Attachment C, WFIRST-MECH-LIST-0078-.pdf
PDF 434 KB Posted
- Attached to
- High Gain Antenna System (HGAS) Jitter Damper for the Wide Field Infrared Survey Telescope (WFIRST) Project
- Solicitation number
- RFP-80GSFC20R0027
About this file
This deliverable items list and schedule (DILS) outlines 44 deliverables required under a contract for a High Gain Antenna System (HGAS) Jitter Damper for the Wide Field Infrared Survey Telescope (WFIRST) project. The National Aeronautics and Space Administration Goddard Space Flight Center is seeking these deliverables on dates ranging from within two weeks of contract award to 12 months after award. Required deliverables include design documents, analysis reports, verification plans and reports, configuration management plans and changes, quality assurance documentation, product data packages, and the flight unit hardware. The contractor must also host various project reviews at designated times.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: February 11, 2020
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
WFIRST-MECH-LIST-0078, Revision -
Wide Field Infrared Survey Telescope (WFIRST), Code 448
High Gain Antenna System (HGAS)
Jitter Damper
Deliverable Items List and Schedule
(DILS)
GSFC WFIRST CMO
February 13, 2020
Released
HGAS Jitter Damper DILS WFIRST-MECH-LIST-0078, Revision -ii
HGAS Jitter Damper
Deliverable Items List and Schedule
(DILS)
Review/Signature/Approval Page
Prepared by:
Lia Sacks
Approved by:
Jason Hylan
Electronic Approval available on-line in the WFIRST CM Tool iii
Preface
This document is a Wide Field Infrared Survey Telescope (WFIRST)
Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee.
Proposed changes shall be submitted to the WFIRST CM Office (CMO), along with supportive material justifying the proposed change.
In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will,” and descriptive material by “is.”
Questions or comments concerning this document should be addressed to:
WFIRST Configuration Management Office
Mail Stop 448
Goddard Space Flight Center
Greenbelt, Maryland 20771 iv
Change History Log
Revision Effective Date Description of Changes
(Reference the CCR & CCB/ERB Approval Date)
Revision - February 11, Initial Release per WFIRST-CCR-0153 v
Table of TBDs/TBRs/TBSs [optional]
Item No. Location Summary Individual/
Organization
Actionee
Due Date vi
Table of Contents
1 INTRODUCTION
1.1 Purpose
1.2 Scope
1.3 Related Documentation
1.3.1 Applicable Documents [and Forms]
1.3.2 Reference Documents
2 DELIVERABLES
APPENDIX A ABBREVIATIONS AND ACRONYMS
List of Tables
Table 1. Data Delivery Documentation and Schedule
1 INTRODUCTION
1.1 Purpose
The Wide Field InfraRed Survey Telescope (WFIRST) is a mission responding to the 2010
National Research Council New Worlds, New Horizons (NWNH) Astronomy and Astrophysics
Decadal Survey top priority recommendation in the large space mission category. The science program includes two dedicated investigations to tackle outstanding questions in dark energy research and exoplanet exploration, and includes a substantial General Observer program to enable targeted investigations of astrophysical phenomena to advance other goals from the
Decadal Survey. A coronagraph instrument is included in the payload for purposes of advancing the present state of the art of coronagraph technology. This document is the Wide Field Infrared
Survey Telescope (WFIRST) High Gain Antenna System (HGAS) jitter damper Deliverable
Items List and Schedule (DILS).
1.2 Scope
This document lists all of the deliverables for HGAS jitter damper, the SOW paragraph number where the deliverable is described further, the type of response required from NASA GSFC, the format of the deliverable, and the schedule for delivery.
1.3 Related Documentation
The latest versions of all documents below should be used. WFIRST documents can be obtained in the WFIRST CM Tool.
1.3.1 Applicable Documents [and Forms]
The following documents are referenced within this document and are directly applicable or contain policies or other directive matters that are binding for the contents of this document. In the event of conflict between an Applicable Document and the content of this document, the
WFIRST Project Configuration Change Board has the final authority for conflict resolution.
