RFP S-69000-00011548.pdf

PDF 1 MB Posted

Attached to
Lower Umatilla Basin Groundwater Management Area Project
Solicitation number
S-69000-00011548
Issued by
Multnomah County, Oregon

About this file

This document is a Request for Proposals (RFP) issued by the Oregon Water Resources Department (OWRD) for the Lower Umatilla Basin Groundwater Management Area Well Sampling Project. The purpose of the project is to collect data to better understand the occurrence of nitrate contamination throughout the aquifers of the Lower Umatilla Basin Groundwater Management Area. The RFP seeks proposals from licensed pump installation specialty contractors, water supply constructors, or monitoring well constructors to remove pumps from approximately 20 domestic wells, allow OWRD staff to perform geophysical surveys, and then reinstall the pumps. Proposals are due by October 14, 2024, and the initial contract term is anticipated to end on June 30, 2025 upon completion of the project.

The RFP outlines the minimum qualifications, submission requirements, and proposal format for responding to the solicitation. It also details the solicitation process, including public notice, question submission, proposal delivery, evaluation criteria, and award notification. The successful proposer must be licensed and in good standing in the state of Oregon to operate a pump services or well construction business. Payment terms and pricing structure requirements are specified, and the state encourages participation from certified small businesses, including disadvantaged, minority-owned, women-owned, service-disabled veteran-owned, and emerging small businesses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DAS Procurement Services, Version 4.5 March 31, 2023 Page 1 of 17

STATE OF OREGON

COVER PAGE

OREGON WATER RESOURCES DEPARTMENT

Is issuing this Request For Proposals (RFP) under OregonBuys Bid Number S-69000-00011548 for

LOWER UMATILLA BASIN GROUNDWATER MANAGEMENT AREA WELL

SAMPLING PROJECT

Date of Issue: September 18th, 2024

Opening Date and Time: October 14th, 2024 @ 5:00 PM

Single Point of Contact (SPC): Robin Ramsey, Procurement and Contract Specialist

Address: 725 Summer Street NE, Suite A City, State ZIP: Salem, OR 97301 Phone: (971) 375-8850 Email: robin.v.ramsey@water.oregon.gov

The State of Oregon promotes the equal opportunity for all individuals without regard to age, color, disability, marital status, na�onal origin, race, religion or creed, sex or gender, sexual orienta�on, or veteran status.

mailto:robin.v.ramsey@water.oregon.gov

DAS Procurement Services, Version 4.5 March 31, 2023 Page 2 of 17

Table of Contents

SECTION 1: GENERAL INFORMATION

1.1 INTRODUCTION

1.2 SCHEDULE

1.3 SINGLE POINT OF CONTACT (SPC)

SECTION 2: AUTHORITY AND METHOD

2.1 AUTHORITY AND METHOD

2.2 DEFINITION OF TERMS

2.3 OVERVIEW AND PURPOSE

2.4 SCOPE OF WORK/SPECIFICATIONS

2.5 PROJECT DETAILS

SECTION 3: PROCUREMENT REQUIREMENTS

3.1 MINIMUM QUALIFICATIONS

3.2 MINIMUM SUBMISSION REQUIREMENTS

3.3 PROPOSAL REQUIREMENTS

SECTION 4: SOLICITATION PROCESS

4.1 PUBLIC NOTICE

4.2 PRE-PROPOSAL CONFERENCE

4.3 QUESTIONS / REQUESTS FOR CLARIFICATIONS

4.4 SOLICITATION PROTESTS

4.5 PROPOSAL DELIVERY OPTIONS

4.6 PROPOSAL MODIFICATION OR WITHDRAWAL

4.7 PROPOSAL DUE

4.8 PUBLIC OPENING

4.9 PROPOSAL REJECTION

4.10 EVALUATION PROCESS

4.11 POINT AND SCORE CALCULATIONS

4.12 RANKING OF PROPOSERS

4.13 ADDITIONAL ROUNDS

SECTION 5: AWARD AND NEGOTIATION

5.1 AWARD NOTIFICATION PROCESS

5.2 INTENT TO AWARD PROTEST

5.3 APPARENT SUCCESSFUL PROPOSER SUBMISSION REQUIREMENTS

5.4 CONTRACT NEGOTIATION

SECTION 6: ADDITIONAL INFORMATION

6.1 COMMITMENT TO DIVERSITY, EQUITY, INCLUSION

6.2 CERTIFIED FIRM PARTICIPATION

6.3 GOVERNING LAWS AND REGULATIONS

6.4 OWNERSHIP/PERMISSION TO USE MATERIALS

6.5 CANCELLATION OF RFP; REJECTION OF PROPOSAL; NO DAMAGES

6.6 COST OF SUBMITTING A PROPOSAL

6.7 STATEWIDE E-WASTE/RECOVERY PROCEDURE

6.8 RECYCLABLE PRODUCTS

6.9 CHECKLIST DISCLAIMER

DAS Procurement Services, Version 4.5 March 31, 2023 Page 3 of 17

LIST OF ATTACHMENTS

ATTACHMENT A SAMPLE CONTRACT/PRICE AGREEMENT

ATTACHMENT B DISCLOSURE EXEMPTION AFFIDAVIT

ATTACHMENT C PROPOSER INFORMATION AND CERTIFICATION SHEET

ATTACHMENT D REFERENCE CHECK FORM

ATTACHMENT E PRICE PROPOSAL FORM – provided by Proposer

ATTACHMENT F COBID CERTIFICATION / OUTREACH PLAN

ATTACHMENT G RESPONSIBILITY INQUIRY

DAS Procurement Services, Version 4.5 March 31, 2023 Page 4 of 17

The State of Oregon, ac�ng by and through the Oregon Water Resources Department, (“Agency”), is issuing this Request for Proposal under the provisions of ORS 279B.060 for the removal and replacement of pumps.

