This is a Schedule of Deliverables attachment to RFP No. 283-24-0642 for Grant & Contract Review Support services for the Substance Abuse and Mental Health Services Administration (SAMHSA). The schedule outlines 33 general requirements deliverables and specific task deliverables related to program management, contract technical support, honorarium payments, and transition activities.

Key deliverables include: IT Plan due 60 days after award; Privacy Threshold Analysis within 30 days; Information Security and Privacy training requirements within 30 days; System Authorization to Operate before system go-live; monthly vulnerability scan reports; Web Content Migration Plan within 60 days; monthly teleconference meetings and reports; technical writer support for peer review meetings (requiring 5-25 meetings with reports due within 10 days); and honorarium payment processing for contract reviewers within 10 business days after meetings. The contract includes optional tasks for additional grant honorarium support (10-50 applications) and increased contract technical support services. The bulk of work is expected between January and August annually, with February through June being peak periods.

View the file

Other files

File Type Posted
SF-30 283-25-0642 Amendment 2.pdf PDF
RFP 283-25-0642 QAs Updated 12-19-24.pdf PDF
RFP 283-25-0642 Questions - Answers.pdf PDF
RFP No. 283-24-0642 Attachment 1a PWS_Revised 12.17.24.pdf PDF
RFP No. 283-24-0642 Attachment 2 QASP_Revised 12.17.24.pdf PDF
SF-30 283-25-0642 Amendment 1.pdf PDF
RFP No. 283-24-0642 Attachment 2 QASP.doc DOC document
RFP No. 283-25-0642 Attachment 6 Packaging and Delivery of Proposals via eCPS.docx DOCX document
RFP No. 283-25-0642 Attachment 15 Section 508 Template.docx DOCX document
RFP. No. 283-25-0642 Attachment 13 Summary of Cost and Hours Spreadsheet.xlsx XLSX spreadsheet
RFP No. 283-25-0642 Attachment 7 Government Notice for Handling Proposals.docx DOCX document
RFP No. 283-25-0642 Attachment 9 & 10 Client Letter & Contractor Performance Form.docx DOCX document
RFP No. 283-25-0642 Attachment 4 SF LLL-A, Disclosure of Lobbying Activities.docx DOCX document
RFP No. 283-25-0642 Attachment 5 Proposal Intent Response.docx DOCX document
RFP No. 283-25-0642 Attachment 14 Sealed Proposal Cover Page & Instructions.docx DOCX document
RFP No. 283-24-0642 Attachment 1b General Requirements.docx DOCX document
RFP No. 283-25-0642 Attachment 11 Breakdown Estimated Costs and Labor Hours.docx DOCX document
RFP No. 283-25-0642 Cover Letter.pdf PDF
RFP No. 283-24-0642 Attachment 1a PWS.docx DOCX document
RFP No. 283-25-0642 Attachment 3 Billing Instructions.docx DOCX document
RFP No. 283-25-0642 Attachment 8 Contact Points.docx DOCX document
RFP No. 283-25-0642 Attachment 12 IT Total Estimate Cost Sheet.xls XLS spreadsheet
RFP 283-25-0642.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. 283-24-0642 Attachment No. 1c

Schedule of Deliverables

General Requirements

Item
Timeline
To
Section
1
Final Information Technology (IT) Plan
60 calendar days after award. Review annually
DTM thru Contracting Officer's Representative (COR)
II
2
Meeting on systems or websites migration from third-party hosted service to SAMHSA
At least 60 calendars days or earlier before the planned migration date
DTM Infrastructure Team thru COR
V
3
IT and Web Cost Reports
Twice a year (July and November)
DTM Federal Information Technology Acquisition Reform Act (FITARA) Team thru COR
IV
4
IT Investment Factsheet
90 calendar days after award and update annually
DTM FITARA Team thru COR
IV
5
Website Domain Registration
When registered and when requested
DTM FITARA Team thru COR
IV
6
Privacy Threshold Analysis (PTA)
30 calendar days after award
Privacy and Chief Information Security Officer (CISO) and Info.Privacy@samhsa.hhs.gov thru COR
V
7
Entity, data type and relationship diagrams
No later than 30 calendar days after award
CISO and Info.Privacy@samhsa.hhs.gov thru COR
V
8
Draft system’s Privacy Impact Assessments (PIAs) if full PIAs is needed
No later than 45 calendar days after contract effective date (CED)
Privacy Officer and Info.Privacy@samhsa.hhs.gov thru COR
V
9
Encryption Key if applicable
When requested or at the end of the contract
Info.Privacy@samhsa.hhs.gov and COR
V
10
Information Security Awareness and Privacy training
Within 30 calendar days after CED and annually
COR
V
11
Security and Privacy Role-based Training
Within 30 calendar days after CED and annually
COR
V
12
Security and Privacy Training Records
Within 35 calendar days after CED and annually
COR
V
13
Read and sign Rules of Behavior
Within 35 calendar days after CED and annually
COR
V
14
Staff Roster
Within 30 calendar days after CED and 10 days when staffing changes
COR
V
15
Project Closeout/System Decommission meeting
At least 30 calendar days before project closeout/system decommission
DTM thru COR
V
16
Initiate security assessment and authorization (SA&A) process
No later than 30 calendar days after CED
CISO thru COR
V
17
System Authorization to Operate (ATO)
Before system goes live
CIO and CISO
V
18
Information System Security Plan (ISSP) (with supporting artifacts and documents listed on the ATO package and the Security Checklist.)
Part of ATO package, before system goes live
CISO and security email box infosecurity@samhsa.hhs.gov
V
19
E-Authentication Questionnaire (Risk Assessment)
Within 30 calendar days after CED
CISO and infosecurity@samhsa.hhs.gov. Template can be requested by emailing CISO and ISSO.
V
20
Privacy and security kickoff meeting
Within four (4) weeks of CED
COR and CISO
Work plan
21
Annual Penetration Testing Summary Report
Annually, anytime during a contract year
COR and DTM Security Team
V
22
Vulnerability scan reports for database, application, and operation system
Every 30 days after ATO is granted
Upload to SAMHSA Sharepoint Site directed by the SAMHSA Security team and COR
V
23
Vulnerability “Change Report” and Cloud Security Continuous Monitoring Reporting
Every 30 days after ATO is granted
Upload to SAMHSA Sharepoint Site directed by the SAMHSA Security team and COR
V
24
Permanent electronic records
60 days prior to period of performance expiration
DTM Records Management Officer
XXXI 2. 3.
25
Records management training and provide Contractor Records Management Training Completion Memorandum
Within 30 days of contract award or new contract staff start date and then annually for the life of the contract.
COR

