This Request for Proposal (RFP) #370471-DSF is issued by Fermi Forward Discovery Group (FFDG) for the fabrication of twenty-seven (27) Tunnel Transfer Line (TTL) Modules and twenty-six (26) TTL Warm Manifolds as part of the Proton Improvement Plan II (PIP-II) project at Fermi National Accelerator Laboratory. The solicitation is unrestricted, with a North American Industry Classification System (NAICS) code of 332420 for Metal Tank (Heavy) Manufacturing and a small business size standard of 750 employees.
Proposals are due by August 29, 2025, and will be evaluated using a best-value trade-off source selection process, with non-cost factors significantly more important than price. The contract will be a firm-fixed-price subcontract, with delivery terms of FOB Destination for domestic offerors and DAP Batavia, IL for non-domestic vendors. Offerors must submit a two-part proposal including a technical proposal demonstrating capabilities in cryogenic equipment fabrication, ASME coding, and specialized instrumentation, as well as a business management and price proposal. A small business subcontracting plan may be required if the awardee does not meet the small business definition and the subcontract exceeds $750,000.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP)
#370471-DSF
Tunnel Transfer Line Fabrication
July 31, 2025
Table of Contents
1. INTRODUCTION
2. INVITATION TO SUBMIT PROPOSAL
3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND SMALL
BUSINESS SUBCONTRACTING PLAN
4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION PERIOD
5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD
6. AMENDMENT OF SOLICITATION
7. PROPOSAL DUE DATE
8. LATE SUBMISSION
9. EXCEPTIONS AND DEVIATIONS
10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS
11. ORDER OF PRECEDENCE
12. SUBCONTRACT AWARD
13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS
A. PART I – TECHNICAL PROPOSAL/EVALUATION CRITERIA
B. PART II – BUSINESS MANAGEMENT & PRICE PROPOSAL
1.1. Duties/Tariffs
1.2. Milestone Payments
15. FNAL-FURNISHED PROPERTY AND MATERIALS
16. DELIVERY TERMS
17. RESTRICTION ON DISCLOSURE AND USE OF DATA
18. EXHIBITS
REQUEST FOR PROPOSAL FORM
The following requirements must be adhered to for the Offeror’s submission of Proposals to Fermi Forward Discovery Group, LLC (FFDG) in support of this specific requirement.
1. INTRODUCTION
Fermi National Accelerator Laboratory (Fermilab or FNAL), managed and operated by Fermi Forward Discovery Group, LLC (FFDG) under the prime contract with the U.S. Department of Energy (DOE), is seeking to subcontract for scope of work aligned with mission objectives.
The Proton Improvement Plan II (PIP-II) project is an essential upgrade to Fermilab’s accelerator complex to enable the world’s most intense high-energy beam of neutrinos for the international Deep Underground Neutrino Experiment at LBNF and a broad physics program, powering discoveries for many decades to come. In support of this project, FNAL requires this acquisition for the fabrication of the Tunnel Transfer Line (TTL) as defined in the Statement of Work, Exhibit A: ED0038443 PIP-II CDS TTL fabrication SoW (Exhibit A).
2. INVITATION TO SUBMIT PROPOSAL
You are invited to submit a proposal for the items specified in this Request for Proposal (RFP), by the provisions contained herein, and the terms and conditions of the proposed firm-fixed price subcontract entered into as a result of this solicitation.
3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND SMALL
BUSINESS SUBCONTRACTING PLAN
This acquisition is unrestrictive and contains no set-aside provisions. The North American Industry Classification System (NAICS) code for this solicitation is 332420, Metal Tank (Heavy) Manufacturing. The small business size standard for this NAICS code is 750 employees.
A small business subcontracting plan will be required should the awardee not meet the definition of a small business as described in the paragraph above, and the subcontract exceed $750,000.00. The Subcontracting Plan shall follow the Federal Acquisition Clause, 52.219-9, Small Business Subcontracting Plan (See Exhibit F. FL-55 - Small Business Subcontracting Plan). A draft plan must be submitted with your RFP response.
4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION PERIOD
The prospective offeror should examine and review the solicitation with care. Any prospective offeror who has questions or desires an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing by close of business (4:00 P.M. CST), August 11, 2025, and be submitted to the Procurement Specialist at the email address identified on the Request for Proposal Form and below. Oral explanations or instructions given before the award of a subcontract will not be binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation if that information is necessary for submitting proposals or if the lack of the information would be prejudicial to other prospective offerors.