The Oregon Water Resources Department (OWRD) is charged with carrying out the water management policies and rules set by the Water Resources Commission and with overseeing the enforcement of Oregon’s water laws.

The OWRD is organized into five divisions: Field Services, Technical Services, Water Rights and Adjudica�ons, Director’s Office, and Administra�ve Services. OWRD headquarters and the Northwest Regional Office are in Salem, Oregon. The OWRD also has four other regional offices and 20 small field offices throughout Oregon.

Agency an�cipates the award of 1 Contract from this RFP.

The ini�al term of the Contract is an�cipated to is an�cipated to end June 30, 2025 upon the comple�on of this Project.

The table below represents a tenta�ve schedule of events. All �mes are listed in Pacific Time. All dates listed are subject to change. N/A denotes that event is not applicable to this RFP.

Event Date Time

Pre-Proposal Conference Not Offered

Ques�ons / Requests for Clarifica�on Due September 25th, 2024 5:00 PM

Answers to Ques�ons / Requests for Clarifica�on Issued (approx.) September 30th, 2024

RFP Protest Period Ends 7 calendar days prior to RFP Opening

Opening (Proposal Due) October 14th, 2024 @ 5:00 PM

Opening of Proposal October 15th, 2024 8:00 AM

Issuance of No�ce of Intent to Award (approx.) October 22nd, 2024

Award Protest Period Ends 7 calendar days a�er No�ce of Intent to Award

The SPC for this RFP is iden�fied on the Cover Page, along with the SPC’s contact informa�on. Proposer shall direct all communica�ons related to any provision of the RFP only to the SPC, whether about the technical requirements of the RFP, contractual requirements, the RFP process, or any other provision.

Agency is issuing this solicita�on pursuant to its authority under ORS 279A.050 and ORS 279A.140.

Agency is using the Intermediate Procurement Solicita�on method set forth in ORS 279B.070 and OAR 125-247-0260.

Agency may use a combina�on of the methods for Compe��ve Sealed Proposals, including op�onal procedures: a) Compe��ve Range; b) Discussions and Revised Proposals; c) Revised Rounds of Nego�a�ons; d) Nego�a�ons; e) Best and Final Offers; and f) Mul�step Sealed Proposals.

For the purposes of this Solicita�on, capitalized words will refer to the following defini�ons.

Capitalized terms not specifically defined in this document are defined in OAR 125-246-0110.

https://oregon.public.law/statutes/ors_537.515 https://oregon.public.law/statutes/ors_279A.050 https://oregon.public.law/statutes/ors_279A.140 https://oregon.public.law/statutes/ors_279b.070 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=309618 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=300204

DAS Procurement Services, Version 4.5 March 31, 2023 Page 5 of 17

Terminology specific to the OregonBuys system may be found at OregonBuys.

The Oregon Water Resources Department (OWRD) is charged with carrying out the water management policies and rules set by the Water Resources Commission and with overseeing the enforcement of Oregon’s water laws.

The OWRD is organized into five divisions: Field Services, Technical Services, Water Rights and Adjudica�ons, Director’s Office, and Administra�ve Services. OWRD headquarters and the Northwest Regional Office are in Salem, Oregon. The OWRD also has four other regional offices and 20 small field offices throughout Oregon.

The Field Services and Technical Services Divisions manage and administer the gage sta�on opera�ons and maintenance. The OWRD operates and maintains over 250 gaging sta�ons across the state.

The Oregon Department of Environmental Quality established the Lower Uma�lla Basin Groundwater Management Area (LUBGWMA) in 1990, in accordance with the Oregon Groundwater Quality Protec�on Act (ORS 468B.150-190) as a result of elevated regional nitrate-nitrogen concentra�ons in groundwater within the Lower Uma�lla Basin in Morrow and Uma�lla Coun�es (see Figure 1).

The purpose of this project is to collect data to beter understand the occurrence of nitrate contamina�on throughout the aquifers of the LUBGWMA. At present, there is uncertainty about the loca�on and degree of nitrate contamina�on in the shallow sedimentary aquifer system and underlying basalt aquifers of the LUBGWMA. While thousands of nitrate samples have been collected and analyzed as part of Oregon Health Authority’s (OHA) effort to address the public health crisis, many of the wells sampled cannot be confidently associated with specific aquifers because the wells do not have original well logs detailing well construc�on and lithology. This project will address that knowledge gap by performing geophysical surveys at approximately twenty (20) wells in key loca�ons across the LUBGWMA.

The LUBGWMA Well Sampling Project (Project) includes the removal of pumps from a group of domes�c wells by an Oregon-Licensed well driller or pump installer licensed by the Construc�on Contractors Board (Pump Contractor) contracted to OWRD. All work shall be conducted according to established, professional pump installa�on standards and in accordance with applicable OARs and ORSs. The Pump Contractor shall conduct work in a manner that priori�zes the health and safety of all site personnel. Should these guidelines and/or health and safety concerns conflict with elements of this technical specifica�on, the Pump Contractor shall request clarifica�on from OWRD before proceeding.

A subset of approximately 20 wells within the LUBGWMA will be iden�fied for the Project. The Project consists of the Pump Contractor removing pumps from wells, OWRD staff performing a geophysical survey, and the Pump Contractor reinstalling the pump to the same specifica�ons as originally installed.

