) Elevator “A” in building 20 at the MPCF in Mount Pleasant, Iowa.
Design services shall include:
1.3.1 The contract for this work will be a modified ConsensusDoc 803. See link on cover page for a sample contract.
1.3.2 All design disciplines necessary to complete the scope of work.
1.3.3 Attend design kick-off meeting onsite to discuss desired outcome of the project with the
Owner, Construction Manager, and Owner’s maintenance staff.
1.3.4 Use of the State of Iowa‘s construction management software program for uploading all documents, submitting and approving pay apps, and construction administration. The cost for the use of the software is paid by the Owner
1.3.5 Collecting and providing meeting minutes from the design meetings.
1.3.6 Existing CAD/PDF floor plans of the overall building can be provided to the successful design firm. Accuracy of drawings shall be verified by the design firm.
1.3.7 Field examination of the existing building.
1.3.8 Design for scope of work. Provide material recommendation based on experience, quality and price. Recommendations for replacements and upgrades shall include non-proprietary equipment and systems. Review the following items (Pit, Shaft, Fire protection, Penthouse, mechanical, electrical) Not limited to the list above.
1.3.9 Provide minor drawing work to assist the Construction Manager in the development of hazardous materials bid package. This shall include providing PDF backgrounds for identification, by others, of hazardous materials removal.
1.3.10 Designer shall include any and all survey work required for completion of project.
1.3.11 Coordinate with State agencies to confirm utilities that may be abandoned as well as shut down requirements where required.
1.3.12 Provide detailed input of design schedule to Construction Manager for overall incorporation into master schedule.
1.3.13 Designer shall assist Construction Manager in the evaluation of long lead times.
1.3.14 Quality control during Design, Preconstruction and Construction.
1.3.15 Compliance with all Federal, State, and applicable Local codes.
1.3.16 Completion of State building and energy code documents, as required.
1.3.17 Design review will be conducted at 100% design development documents, 50% construction documents, and 95% construction documents. Review will be conducted with DAS Owner Representative, Construction Manager, and Facility Representative, at a minimum. Drawings, specifications, and cost opinions shall be provided at least five days prior to each review meeting. An additional review meeting may be required at the end if there are discrepancies in cost opinions or constructability review questions.
1.3.18 Review with the State Fire Marshal’s office for approval of plans or exemption from review. All fees associated with the State Fire Marshal’s office are the responsibility of the designer.
1.3.19 Develop and distribute agendas and meeting minutes for all meetings during the Design phase.
1.3.20 Designer shall provide any information necessary to obtain utility rebates where applicable.
1.3.21 Construction cost opinions provided by the Design Professional team during Design (100% design development documents, 50% construction documents, and 95% construction documents) with a Final Estimate for construction included with bid documents, per Iowa
Code.
1.3.22 Construction drawings, specifications (the Construction Manager will produce Divisions 00 and 01), and addenda.
1.3.23 Provide bid alternates as determined during the course of design and bid package development.
1.3.24 Assist Owner and Construction Manager in obtaining bids from qualified contractors.
1.3.25 Construction administration, including creation of the submittal and closeout items log, review of and responses to submittals and closeout documentation, RFIs, proposal requests, change orders, pay applications, periodic site visits, attendance at project meetings as required, participation / development of contractor punch list, closeout documentation review and approval, certificates of substantial completion, and certificates of final completion, as well as development of Architectural Supplemental
Instructions for design revisions, and punch lists within the construction management software program.
1.3.26 Participation with project team during construction progress meetings as required.
Designer shall participate in bi-weekly conference calls during the construction period.
1.3.27 Field Observation reports, with photos, submitted for each site inspection within five (5) days of the site visit.
1.3.28 Acknowledgement that all documents are copyright to the State of Iowa and shall be turned over to the State of Iowa in their native computer format. Any ASIs/RFIs/PRs and addendums will be expected to be incorporated before final posting. Both the native computer format and PDF versions shall be uploaded to the construction management software program at the end of the project.
1.3.29 The Department requests lump sum pricing from the respondents to this RFP, with the lump sum base scope price being inclusive of all reimbursables, such as printing, mileage and travel expenses. The Department requests the fee proposal from the respondents to this RFP be broken down as follows. These breakdown prices will be used as the schedule of values for billing purposes.
1.3.29.1 Design Development Documents
1.3.29.2 Construction Documents
1.3.29.3 Bidding or Negotiation Assistance
1.3.29.4 Construction Phase
Include at a minimum, nine (9) site visits. Design kick off, 100% design development document review meeting, 50% document review, Pre-bid meeting, Construction Field
Observation (2), Substantial completion/punch list development, Punch list/Final
Completion approval, and one year warranty correction period visit. Design Review at
95% construction document development will be conducted via conference call. Beyond these site visits, each proposing firm shall provide additional visits as they see fit to complete the work of design. In addition to the lump sum pricing, the Department requests a unit price per construction inspection visit. This unit price will be additive or deductive based on the number of actual visits made.