RFP 935400-01 Addendum#1.pdf
PDF 3 MB Posted
- Attached to
- DOC Anamosa State Penitentiary LUC Plumbing
- Solicitation number
- RFP935400-01
- Issued by
- Jones County, Iowa
About this file
This is an Addendum #1 to RFP 935400-01 issued by the State of Iowa Department of Administrative Services (DAS) for professional design services related to plumbing repairs at the DOC Anamosa State Penitentiary Living Unit C. The project encompasses the replacement of existing pipe chases, supply/waste/vent piping, and plumbing fixtures across all 320 individual cells within Living Unit C, along with installation of new combination toilet/lavatory units. The design scope requires detailed construction drawings, specifications, and coordination with the Construction Manager regarding phasing, budget, and construction administration. A pre-bid meeting was held on October 12, 2023, with representatives from McGough Construction, Innovative Engineers, ISG, Bluestone, MODUS, and Shive-Hattery in attendance. Proposals were due October 26, 2023, at 2:00 p.m., with designer selection and contract execution anticipated for the week of October 30, 2023, and a design kickoff meeting scheduled for the week of November 6, 2023. Design deliverables include 100% Design Development by coordination with the Construction Manager, 50% and 95% Construction Documents at defined milestones, and 100% Construction Documents due January 8, 2024. Site visits to Living Unit C during the walkthrough were conducted during the pre-bid meeting.
The project budget ranges from $3,794,170 for a 13-week construction period to $5,322,023 for a 45-week construction period, depending on construction phasing. Pricing proposals must include lump sum fees broken down by design milestones and schedule of values. The hot water supply line replacement up to 100 feet from cells must be treated as an add alternate separate from the base bid scope. A hazardous material survey will be conducted to determine if abatement work is necessary prior to base bid work commencement. The selected design firm must provide a Professional Liability policy of $2,000,000 with a $25,000 deductible and submit a project-specific Certificate of Insurance prior to contract execution. DAS utilizes the Procore online project management system at no cost to the designer and employs a modified ConsensusDocs 803 Form of Agreement. Proposals must include resumes for all assigned technical staff, anticipated hours and rates for design team members, and a project-specific schedule. The facility indicated capacity to empty half of Living Unit C during construction as the preferred phasing method.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 1 for RFP 935400-01
Project Name: DOC Anamosa Living Unit Plumbing Repairs
RFP #: 935400-01
DAS Project #: 9354.00
Date: 10/23/2023
Bids Due: October 26, 2023 at 2:00 p.m.
Pre-Bid Meeting Minutes and Sign-In Sheet Included
General Notes:
• The budget for the project will vary depending on the phasing of the construction. The budget will range from $3,794,170(13 Week Construction Period) to $5,322,023(45 Week Construction
Period).
• A hazardous material survey will be conducted to determine if abatement will be needed to perform the base bid scope.
Project Scope
• The replacement of the hot water supply lines will need to be separated from the rest of the project and treated as an add alternate.
Appendix 1
• Photos from Living Unit C taken during the site walkthrough.
END OF ADDENDUM
State of Iowa - Department of Administrative Services 109 SE 13th St.
Des Moines, Iowa 50319 P: (515) 281-7260
Project: 9354.00 DOC ASP LUC Plumbing Repairs 406 N High Street
Anamosa, Iowa 52205 P: 319-462-3504
RFP Pre-Proposal Minutes: Meeting #1
Meeting Date Oct 12, 2023 Meeting Time 10:00 AM - 11:00 AM Central Time (US & Canada)
Meeting Location Video Conferencing Link https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxL TgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?cont ext=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a5 4b-41d5-46ef-82bc-8260ef04c509%22%7d
Overview Meeting to allow prospective design firms to visit the project site, when possible, and learn more about the scope.