The Project must be completed before June 30, 2025. Contractors shall iden�fy their an�cipated mobiliza�on date and job dura�on in their Proposal. OWRD staff will frequently be present onsite during the dura�on of the project and will work with the Pump Contractor to schedule a mutually acceptable schedule.

OWRD staff will coordinate directly with the property owners for each well to determine schedule and other specifica�ons. OWRD will be the primary point of contact with the well owner. Contact informa�on will be provided to the Pump Contractor as needed to coordinate work and site access. The Project sites will be proper�es with wells throughout the LUBGWMA. Wells selected for this project are not located inside of buildings and will have immediately adjacent truck / equipment access.

https://www.oregon.gov/das/ORBuys/Pages/Index.aspx https://oregon.public.law/statutes/ors_468B.150 https://oregon.public.law/statutes/ors_468B.190

DAS Procurement Services, Version 4.5 March 31, 2023 Page 6 of 17

There is no guaranteed access to u�li�es on each site (water, power, restrooms, etc.). The Pump Contractor will be responsible for providing all suppor�ng Services and supplies required to complete the project Scope and will remove all unused and waste materials from the site a�er comple�on of the work.

The Pump Contractor will make all reasonable efforts to minimize impact to the landscape by contractor’s equipment, including use of mats or plywood. At the comple�on of the work, the ground surface surrounding the well will be returned to a state substan�ally similar to that present before mobiliza�on to the site.

The Pump Contractor will employ an effec�ve and efficient approach to pump removal. The pump and associated components will be stored in a sanitary manner, once removed from the well.

While the pump is removed from the well, OWRD will perform a geophysical survey with OWRD equipment.

These tests may have a dura�on up to 10 hours. The Pump Contractor is not required to be onsite during the geophysical survey.

Once the geophysical survey is complete, the Pump Contractor will replace the pump to the same specifica�ons as originally installed. At the property owners’ request, the Pump Contractor may perform any requested repairs or maintenance on the pumps while removed from the well, provided such work does not interfere with the Project schedule or outcomes. Any addi�onal pump maintenance or repair work performed will be at the cost of the well owner. Details of any addi�onal pump work will be coordinated directly between the Pump Contractor and the property owner, separate from the Project.

Figure 1. Loca�on and Boundaries of the Lower Uma�lla Basin Groundwater Management Area (Figure 2-1, DEQ, 2020)

DAS Procurement Services, Version 4.5 March 31, 2023 Page 7 of 17

To be considered for evalua�on, Proposal must demonstrate how Proposer meets all requirements of this sec�on:

• Must be State licensed as a pump installa�on specialty contractor, water supply constructor or monitoring well constructor in good standing.

• Must be licensed and in good standing with the State to operate a pump services or well construc�on business in the state or Oregon.

• The Proposer must be currently registered with the Secretary of State to conduct business in the state of

Oregon and must be in compliance with applicable State laws.

• Key Person must be currently licensed as a pump installa�on specialty contractor, water supply constructor, or monitoring well constructor in good standing with the Oregon Water Resources Department’s Well Construc�on and Compliance Sec�on and have at least five years of experience in the field.

To be considered for evalua�on, Proposal must contain each of the following elements (further detailed in Proposal Requirements Sec�on below):

• Execu�ve Summary

• Administra�ve Proposal

• Technical Proposal

• Disclosure Exemp�on Affidavit (Atachment A)

• Proposer Informa�on and Cer�fica�on Sheet (Atachment B)

• Reference Check form (Atachment C)

• Price Proposal (Atachment D) – submited by Proposer

• Key Persons and Resumes

• Work Samples

Proposal is limited to 5 pages. Any pages exceeding this limit will not be provided to the evalua�on commitee or considered in the evalua�on. The following items do not count toward the page limit:

• Disclosure Exemp�on Affidavit (Atachment B)

• Proposer Informa�on and Cer�fica�on Sheet (Atachment C)

• Reference Check forms

• Price Proposal

• COBID Cer�fica�on / Outreach Plan (Atachment F)

• Responsibility Inquiry (Atachment G)

Proposal should follow the format and reference the sec�ons listed in the Proposal Requirements sec�on.

Responses to each sec�on and subsec�on should be labeled to indicate the item being addressed.

OregonBuys Electronic Response. Proposer should submit its Proposal electronically through OregonBuys.

Proposer should follow the procedures outlined in OregonBuys Vendor Formal Solicita�on Response.pdf for electronic submission.

https://www.oregon.gov/das/ORBuys/Documents/OregonBuys%20Vendor%20Formal%20Solicitation%20Response.pdf

DAS Procurement Services, Version 4.5 March 31, 2023 Page 8 of 17

The Price Proposal must be submited as a separate electronic response file.

Proposer shall submit one copy of its Proposal and all other submital requirements, with Atachment C – Proposer Informa�on and Cer�fica�on Sheet bearing the Proposer’s authorized representa�ve's signature, in one of the following formats: Adobe Acrobat (pdf), Microso� Word (docx), or Microso� Excel (xlsx). If Proposer believes any of its Proposal is exempt from disclosure under Oregon Public Records Law (ORS 192.311 through 192.478), Proposer shall complete and submit the Disclosure Exemp�on Affidavit (Atachment B). Proposer shall also mark as “Confiden�al” in OregonBuys all atachments to its Proposal that Proposer believes are exempt from disclosure.

The Proposer Informa�on and Cer�fica�on Sheet (Atachment C) must bear the Proposer’s authorized representa�ve's signature.

Failure of Proposer’s authorized representa�ve to sign the Proposal may result in rejec�on of the Proposal by Agency.

Proposal must address each of the items listed in this sec�on and all other requirements set forth in this RFP. Proposer shall describe the Goods to be provided or the Services to be performed or both. A Proposal that merely offers to provide the goods or services as stated in this RFP may be considered non-Responsive to this RFP and will not be considered further.

