This RFP Questions and Answers document addresses inquiries from prospective consultants regarding Fond du Lac Area Transit's (FDLAT) Transit Development Plan (TDP) update project in Wisconsin, coordinated in partnership with the City of Fond du Lac and the East Central Wisconsin Regional Planning Commission (ECWRPC). The consultant will be responsible for helping craft a ridership survey, which FDLAT and ECWRPC will administer through both in-person and online methods. The scope includes access to previous transit ridership data and origin-destination data from prior Transit Development Plans. Consultants may propose engagement activities beyond those explicitly listed in the RFP, though capital planning recommendations regarding transit centers and electric bus fleets will be addressed in future separate studies. The project completion deadline is September 30, 2022.
Regarding pricing and participation requirements, project costs should be tailored to the scope outlined in the RFP with no specific budget range provided in this document. There is no contract-specific Disadvantaged Business Enterprise (DBE) or Minority Business Enterprise (MBE) participation goal at this time, though proposing firms must indicate their DBE/MBE status. No incumbent information is referenced in the questions and answers. The consultant will work under the direction of City of Fond du Lac, FDLAT, and ECWRPC staff to develop materials that provide adequate direction for the transit system's five to ten year development horizon.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Boarding and Alighting 2014.pdf | ||
| Fond du Lac Area Transit TDP RFP_2022.pdf | ||
| Sample Survey.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Will FDLAT or the consultant be responsible for administering the rider (on-board) survey?
Answer: Per the RFP, the consultant will help craft the ridership survey. FDLAT, in conjunction with East Central Wisconsin Regional Planning Commission, will administer the rider survey. We hope to administer this both in person and with an online survey.
2. Regarding Task 2, can you provide examples of the transit ridership data and origin and destination data that will be made available to the consultant?
Answer: Please see attachments from previous Transit Development Plan.
3. Page 4, Item F references public outreach and states the consultant’s responsibilities are in Task A (5). Task A (5) does not cover engagement, can you provide some clarification regarding responsibilities?
Answer: Consultant may propose engagement activities beyond what is listed in the RFP.
4. The scope does not specifically address capital planning, is this an element you would like to see in the proposals?
Answer: Capital recommendations, including but not limited to, a transit center and electric bus fleet, will be covered in future studies.
5. The RFP states proposing firms must indicate their DBE/MBE status. Is there a contract specific goal for DBE/MBE participation?
Answer: No specific goal at this time.
6. What is the approximate budget for this project?
Answer: Cost should be tailored to the scope outlined in the RFP.