This document is an Addendum for RFP 935400-01 issued by the State of Iowa Department of Administrative Services (DAS) for the DOC Anamosa Living Unit Plumbing Repairs project. The project scope includes the replacement of hot water supply lines, plumbing fixtures, and associated components in all 320 individual cells within Living Unit C of the Anamosa State Penitentiary. The budget for the project will range from $3,794,170 for a 13-week construction period to $5,322,023 for a 45-week construction period. A hazardous materials survey will be conducted prior to the start of construction to determine if any abatement work is required. The RFP has a proposal due date of October 26, 2023, and the selected design firm is expected to be under contract by the week of October 30, 2023.

The addendum also includes details on the project schedule, with design milestones, bidding, and construction phasing information. The project will utilize a modified ConsensusDocs 803 contract, and the design firm will be required to provide a $2,000,000 professional liability policy with a $25,000 deductible. Additional details on proposal requirements, including a project-specific schedule, staff resumes, and pricing information, are also provided.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1 for RFP 935400-01

Project Name: DOC Anamosa Living Unit Plumbing Repairs

RFP #: 935400-01

DAS Project #: 9354.00

Date: 10/23/2023

Bids Due: October 26, 2023 at 2:00 p.m.

Pre-Bid Meeting Minutes and Sign-In Sheet Included

General Notes:

• The budget for the project will vary depending on the phasing of the construction. The budget will range from $3,794,170(13 Week Construction Period) to $5,322,023(45 Week Construction

Period).

• A hazardous material survey will be conducted to determine if abatement will be needed to perform the base bid scope.

Project Scope

• The replacement of the hot water supply lines will need to be separated from the rest of the project and treated as an add alternate.

Appendix 1

• Photos from Living Unit C taken during the site walkthrough.

END OF ADDENDUM

State of Iowa - Department of Administrative Services 109 SE 13th St.

Des Moines, Iowa 50319 P: (515) 281-7260

Project: 9354.00 DOC ASP LUC Plumbing Repairs 406 N High Street

Anamosa, Iowa 52205 P: 319-462-3504

RFP Pre-Proposal Minutes: Meeting #1

Meeting Date Oct 12, 2023 Meeting Time 10:00 AM - 11:00 AM Central Time (US & Canada)

Meeting Location Video Conferencing Link https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxL TgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?cont ext=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a5 4b-41d5-46ef-82bc-8260ef04c509%22%7d

Overview Meeting to allow prospective design firms to visit the project site, when possible, and learn more about the scope.

Notes

Attachments

Scheduled Attendees

Name Company Phone Number Email Attendance

Jon Day Anamosa State Penitentiary P: (319) 462-3504 jon.day@iowa.gov Present

Adam Douglas McGough Construction adam.douglas@mcgough.com Conference

Jon Handley McGough Construction P: (515) 805-3987 jon.handley@mcgough.com Present

Jonathan Peters McGough Construction jon.peters@mcgough.com Present

Jennie Elliott State of Iowa - Department of Administrative Services jennie.elliott@iowa.gov Present

Introduction

No. Mtg Origin Title Assignment Due Date Priority Status

1.1 1 Introductions Open

Description Attendance

Official Documented Meeting Minutes Attendees(Designers):

Innovative Engineers

ISG

Bluestone

MODUS

Shive-Hattery

Project Overview

State of Iowa - Department of Administrative Services Page 1 of 3 Printed On: Oct 19, 2023 02:40 PM CDT https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmE1NjBlYzUtYzk3ZC00NjcxLTgzMjgtYTkyOGQyYzgwZDVk%40thread.v2/0?context=%7b%22Tid%22%3a%22c6c429d4-d18c-4ab8-a9a8-f0c82d33f945%22%2c%22Oid%22%3a%221429a54b-41d5-46ef-82bc-8260ef04c509%22%7d

2.1 1 Scope Review Open

Description Living Unit C Plumbing Replacement The existing pipe chase and supply/waste/vent piping will be demoed and replaced in all 320 units. The existing toilets and lavatories will also be removed and replaced with a combination toilet/lavatory in each unit. The hot water supply piping will be replaced up to 100 feet away from the cells. The new pipe chase will be constructed steel studs and sheeting and include an access panel.