Any and all changes to these specifications are valid only if they are included by a written addendum and shall become a part of the subcontract.
All questions concerning this RFP should be submitted in email form and directed to the Procurement Specialist identified below.
Procurement Specialist: Seth Fryar Phone: (630) 840-3665 Email: sfryar@fnal.gov
Fermi Forward Discovery Group, LLC Procurement Department Kirk Road & Wilson Street mailto:sfryar@fnal.gov
Batavia, IL 60510-0500
5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD
All offerors are prohibited from making any contact (including sales calls) with officials or employees of FFDG (collectively “FFDG personnel”) with regard to the request for proposals, other than in the manner and to the persons designated herein, until after an award has been made. The Chief Procurement Officer or their designee reserves the right to disqualify any offeror found to have contacted FFDG personnel in any manner regarding the proposal request.
6. AMENDMENT OF SOLICITATION
FFDG may, by addenda/amendment, modify any provision or part of this RFP at any time before the award of any resultant subcontract. All terms and conditions that are not modified remain unchanged.
An offeror shall acknowledge receipt of any addenda/amendments to this RFP. Failure to acknowledge may result in the disqualification of an offeror’s proposal with no further consideration for an award. The acknowledgment shall be provided in one of the following ways:
• Immediately upon receipt of the amendment via an email sent to the FFDG Procurement Specialist.
• Return of the Amendment with a signature on the acknowledgment signature line; or
• In the offeror’s proposal.
7. PROPOSAL DUE DATE
The offeror’s proposal shall be emailed to the Procurement Specialist no later than the close of business (4:00 P.M. CST), August 29, 2025. Partial or incomplete proposals [including required documents (e.g. project timeline, examples of prior work, references, submission of the Request for Proposal Form)] may be considered non-responsive and will not be considered for an award.
8. LATE SUBMISSION
Proposals received by FFDG after the Submittal Date and Time indicated may not be considered. The Respondent assumes the risk of the method of dispatch chosen.
9. EXCEPTIONS AND DEVIATIONS
Any exceptions to the General Terms and Conditions identified herein MUST be documented on a separate sheet on the Offeror’s Letterhead with your proposal submission. Exceptions to FFDG’s Terms and Conditions MUST be clearly and completely indicated on a company letterhead. FFDG is not required to accept any exceptions or deviations.
Any exceptions or additional terms noted on a Quote Form will not be considered and are hereby expressly rejected. Likewise, any references—whether through language or hyperlink—to additional terms and conditions are not accepted and are similarly rejected.
Offerors taking exceptions, deviations, or conditional assumptions to the specifications provided herein must clearly identify and explain each exception/deviation, or conditional assumption taken with sufficient amplification and justification to permit evaluations. Such exceptions, deviations, or conditional assumptions will not themselves automatically cause a proposal to be deemed unacceptable to FFDG. However, a large number of exceptions or one or more significant exceptions not providing benefit to FFDG may result in the rejection of the offeror’s proposal as unacceptable.
NOTE TO OFFERORS: Please be advised that any exceptions to the specifications or to FFDG’s terms and conditions may cause your proposal to be disqualified.
10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS
The offeror may submit modifications to its proposal at any time before the solicitation closing date and time and may submit modifications in response to an amendment or to correct a mistake at any time before award.
Proposals may be withdrawn at any time before the submission deadline. Withdrawals are effective upon receipt of notice by the Procurement Specialist.
11. ORDER OF PRECEDENCE
Where there appear to be variances or conflicts, the following order of precedence shall prevail: FFDG’s drawings (if applicable), FFDG’s Statement/Scope of Work, and the RFP General Terms and Conditions.
12. SUBCONTRACT AWARD
Issuance of the RFP does not compel FFDG to make an award. FFDG reserves the right to accept or reject all proposals if that is determined to be in its best interest. A decision may be made without discussion; hence, an offeror’s proposal should be submitted initially on the most favorable terms. The proposed award is based on a continuing program requirement and the issuance of obligation authority from the Procurement Department of the Fermi National Accelerator Laboratory (FNAL). Any subsequent award issued by FFDG shall be constituted in writing by authorized representatives of the Procurement Department of the FNAL.