XXXI 2. 11.

26
Electronic Systems Questionnaire
Responses within 4 weeks after the CED and 30 days prior to modifications to system
DTM thru COR during the kickoff meeting
XXXI 2.12.
27
HHS Accessibility Checklist
Each content deliverables
COR
OC requirements I. G
28
Content Development and Management Plan
Within 60 days after CED
OC and DTM (including Records Officer) thru COR
OC requirements IV. A
29
Web Content Approval
No later than 3 weeks prior to the planned initial posting of document
COR
OC requirements IV. C
30
Web Content Migration Plan including a demo
Within 60 days after CED; demo within 30 days after CED
COR and DTM (including Records Officer) thru COR
OC requirements IV. D
31
Meeting on IT transition activities related to data, software, web content, and electronic records
Within 30 days after CED
COR, DTM, and OC
OC requirements IV. E
32
Reports of actual Web-related IT costs
Twice a year (July and November)
OC and DTM thru COR

(could be combined with IT and Web Cost reports, see #3) OC requirements IV. F

33
Transition Task
Schedule meeting with COR and DTM to discuss transition activities
COR and DTM
Transition Task

Specific Requirements

Task
Item
Quantity
Due Date

Task 1: Program Management and Reporting Activities

Task 1.1
Kick-Off Meeting

Kick-Off Meeting Summary Report

No later than (7) business days after Contract Effective Date (CED)

Within one (1) business day after meeting

Task 1.2
Draft Work Plan
1
Two (2) business days before the Contract kick-off meeting date
Task 1.3
Final Work Plan

Draft Work Plan for next year

Final Work Plan for next year

Within one (1) week after receipt of comments from the COR on the draft Work Plan

48 weeks after CED

Within two (2) week after COR comments

Task 1.4
Task 1.4: Monthly Teleconference Meeting

Summary of Monthly Teleconference Meeting

At the end of each month

Within one (1) business day of meeting completion

Task 1.5

Monthly reports

Draft Annual Report

Final Annual Report

10th day after the end of the month

No later than three (3) weeks before the end of the year

No later than one (1) week after receipt of COR comments

Task 3: Contract Technical Support

Task 3.2
Provide Technical Writers for Peer Review Meetings

Technical Review Summary Report Summary * Others

Writers’ fee

Writers’ Summary fee

Seven (7) business days after task received

Ten (10) calendar days after meeting 20 calendar days after meeting

Ten (10) business days after meeting

Ten (10) business days after COR acceptance of the final Summary

Task 3.3
Provide Technical Writers for Objective Review Meetings

Technical Review Summary Report

Seven (7) business days after task received

Ten (10) business days after meeting

Ten (10) business days after COR acceptance of the final Summary

Task 3.5
Establish and Maintain Reviewer and Technical Writer Database
1
TBD

Task 4: Honorarium Payments Support

Task 4.1
Contract Reviewer Honorarium payments
TBD
Ten (10) business days after meeting
Task 4.2
Grant Honorarium Payment Support
TBD
Ten (10) business days after receipt of honorarium documents

Task 5: Transition of Contract Specific Activities

Startup at the beginning of contract

Turnover at the end of contract

Implement a smooth transition Participate in meetings with previous contractor

Plans for transfer of project

Meetings with the new Contractor Five (5)

One (1)

Five (5) TBD – As director by CO

No later than two (2) months prior to completion of the final period of performance

TBD – As director by CO

Optional Task 6: Ability to increase Grants honorarium support for ten (10) applications

Optional Task 6
Ability to increase Grants honorarium support for ten (10) applications
10
Within ten (10) business days of receipt of honorarium documents

Optional Task 7: Ability to increase Grants honorarium support for fifty (50) applications

Optional Task 7
Ability to increase Grants honorarium support for fifty (50) applications
50
Within ten (10) business days of receipt of honorarium documents

Optional Task 9 – Ability to increase Contract Technical Support

Optional Task 9
Provide Technical Writers for Objective Review Meetings

Technical Review Summary Report

Seven (7) business days after task received

Ten (10) business days after meeting

Ten (10) business days after COR acceptance of the final Summary

Optional Task 10 – Ability to hold an In-Person Contract Review Meeting

Task 10.1
Contract Reviewer Honorarium payments

Reviewer travel

5
Honoraria mailed within ten (10) business days following the close of the meeting

Reimbursement checks for travel mailed by no later than 30 calendar days after receipt of Reviewers travel voucher

Task 10.2
Finalize Contract with Hotel for Lodging and Meeting Rooms for the Technical Merit Peer Review Committee Meetings
1
Within four (4) weeks of the Option Task Effective Date (OTED)
Task 10.4
Provide Technical Writers for In-Person Review Meetings

Technical Review Summary Report

Within seven (7) business days after receipt of the task

Ten (10) business days after meeting

Ten (10) business days after COR acceptance of the final Summary