Document Number Title
WFIRST-MECH-SOW-
WFIRST High Gain Antenna System Jitter Damper Statement of
Work (SOW)
1.3.2 Reference Documents
The following documents are referenced herein and amplify or clarify the information presented in this document. These documents are not binding on the content of this document.
Document Number Title
WFIRST-MECH-
SPEC-0128
WFIRST High Gain Antenna System Jitter Damper Specification
MICD-2237261 Jitter Damper, HGAS Mechanical Interface Control Document
(MICD)
2 DELIVERABLES
Description: This provides the Title of the deliverable item.
Reference: This provides the reference back to the pertinent document calling out the deliverable.
Category:
A = Approval – Items in this category require approval from the National Aeronautics and Space Administration (NASA)/Goddard Space Flight Center (GSFC) Contracting
Officer (CO). In general, documents shall be provided in contractor format as long as required content, as specified in the Wide Field Infrared Survey Telescope (WFIRST)
HGAS Jitter Damper Statement of Work (WFIRST-MECH-SOW-0036), is addressed.
The NASA GSFC CO reserves the time-limited right of disapproval for each submission.
The time-limited period is 30 working days from receipt of documents.
R= Review – Items in this category do not require formal NASA GSFC CO approval, but will be reviewed by the GSFC or its designated representatives in order to determine contractor effectiveness in meeting contract objectives. When Government review reveals inadequacies, the contractor may be requested to correct the inadequacies. GSFC will review and comment within 20 working days of receipt.
I = Information – Items in this category are informal and are for information only.
Format: This provides the format for the deliverable. For documents, the following format applies:
E = Electronic – Provide submittal in electronic format to the COR, and Contracting
Officer. The vendor and COR shall jointly determine the type of electronic format (e.g., Word, Excel, PowerPoint, PDF, MATLAB) acceptable for each deliverable.
Table 1. Data Delivery Documentation and Schedule
Item
Description Reference Category Category/Format
1 SOW Compliance Matrix SOW 1.2 With Proposal Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
2 Monthly Status Report SOW 2.2 Fourteen (14) calendar days following the month being reported.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
For Information Purposes.
3 Milestone List SOW 2.2 With Proposal
4 Notifications SOW 2.3 Seven (7) calendar days in advance of all mandatory hardware inspections, test activities, TIM’s, and deliveries.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
5 Kick Off Meeting SOW 2.4.1 Fourteen (14) calendar days after contract award
In person at Contractor
Facility.
Review Required.
6 Kick Off Meeting Presentation
Package
SOW 2.4.1 Three (3) working days before the meeting
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required
7 Design Conformance Review
(DCR)
SOW 2.4.2 Three (3) months after
Award of Contract
In person at Contractor
Facility.
Review Required.
8 Design Conformance Review
Presentation Package
SOW 2.4.2 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
9 Design Conformance Review
Report
SOW 2.4.2 Fourteen (14) calendar days after completion of DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
10 Pre-Environmental Review
(PER)
SOW 2.4.3 Seven (7) calendar days before start of environmental testing on first Flight Unit
In person at Contractor
Facility.
Review Required.
Description Reference Category Category/Format
11 Pre-Environmental Review
Presentation Package
SOW 2.4.3 At PER Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
12 Flight Unit(s) Pre-Ship
Review (PSR)
SOW 2.4.4 Seven (7) calendar days prior to delivery of each
Flight Unit
In person at Contractor
Facility.
Approval Required.
13 Flight Unit(s) Pre-Ship
Review Presentation Package
SOW 2.4.4 At PSR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
14 Flight Unit(s) End Item Data
Package(s) (EIDP)
SOW
2.4.4, 6.7.3, 6.7.6, 6.8.2
With each delivered Flight
Unit and available at PSR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
15 TIM SOW 2.4.5 As Negotiated In person at Contractor
Facility.
Review Required.
16 Interface Control Document(s) SOW 3.1 Preliminary at Kick-off
Meeting
Final at fourteen (14) calendar days before
DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
17 Drawing Package SOW 3.2 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
18 Computer Models SOW 3.3 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
For Information Purposes.
19 Structural Analysis Report SOW 3.4 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
20 Structural Finite Element
Model
SOW 3.5 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Description Reference Category Category/Format
And Fourteen (14) calendar days before PSR Review Required.