Proposal should not include extensive artwork, unusual prin�ng, or other materials not essen�al to the u�lity and clarity of the Proposal. Do not include marke�ng or adver�sing material in the Proposal, unless requested. Proposal should be straigh�orward and address the requests of the RFP. Proposal containing unsolicited marke�ng or adver�sing material may receive a lower evalua�on score if required informa�on is difficult to locate.

Proposer shall complete and submit the Proposer informa�on and Cer�fica�on Sheet (Atachment C).

Failure to demonstrate compliance with Oregon Tax Laws and sign the Proposer Informa�on Cer�fica�on Sheet may result in a finding of non-responsibility.

Provide 3 references from current or former client firms for similar projects performed for any clients within the last 5 years. References must be able to verify the quality of previous, related Work.

Agency may check to determine if references provided support Proposer’s ability to comply with the requirements of this RFP. Agency may use references to obtain addi�onal informa�on, or verify any informa�on needed. Agency may contact any reference (submited or not) to verify Proposer’s qualifica�ons.

Proposer shall submit reference names and contact informa�on. Agency will make three atempts to contact each of the references provided by the Proposer. If these atempts are unsuccessful, the Proposer will receive a score of zero for that reference.

Submit a detailed Price Proposal (Atachment E) in a separate atachment electronically through OregonBuys.

• For each ac�vity described in the Scope of Work, the Price Proposal must include iden�fiable costs, �me es�mates for comple�ng each ac�vity, and a summary of all proposed costs;

• The Price Proposal must include separate line items for personnel, travel, supplies, other costs, and administra�ve and overhead charges; and

• Submit the detailed Price Proposal sta�ng the cost for each listed line item and the total cost for the en�re project. Include a unit-cost breakdown of all labor, mobiliza�on, drilling footage, materials, development �me, standby �me, and other expenses.

https://oregon.public.law/statutes/ors_chapter_192 https://oregon.public.law/statutes/ors_chapter_192

DAS Procurement Services, Version 4.5 March 31, 2023 Page 9 of 17

Specify Key Persons to be assigned to this Project and include a current resume (not to exceed two pages each) for each Key Person that demonstrates the person’s qualifica�ons and experience for the work described in this RFP.

Briefly describe how propose would carry out the major ac�vi�es of this Project in context with the Scope of Work. Provide a comprehensive management plan that the Proposer intends to follow. Illustrate how the plan will serve to coordinate and accomplish the work.

The RFP and atachments are published in the State of Oregon’s electronic Procurement system, OregonBuys, at htps://oregonbuys.gov/. Documents will not be mailed to prospec�ve Proposers.

Modifica�ons, if any, to this RFP will be made only by writen Addenda published in OregonBuys. Prospec�ve Proposer is solely responsible for checking OregonBuys to determine whether or not any Addenda have been issued. Addenda are incorporated into the RFP by this reference.

By submi�ng a Proposal, each Proposer thereby agrees that it accepts all risks, and waives any claims that may be associated with or related its failure to obtain any Addendum, Addenda, or informa�on therein.

A Pre-Proposal conference will not be held for this RFP.

All inquiries, whether rela�ng to the RFP process, administra�on, deadline, or method of Award, or to the intent or technical aspects of the RFP must:

• Be delivered to the SPC via an OregonBuys submission or email;

• Reference the OregonBuys Bid number;

• Iden�fy Proposer’s name and contact informa�on;

• Refer to the specific area of the RFP being ques�oned (i.e., page, sec�on, and paragraph number); and

• Be received by the due date and �me for Ques�ons/Requests for Clarifica�on iden�fied in the Schedule in

Sec�on 1.2.

Prospec�ve Proposer may submit a writen protest of anything contained in this RFP, including but not limited to, the RFP process, specifica�ons, Scope of Work, and the proposed sample Contract. This is prospec�ve Proposer’s only opportunity to protest the provisions of the RFP, except that Proposer may protest Amendment(s) as provided below and Proposer may take excep�on to the terms and condi�ons of the sample Contract marked as nego�able as set forth in Sec�on 5: Award and Nego�a�on.

Prospec�ve Proposer may submit a writen protest of anything contained in an Amendment. Protests to an Amendment, if issued, must be submited by 5:00 p.m. Pacific Time on the second Business Day following the issuance of the Amendment or the date/�me specified in the Amendment, or they will not be considered.

Protests of maters not added or modified by the Amendment will not be considered.

All protests must:

• Be delivered to the SPC via email;

https://oregonbuys.gov/

DAS Procurement Services, Version 4.5 March 31, 2023 Page 10 of 17

• Reference the OregonBuys Bid Solicita�on number;

• Iden�fy prospec�ve Proposer’s name and contact informa�on;

• Be sent by an authorized Representa�ve;

• State the reason for the protest, including:

o The grounds that demonstrate how the Procurement Process is contrary to law, unnecessarily restric�ve, Legally Flawed, or improperly specifies a Brand Name; and o Evidence or documenta�on that supports the grounds on which the protest is based; and

• State the proposed changes to the RFP provisions or other relief sought.

• Protest to the RFP must be received by the due date and �me iden�fied in the Schedule in Sec�on 1.2.

• Protests to an amendment must be received by the due date iden�fied in the Amendment.