The selected design firm shall provide drawings and specifications detailing the extent of the piping replacement, details of the pipe chase and plumbing equipment, and specify new plumbing equipment and associated architectural items.

Official Documented Meeting Minutes

• The new hot water supply lines will need to be treated as an alternate. All other scope will be included in the base bid.

• The schedule and budget of the project will be dependent on the construction phasing of the project.

• Budget Range(Includes Construction and Indirect Costs): $3,794,170(13 Week Construction Duration) to $5,322,023(45 Week Construction Duration)

• A hazardous material survey will be conducted to determine if there will need to be abatement work before the base bid work begins.

2.2 1 Schedule Review Open

Description

• Questions Due to construction.procurement@iowa.gov: 10/19/23 at 2:00 PM

• Addendum Issued: Tentatively 10/20/23

• Proposals Due: 10/26/23 at 2:00 PM

• Selection of Designer/Issue NOI: Week of October 30th

• Execution of 803 Contract: Week of October 30th

• Tentative Design Kickoff Meeting: Week of November 6th

• 100% DD: Design professional to coordinate with Construction Manager

• 50% CD and budget: Design professional to coordinate with Construction Manager

• 95% CD: Design professional to coordinate with Construction Manager

• 100% CD and budget: January 8th, 2024

• Contractor Bidding: January 2024

• Execution of Contractor's Contract(s): February 2024

• Submittals and Procurement: February 2024 to April 2024

• Construction Partial Takeover: April 2024 to April 2025

• Construction Complete Takeover: April 2024 to July 2024

• Closeout: July 2024 or April 2025

Official Documented Meeting Minutes Jon Day with Anamosa stated that they would have the capacity to empty out half of Living Unit C during the construction period and would be the preferred method of phasing.

RFP Overview

3.1 1 RFP Requirements Review Open

Description

• All questions to be directed to construction.procurement@iowa.gov

Meeting #1 - RFP Pre-Proposal Project: 9354.00 DOC ASP LUC Plumbing Repairs

State of Iowa - Department of Administrative Services Page 2 of 3 Printed On: Oct 19, 2023 02:40 PM CDT mailto:construction.procurement@iowa.gov:

• DAS uses Procore online project management system for all projects, at no cost to the designer.

• DAS uses a modified ConsensusDocs 803 Form of Agreement

• DAS requires a project-specific Certificate of Insurance and specifies a Professional Liability policy of $2,000,000 with a deductible of $25,000 o Must note in proposal if deductible is different and provide a letter of financial stability from bank o Must provide COI prior to contract execution

• Ensure the following items are included in the proposal:

o Project-specific schedule o Resumes for all technical staff that will be assigned to the project o Anticipated hours and rates for each person on the design team o Lump sum broken down by schedule of values

Conclusion

4.1 1 Designer Questions Open

Description Any questions?

Official Documented Meeting Minutes It was asked if there may be additional architectural repair work that will need to be added to the scope. No exploratory demo has been performed, so any additional work should be handled on the allowance basis.

4.2 1 Site Visit Open

Description Walkthrough

• Is the amount of people present acceptable to be inside of Living Unit C?

• Please do not take any photographs with your personal cell phones. If there is something you wish to photograph, please have Jon Day with the facility photograph them. Photos can be shared via email/addendum.

• Any other questions or concerns?

Meeting #1 - RFP Pre-Proposal Project: 9354.00 DOC ASP LUC Plumbing Repairs

These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.

Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.

State of Iowa - Department of Administrative Services Page 3 of 3 Printed On: Oct 19, 2023 02:40 PM CDT