21 Thermal Analysis Report SOW 3.6 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
22 Thermal Model &
Documentation
SOW 3.7 Fourteen (14) calendar days before DCR
And Fourteen (14) calendar days before PSR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
24 Error Analysis Report SOW 3.9 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
27 Reserved
28 Verification Plan (Including
Verification Matrix)
SOW 5.1,
6.5.1
Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
29 Individual Verification Test
Plan(s) (if needed)
SOW 5.1 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
30 Verification Test Procedure(s) SOW 5.2 Twenty-eight (28) calendar days before start of testing and as changes occur.
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
31 Verification Test Report(s) SOW 5.3 At PSR Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
32 Mission Assurance
Implementation Plan / Quality
Assurance Plan
SOW 6.1 Twenty-eight (28) calendar days after contract award
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
33 Class I Configuration
Management (CM) Changes
SOW 6.2 Seven (7) calendar days after Contractor CM review
Electronic – Provide submittal in electronic format to the COR and
Description Reference Category Category/Format
Contracting Officer.
Approval Required.
34 Class II CM Changes SOW 6.2 Seven (7) calendar days after Contractor CM review
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
See
As-Built MIUL (Materials
Identification and Usage List)
SOW 6.7.3 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
38 Materials Usage Agreement SOW 6.7.4 Fourteen (14) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
See
Materials Certificate of
Compliance
SOW 6.8.6 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
39 Additive Manufacturing &
Qualification Plan SOW
6.7.5.2.2
Thirty (30) calendar days before hardware fabrication
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
40 Fastener Integrity Control
Plan SOW
6.7.5.4.1
Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
41 List of Critical Fasteners
SOW
6.7.5.4.1
Thirty (30) calendar days before DCR
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
See
Cleanliness Certification
Report
SOW 6.8.2 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Review Required.
42 Thermal Vacuum Bakeout
Plan
SOW 6.8.3 Twenty-eight (28) calendar days prior to beginning of
Thermal Vacuum Bakeout
Tests
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
Description Reference Category Category/Format
43 Thermal Vacuum Bakeout
Test Results (if not part of
Thermal Vacuum Report)
SOW 6.8.3 Fourteen (14) calendar days after completion of Thermal
Vacuum Bakeout Tests
Electronic – Provide submittal in electronic format to the COR and
Contracting Officer.
Approval Required.
44 HGAS Jitter Damper Flight
Unit(s)
Qty: 1
SOW 4.2 12 months after contract award (ACA)
As specified in Clause
GSFC 52.247-94
Approval Required.
45 Optional HGAS Jitter Damper
Flight Unit(s)
Qty: 1
SOW 4.2 12 months after contract award (ACA)
Deadline to exercise is 1 month after contract award
(ACA)
As specified in Clause
GSFC 52.247-94
Approval Required.
Appendix A Abbreviations and Acronyms
Abbreviation/
Acronym
DEFINITION
HGAS Jitter
Damper
High Gain Antenna System Jitter Damper
ACA After contract award
CIR Configuration Initial Release
CCB Configuration Control Board
CCR Configuration Change Request
CM Configuration Management
CMO Configuration Management Office
CO Contracting Officer
COR Contracting Officer's Representative
DCR Design Conformance Review
DILS Deliverable Items List and Schedule
EEE Electrical, Electronic, and Electromechanical
EIDP End Item Data Package(s)
FMEA Failure Modes and Effects Analysis
FMECA Failure Modes and Effects Criticality Analysis
GIDEP Government Industry Data Exchange Program
GSE Ground Support Equipment
GSFC Goddard Space Flight Center
I Information
INST Instrument
NASA National Aeronautics and Space Administration
NDE Nondestructive Evaluation
PDL Product Design Lead
PEM Plastic Encapsulated Microcircuit
PER Pre-Environmental Review
PSR Pre-Ship Review
PWB Printed Wiring Board
R Review
SOW Statement of Work
TBD To Be Determined
TBR To Be Resolved
TIM Technical Interchange Meeting
WFIRST Wide Field Infrared Survey Telescope
Yrs years
File details come from the government source that posted it. Updated .