Proposer is solely responsible for ensuring its Proposal is received by the SPC in accordance with the RFP requirements before Opening. Agency is not responsible for any delays in mail or by common carriers or by transmission errors or delays, or for any mis-delivery for any reason. A Proposal submited by any means not authorized below will be rejected. The following delivery op�ons are permited for this RFP:

Delivery through OregonBuys

Proposal submission should be submited electronically through OregonBuys at: OregonBuys.gov. Detailed instruc�ons on how to submit a Proposal can be found at OregonBuys Vendor Formal Solicita�on Response.pdf

If a Proposer wishes to make modifica�ons to a submited Proposal, the Proposer must submit its modifica�on in one of the authorized methods listed in Sec�on 4.5 (Proposal Delivery Op�ons). To be effec�ve, the modifica�on must include the OregonBuys Bid Solicita�on number and be submited to the SPC prior to Opening.

If a Proposer wishes to withdraw a submited Proposal, it must submit a writen no�ce signed by an authorized representa�ve of its intent to withdraw to the SPC via email prior to the Opening in accordance with OAR 137-047- 0440. To be effec�ve, the no�ce must include the OregonBuys Bid Solicita�on number.

A Proposal (including all required submital items) must be received by the SPC on or before Opening. All Proposal modifica�ons or withdrawals must also be received prior to Opening.

A Proposal received a�er Opening is considered LATE and will NOT be accepted for evalua�on. A late Proposal will be returned to the Proposer or destroyed.

There will not be a public Opening held for this RFP. OWRD will post a list of Proposals received on OregonBuys within two business days of the Opening date.

Agency may reject a Proposal for any of the following reasons:

• Proposer fails to substan�ally comply with all prescribed RFP procedures and requirements, including but not limited to the requirement that Proposer’s authorized representa�ve sign the Proposal.

• Proposer has liquidated and delinquent debt owed to the State or any Department or Agency of the State.

• Proposer fails to meet the responsibility requirements of ORS 279B.110.

• Proposer makes any contact regarding this RFP with State representa�ves, such as State employees or officials other than the SPC or persons authorized by the SPC, or inappropriate contact with the SPC.

• Proposer atempts to influence a member of the Evalua�on Commitee.

• Proposal is condi�oned on Agency’s acceptance of any other terms and condi�ons or rights to nego�ate any alterna�ve terms and condi�ons that are not reasonably related to those expressly authorized for nego�a�on in the RFP or Amendment(s).

https://www.oregon.gov/das/ORBuys/Documents/OregonBuys%20Vendor%20Formal%20Solicitation%20Response.pdf https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11316 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11316 https://oregon.public.law/statutes/ors_279B.110

DAS Procurement Services, Version 4.5 March 31, 2023 Page 11 of 17

A Proposal received prior to Opening will be reviewed to determine if it is Responsive to all RFP requirements including compliance with Sec�on 3.1 (Minimum Qualifica�ons) and Sec�on 3.2 (Minimum Submission Requirements). If the Proposal is unclear, the SPC may request clarifica�on from Proposer. However, clarifica�on may not be used to rehabilitate a non-Responsive Proposal. If the SPC finds the Proposal non-Responsive, the proposal may be rejected; however, Agency may waive mistakes in accordance with OAR 137-047-0470.

Agency will determine if an apparent successful Proposer is Responsible prior to Award and execu�on of the Contract. Selected Proposer(s) shall submit a signed Responsibility Inquiry Form (Atachment G) within 5 Business Days of receipt of Intent to Award No�ce.

At any �me prior to award, Agency may reject a Proposer found to be not Responsible.

The following is how the evalua�on will be structured.

SCORE EXPLANATION

OUTSTANDING – Response meets all the requirements and has demonstrated in a clear and concise manner a thorough knowledge and understanding of the subject mater and Project.

The Proposer provides insight into its exper�se, knowledge, and understanding of subject mater.

6-9 VERY GOOD – Response provides useful informa�on, while showing experience and knowledge within the category. Response demonstrates above average knowledge and ability with no apparent deficiencies noted.

ADEQUATE – Response meets all requirements in an adequate manner. Response demonstrates an ability to comply with guidelines, parameters, and requirements with no addi�onal informa�on put forth by the Proposer.

1 – 4 FAIR – Proposer meets minimum requirements but does not demonstrate sufficient knowledge of the subject mater.

0 RESPONSE OF NO VALUE – An unacceptable response that does not meet the requirements set forth in the RFP. Proposer has not demonstrated knowledge of the subject mater.

Each Proposal mee�ng all Responsiveness requirements will be independently evaluated by members of an Evalua�on Commitee. Evalua�on Commitee members my change, and Agency may have addi�onal or fewer evaluators for op�onal rounds of compe��on. Evaluators will assign a score for each evalua�on criterion listed below in Sec�on 4.10.2.1 through 4.10.2.3 up to the maximum points available as specified in Sec�on 4.11 (Point and Score Calcula�on).

SPC may request further clarifica�on to assist the Evalua�on Commitee in gaining addi�onal understanding of a Proposal. A response to a clarifica�on request may only clarify or explain por�ons of the already submited Proposal and may not contain new informa�on not included in the original Proposal.

• How well does the Proposal demonstrate the Proposer’s project team experience, project management, and organiza�on will contribute to successful and efficient comple�on of OWRD work assignments?

https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11322

DAS Procurement Services, Version 4.5 March 31, 2023 Page 12 of 17

• How well does the Proposal demonstrate specific experience relevant to OWRD’s well pump, and installa�on standards?

• Does the Proposal demonstrate the Proposer’s ability to mobilize, start, and complete the Project by June 30, 2025?

The SPC will conduct the price evalua�on. The SPC will Award a price score to each Price Proposal based upon the percentage of the proposed price as compared to the lowest Proposer’s price using the following formula:

lowest price of all Proposers X price points possible = price score price being scored

Agency prefers Oregon Goods and Services, and for evalua�on purposes per ORS 279A.128, Agency shall subtract 5% from the price for any Proposer proposing all Goods fabricated or processed or all services performed en�rely in Oregon before calcula�ng the price score.