Notes
Attachments
Scheduled Attendees
Name Company Phone Number Email Attendance
Jon Day Anamosa State Penitentiary P: (319) 462-3504 jon.day@iowa.gov Present
Adam Douglas McGough Construction adam.douglas@mcgough.com Conference
Jon Handley McGough Construction P: (515) 805-3987 jon.handley@mcgough.com Present
Jonathan Peters McGough Construction jon.peters@mcgough.com Present
Jennie Elliott State of Iowa - Department of Administrative Services jennie.elliott@iowa.gov Present
Introduction
No. Mtg Origin Title Assignment Due Date Priority Status
1.1 1 Introductions Open
Description Attendance
Official Documented Meeting Minutes Attendees(Designers):
Innovative Engineers
ISG
Bluestone
MODUS
Shive-Hattery
Project Overview
State of Iowa - Department of Administrative Services Page 1 of 3 Printed On: Oct 19, 2023 02:40 PM CDT https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d
2.1 1 Scope Review Open
Description Living Unit C Plumbing Replacement The existing pipe chase and supply/waste/vent piping will be demoed and replaced in all 320 units. The existing toilets and lavatories will also be removed and replaced with a combination toilet/lavatory in each unit. The hot water supply piping will be replaced up to 100 feet away from the cells. The new pipe chase will be constructed steel studs and sheeting and include an access panel.
The selected design firm shall provide drawings and specifications detailing the extent of the piping replacement, details of the pipe chase and plumbing equipment, and specify new plumbing equipment and associated architectural items.
Official Documented Meeting Minutes
• The new hot water supply lines will need to be treated as an alternate. All other scope will be included in the base bid.
• The schedule and budget of the project will be dependent on the construction phasing of the project.
• Budget Range(Includes Construction and Indirect Costs): $3,794,170(13 Week Construction Duration) to $5,322,023(45 Week Construction Duration)
• A hazardous material survey will be conducted to determine if there will need to be abatement work before the base bid work begins.
2.2 1 Schedule Review Open
Description
• Questions Due to construction.procurement@iowa.gov: 10/19/23 at 2:00 PM
• Addendum Issued: Tentatively 10/20/23
• Proposals Due: 10/26/23 at 2:00 PM
• Selection of Designer/Issue NOI: Week of October 30th
• Execution of 803 Contract: Week of October 30th
• Tentative Design Kickoff Meeting: Week of November 6th
• 100% DD: Design professional to coordinate with Construction Manager
• 50% CD and budget: Design professional to coordinate with Construction Manager
• 95% CD: Design professional to coordinate with Construction Manager
• 100% CD and budget: January 8th, 2024
• Contractor Bidding: January 2024
• Execution of Contractor's Contract(s): February 2024
• Submittals and Procurement: February 2024 to April 2024
• Construction Partial Takeover: April 2024 to April 2025
• Construction Complete Takeover: April 2024 to July 2024
• Closeout: July 2024 or April 2025
Official Documented Meeting Minutes Jon Day with Anamosa stated that they would have the capacity to empty out half of Living Unit C during the construction period and would be the preferred method of phasing.
RFP Overview
3.1 1 RFP Requirements Review Open
Description
• All questions to be directed to construction.procurement@iowa.gov
Meeting #1 - RFP Pre-Proposal Project: 9354.00 DOC ASP LUC Plumbing Repairs
State of Iowa - Department of Administrative Services Page 2 of 3 Printed On: Oct 19, 2023 02:40 PM CDT mailto:construction.procurement@iowa.gov:
• DAS uses Procore online project management system for all projects, at no cost to the designer.
• DAS uses a modified ConsensusDocs 803 Form of Agreement
• DAS requires a project-specific Certificate of Insurance and specifies a Professional Liability policy of $2,000,000 with a deductible of $25,000 o Must note in proposal if deductible is different and provide a letter of financial stability from bank o Must provide COI prior to contract execution
• Ensure the following items are included in the proposal:
o Project-specific schedule o Resumes for all technical staff that will be assigned to the project o Anticipated hours and rates for each person on the design team o Lump sum broken down by schedule of values
Conclusion
4.1 1 Designer Questions Open
Description Any questions?
Official Documented Meeting Minutes It was asked if there may be additional architectural repair work that will need to be added to the scope. No exploratory demo has been performed, so any additional work should be handled on the allowance basis.
4.2 1 Site Visit Open
Description Walkthrough
• Is the amount of people present acceptable to be inside of Living Unit C?
• Please do not take any photographs with your personal cell phones. If there is something you wish to photograph, please have Jon Day with the facility photograph them. Photos can be shared via email/addendum.
• Any other questions or concerns?
Meeting #1 - RFP Pre-Proposal Project: 9354.00 DOC ASP LUC Plumbing Repairs
These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.
Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.
State of Iowa - Department of Administrative Services Page 3 of 3 Printed On: Oct 19, 2023 02:40 PM CDT