For evalua�on purposes per OAR 137-046-0310, Agency shall add a percentage increase to each out-of- State Proposer’s Proposal price that is equal to the percentage preference, if any, given to a resident Proposer in the Proposer’s State.

Agency will give preference to Goods manufactured from Recycled Materials if each of the condi�ons specified in ORS 279A.125(2) exists following any adjustments made to the price of the Goods according to any applicable reciprocal preference.

If Agency receives Proposal iden�cal in price, fitness, availability, and quality and chooses to Award a Contract, Agency shall Award the Contract in accordance with the procedures outlined in OAR 137-046- 0300.

TOTAL POINTS POSSIBLE: 50

POINTS POSSIBLE

4.10.2.1 Evalua�on Item 1 10

4.10.2.2 Evalua�on Item 2 10

4.10.2.3 Evalua�on Item 3 10

4.10.3 Price Evalua�on 20

The SPC will average all scores for each evalua�on criterion. The average score will be used as a percentage mul�plier of the maximum points for that criterion. 1=10%, 5=50%, 7.2=72%, 9=90%, etc. Price points are calculated as stated in the Price Evalua�on sec�on as set forth in Sec�on 4.10.3.

Example:

https://oregon.public.law/statutes/ors_279A.128 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11216 https://www.naspo.org/reciprocity1 https://oregon.public.law/statutes/ors_279A.125 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11212 https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=11212

DAS Procurement Services, Version 4.5 March 31, 2023 Page 13 of 17

Proposer A receives scores of 10, 9, and 9.5 for criterion worth 50 points. The SPC averages 10, 9, and 9.5 for a score of 9.5 and uses 95% as a mul�plier to the possible points of 50. 50 Mul�plied by 95% is 47.5. Proposer A’s points for the criterion is 47.5.

The SPC will average the scores for each Proposal in a given round of compe��on (calculated by totaling the points awarded by each Evalua�on Commitee member and dividing by the number of members). The SPC will combine the average score for each Proposal with Proposer’s Price Score and Reference Score.

A�er any applicable preference has been applied, the SPC will determine the rank of each Proposal, with the highest score receiving the highest rank, and successive rank order determined by the next highest score.

Agency may, in Agency’s sole discre�on, determine an apparent successful Proposer with no addi�onal rounds of compe��on. If addi�onal rounds are conducted, Agency will rank advancing proposers at the conclusion of each subsequent round and may determine an apparent successful Proposer at any �me during the Solicita�on process.

If Agency, in its sole discre�on, determines that one or more addi�onal rounds of compe��on is necessary, it will select a Compe��ve Range to indicate the Proposers that will be invited to par�cipate in a subsequent round. The Compe��ve Range may include all, or at Agency’s sole discre�on, some (based primarily on a natural break in the distribu�on of scores), of the Proposers from a previous round. Agency will post a no�ce in OregonBuys of its Compe��ve Range Determina�on and provide details about the process and schedule for the subsequent round.

Proposers excluded from a round may submit a writen protest of Compe��ve Range. Protest must:

• Be emailed to the SPC;

• Reference the OregonBuys Bid Solicita�on number;

• Iden�fy Proposer’s name and contact informa�on;

• Be sent by an authorized representa�ve;

• State the reason for the protest; and

• Be received within 7 Calendar Days a�er issuance of the No�ce of the Compe��ve Range unless a different due date and �me is specified in such no�ce.

Agency will address all protests within a reasonable �me and will issue a writen decision to the respec�ve Proposer. Protests that do not include the required informa�on may not be considered by Agency.

There will be no addi�onal rounds of selec�on for this Solicita�on.

Agency, if it awards a Contract, will Award a Contract to the highest ranking Responsible Proposer(s) based upon the scoring methodology and process described in Sec�on 4. Agency may Award less than the full Scope of Work described in this RFP.

Agency will no�fy all Proposers in wri�ng that Agency intends to Award a Contract to the selected Proposer(s) subject to successful nego�a�on of any nego�able provisions.

DAS Procurement Services, Version 4.5 March 31, 2023 Page 14 of 17

An affected Proposer shall have 7 calendar days from the date of the Intent to Award no�ce to file a writen protest.

A Proposer is an Affected Proposer only if the Proposer would be eligible for Contract Award in the event the protest was successful and is protes�ng for one or more of the following reasons as specified in ORS 279B.410:

• All higher ranked Proposals are non-Responsive.

• Agency has failed to conduct an evalua�on of Proposals in accordance with the criteria or process described in the RFP.

• Agency abused its discre�on in rejec�ng the protestor’s Proposal as non-Responsive.

• Agency’s evalua�on of Proposal or determina�on of Award otherwise violates ORS Chapter 279B or

ORS Chapter 279A.

If Agency receives only one Proposal, Agency may dispense with the evalua�on process and Intent to Award protest period and proceed with Contract Nego�a�ons and Award.

Protests must:

• Be delivered to the SPC via email;

• Reference the OregonBuys Bid Solicita�on number;

• Iden�fy Proposer’s name and contact informa�on;

• Be signed by an authorized representa�ve of Proposer;

• Specify the grounds for the protest; and

• Be received within 7 calendar days of the Intent to Award no�ce.

Agency will address all �mely submited protests within a reasonable �me and will issue a writen decision to the respec�ve Proposer. Protests that do not include the required informa�on may not be considered by

Proposer(s) who are selected for a Contract award under this RFP will be required to submit addi�onal informa�on and comply with the following:

Prior to award, Proposer shall secure and demonstrate to Agency proof of insurance as required in this RFP or as nego�ated. Insurance Requirements are found in Exhibit B of Atachment A (Sample Contract).

Proposer shall provide its Taxpayer Iden�fica�on Number (TIN) and backup withholding status of a completed W-9 form when requested by Agency or when the backup withholding status or any other relevant informa�on of Proposer has changed since the last submited W-9 form, if any.

If selected for Award, Proposer shall be duly authorized by the State of Oregon to transact business in the State of Oregon before execu�ng the Contract. Visit htp://sos.oregon.gov/business/pages/register.aspx for Oregon Business Registry informa�on.

Prior to award, Proposer shall be required to complete and submit Atachment G – Responsibility Inquiry.

https://oregon.public.law/statutes/ors_279b.410 https://oregon.public.law/statutes/ors_chapter_279B https://oregon.public.law/statutes/ors_chapter_279A http://sos.oregon.gov/business/pages/register.aspx

DAS Procurement Services, Version 4.5 March 31, 2023 Page 15 of 17

If selected for award and the Contract value exceeds $500,000 and Proposer employs 50 or more full-�me workers, Proposer shall submit to Agency a true and correct copy of an unexpired Pay Equity Compliance Cer�ficate, issued to the Proposer by the Oregon Department of Administra�ve Services. For instruc�ons on how to obtain the Cer�ficate, visit htps://www.oregon.gov/das/Procurement/Pages/PayEquity.aspx.

ORS 279B.110(2)(f) requires that Proposer provide this prior to execu�on of the Contract.

As a condi�on of receiving the award of a Contract under this RFP, Proposer must cer�fy by its Signature on Atachment C – Proposer Informa�on and Cer�fica�on Sheet, in accordance with ORS 279A.112, that it has in place a policy and prac�ce of preven�ng sexual harassment, sexual assault, and discrimina�on against employees who are members of a protected class. The policy and prac�ce must include giving employees a writen no�ce that the policy both prohibits, and prescribes disciplinary measures for, conduct that cons�tutes sexual harassment, sexual assault, or unlawful discrimina�on.

A�er selec�on of a successful Proposer, Agency may enter into Contract Nego�a�ons with the successful Proposer. By submi�ng a Proposal, Proposer agrees to comply with the requirements of the RFP, including the terms and condi�ons of the Sample Contract (Atachment A), with the excep�on of those terms listed below for nego�a�on.

Proposer shall review the atached sample Contract and note excep�ons.

Proposer must submit those excep�ons to Agency during the Ques�ons / Request for Clarifica�on period set forth in Sec�on 1.2. if Agency agrees to make any requested changes to the Sample Contract, Agency will issue an Amendment to no�fy Proposers of such changes. Unless Agency issues an Amendment modifying any of the terms and condi�ons, Agency intends to enter into a Contract with the successful Proposer substan�ally in the from set forth in the Sample Contract (Atachment A).

Following the selec�on of the apparent successful Proposer, Agency may agree to nego�ate changes to the nego�able provisions of the sample Contract listed below. However, Agency is not required to make any changes and many provisions cannot be changed. Proposer is cau�oned that the State of Oregon believes modifica�ons to the standard provisions cons�tute increased risk and increase cost to the State.

Any subsequent nego�ated changes are subject to prior approval of the Oregon Department of Jus�ce.

Agency is willing to nego�ate ONLY the Statement of Work and the following terms and condi�ons:

• Methods of Payment

• Term of Contract; and

• Pricing.

In the event that the par�es have not reached mutually agreeable terms within 14 calendar days, Agency, t its discre�on, may termina�on Nego�a�ons and commence Nego�a�ons with the next highest ranking Proposer.

The State of Oregon is commited to taking ac�ve steps toward increasing and promo�ng diversity, equity, and inclusion values across Procurement processes or minority, women, emerging small, and service-disabled veteran owned businesses by reducing barriers to compete for and be awarded State contracts. All interested businesses are encouraged to submit proposals for this contrac�ng opportunity.

https://www.oregon.gov/das/Procurement/Pages/PayEquity.aspx https://oregon.public.law/statutes/ors_279b.110 https://oregon.public.law/statutes/ors_279A.112

DAS Procurement Services, Version 4.5 March 31, 2023 Page 16 of 17

Pursuant to Oregon Revised Statute (ORS) Chapter 200, Agency encourages the par�cipa�on of small businesses, cer�fied by the Oregon Cer�fica�on Office for Business Inclusion and Diversity (“COBID”) in all contrac�ng opportuni�es. This includes cer�fied small businesses in the following categories: disadvantaged business enterprise, minority-owned business, woman-owned business, a business that a service-disabled veteran owns or an emerging small business. Agency also encourages joint ventures or subcontrac�ng with cer�fied small business enterprises. For more informa�on, visit:

htps://oregon4biz.diversityso�ware.com/FrontEnd/SearchCer�fiedDirectory.asp?XID=2315&TN=oregon4biz

If the Contract has poten�al subcontrac�ng opportuni�es, the successful Proposer may be required to submit a completed Cer�fied Disadvantaged Business Outreach Plan (Atachment F) prior to execu�on.

This RFP is governed by the laws of the State of Oregon. Venue for any administra�ve or judicial ac�on rela�ng to this RFP, evalua�on and award is the Circuit Court of Marion County for the State of Oregon; provided, however, if a proceeding must be brought in a federal forum, then it must be brought and conducted solely and exclusively within the United States District Court for the District of Oregon. In no event shall this Sec�on 6.3 be construed as a waiver by the State of Oregon of any form of defense or immunity, whether sovereign immunity, governmental immunity, immunity based on the Eleventh Amendment to the Cons�tu�on of the United States or otherwise, to or from any claim or consent to the jurisdic�on of any court.

All Proposals are public records and are subject to public inspec�on a�er Agency issues the No�ce of Intent to Award.

Applica�on of the Oregon Public Records Law will determine whether any informa�on is exempt from disclosure.

All Proposals submited in response to this RFP become the Property of Agency. By submi�ng a Proposal in response to this RFP, Proposer grants the State a non-exclusive, perpetual, irrevocable, royalty-free license for the rights to copy, distribute, display, prepare deriva�ve works of and transmit the Proposal solely for the purpose of evalua�ng the Proposal, nego�a�ng a Contract, if awarded to Proposer, or as otherwise needed to administer the RFP process, and to fulfill obliga�ons under Oregon Public Records Law (ORS 192.311 through 192.478). Proposals, including suppor�ng materials, will not be returned to Proposer, except in the case of Proposals that were submited late and rejected by

Pursuant to ORS 279B.100, Agency may reject any or all Proposals in-whole or in-part, or may cancel this RFP at any �me when the rejec�on or cancella�on is in the best interest of the State or Agency, as determined by Agency. Neither the State nor any State Agency is liable to any Proposer for any loss or expense caused by or resul�ng from the delay, suspension, or cancella�on of the RFP or a Contract award, or the rejec�on of any Proposal.

Proposer shall pay all costs incurred in connec�on with its Proposal, including, but not limited to, the costs to prepare and submit the Proposal, costs of samples and other suppor�ng materials, costs to par�cipate in demonstra�ons, and costs associated with protests.

If applicable, Proposer shall include informa�on in its Proposal that demonstrates compliance with the Statewide E- Waste/Recovery Procedure #107-011-050_PR. Visit the DAS website www.oregon.gov/das and use the search bar feature to locate the procedure.

Proposal shall use recyclable products to the maximum extent economically feasible in the performance of the Services or Work described in this RFP and the subsequent Contract (ORS 279B.025).

https://oregon.public.law/statutes/ors_chapter_200 https://oregon4biz.diversitysoftware.com/FrontEnd/SearchCertifiedDirectory.asp?XID=2315&TN=oregon4biz https://oregon.public.law/statutes/ors_chapter_192 https://oregon.public.law/statutes/ors_279b.100 https://www.oregon.gov/das/policies/107-011-050_pr.pdf https://www.oregon.gov/das/policies/107-011-050_pr.pdf https://www.oregon.gov/das https://oregon.public.law/statutes/ors_279b.025

DAS Procurement Services, Version 4.5 March 31, 2023 Page 17 of 17

Any checklists that may be contained in this RFP are provided only as a courtesy to prospec�ve Proposer. Agency makes no representa�on as to the completeness or accuracy of any Checklist. Prospec�ve Proposer is solely responsible for reviewing and understanding the RFP and complying with all the requirements of this RFP, whether listed in a checklist or not. Neither the State nor Agency is liable for any claims, or subject to any defenses, asserted by Proposer based upon, resul�ng from, or related to, Proposer’s failure to comprehend all requirements of this RFP.

SECTION 1: GENERAL INFORMATION
1.1 INTRODUCTION
1.2 SCHEDULE
1.3 SINGLE POINT OF CONTACT (SPC)
SECTION 2: AUTHORITY AND METHOD
2.1 AUTHORITY AND METHOD
2.2 DEFINITION OF TERMS
2.3 OVERVIEW AND PURPOSE
2.4 SCOPE OF WORK/SPECIFICATIONS
2.5 PROJECT DETAILS
SECTION 3: PROCUREMENT REQUIREMENTS
3.1 MINIMUM QUALIFICATIONS
3.2 MINIMUM SUBMISSION REQUIREMENTS
3.3 PROPOSAL REQUIREMENTS
SECTION 4: SOLICITATION PROCESS
4.1 PUBLIC NOTICE
4.2 PRE-PROPOSAL CONFERENCE
4.3 QUESTIONS / REQUESTS FOR CLARIFICATIONS
4.4 SOLICITATION PROTESTS
4.5 PROPOSAL DELIVERY OPTIONS
4.6 PROPOSAL MODIFICATION OR WITHDRAWAL
4.7 PROPOSAL DUE
4.8 PUBLIC OPENING
4.9 PROPOSAL REJECTION
4.10 EVALUATION PROCESS
4.11 POINT AND SCORE CALCULATIONS
4.12 RANKING OF PROPOSERS
4.13 ADDITIONAL ROUNDS
SECTION 5: AWARD AND NEGOTIATION
5.1 AWARD NOTIFICATION PROCESS
5.2 INTENT TO AWARD PROTEST
5.3 APPARENT SUCCESSFUL PROPOSER SUBMISSION REQUIREMENTS
5.4 CONTRACT NEGOTIATION
SECTION 6: ADDITIONAL INFORMATION
6.1 COMMITMENT TO DIVERSITY, EQUITY, INCLUSION
6.2 CERTIFIED FIRM PARTICIPATION
6.3 GOVERNING LAWS AND REGULATIONS
6.4 OWNERSHIP/PERMISSION TO USE MATERIALS
6.5 CANCELLATION OF RFP; REJECTION OF PROPOSAL; NO DAMAGES
6.6 COST OF SUBMITTING A PROPOSAL
6.7 STATEWIDE E-WASTE/RECOVERY PROCEDURE
6.8 RECYCLABLE PRODUCTS
6.9 CHECKLIST DISCLAIMER

File details come from the government source that posted it. Updated .