No other representatives of FFDG are authorized to issue contracts or agreements or bind FFDG to any form of agreement or understanding. The authorized Procurement Department official of the FNAL is the only individual who can legally commit FFDG to the expenditure of funds in connection with this proposed procurement.
13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS
This is a best-value trade-off source selection. This process permits tradeoffs between cost or price and non-cost factors. As a result, FFDG will accept an offer based on the totality of the proposal, not simply based on the lowest-priced proposal. All evaluation factors other than cost or price, when combined, are significantly more important than cost or price. An award shall be made to the offeror who is deemed most responsive and responsible by FFDG, whose proposal conforms to the solicitation’s requirements and is judged to represent the best value to FFDG. FFDG intends to award without discussions. FFDG shall be the sole determiner of what is of the best value to FFDG.
FFDG reserves the right to cancel this solicitation at any time without incurring any liability or damages associated with such cancellation.
Under no circumstances shall FFDG be responsible for any proposal preparation expenses, submission costs, or any other expenses, costs, or damages, of whatever nature, incurred as a result of an offeror’s participation in this RFP process. The Offeror understands and agrees that it submits its proposal at its own risk and expense and releases FFDG from any claim for damages or other liability arising out of the RFP and award process.
FFDG shall not be liable for any errors in the offeror’s proposal submission. Except during negotiations initiated by FFDG, no modifications to the proposal shall be accepted from the offeror after the Submittal Date. The offeror is responsible for a careful review of their entire proposal to ensure that all information, including pricing, is correct and complete. Offerors are liable for all errors or omissions contained in their proposals.
FFDG reserves the right to award a subcontract only to responsive and responsible proposers. Responsive offers are defined as a proposal that meets all of the minimum requirements (e.g. submits all required documents, meets minimum years requirement, etc.). Responsible proposers are defined as companies that demonstrate the financial ability, resources, skills, capability, willingness, and business integrity necessary to perform on the subcontract. FFDG shall be the sole determiner of whether an offer or Offeror is considered responsive and/or responsible.
The proposal shall be submitted in two (2) parts: Part I - Technical Proposal and Part II –
Business/Management Proposal. Under no circumstances shall Part I and Part II be bound together or presented in such manner as to make them not severable. The Technical Proposal shall not contain any reference to cost other than what is referenced in Current/Past Projects.
Any information of a proprietary nature shall be CLEARLY MARKED and identified in the offeror’s submission.
Offerors shall explain, provide support, and address each of the Evaluation Criteria below, which will assist FFDG in the Source Selection process. All information shall be provided in a clear and organized manner.
Additionally, Offerors may state any recommendations or areas of concern related to the scope of work requirements in their proposals.
A. Part I – TECHNICAL PROPOSAL/EVALUATION CRITERIA
As part of the Technical Proposal submission, offerors are required to complete and return the Technical Questionnaire included with this RFP (Exhibit D. Technical Questionnaire).
Offerors shall provide information for the following technical criteria to enable FFDG to evaluate technical capability.
NOTE: A full list of required documents for the Technical Proposal is provided in the Statement of Work (Exhibit A, Section 5.1, Bidding Phase).
1. Technical Merit & Quality
The Technical Proposal must demonstrate the Offeror’s capability to perform the fabrication, assembly, and testing of the PIP-II Tunnel Transfer Line in accordance with the Statement of Work (Exhibit A). Offerors must address the following evaluation factors:
• Overall Quality of Proposal - Offerors are to submit a detailed technical proposal that demonstrates the ability of the Offeror to deliver the assembly with performance that meets or exceeds the Statement of Work (Exhibit A).
• Technical Capabilities, Experience, and Infrastructure – Offerors are to include documentation showing technical capabilities, staffing level and experience, and infrastructure to fabricate, assembly, and perform all factory acceptance tests specified in Statement of Work (Exhibit A).
• Quality Assurance and other Plans - Offerors are to include copies of:
o Quality Assurance Plan o Detailed plan on how FNAL provided parts will be inventoried and stored o Sample shipping and handling plan
2. Past Experience
Offeror shall provide documentation demonstrating experience with projects of a similar size, scope, and complexity. At minimum, the offeror shall submit three (3) relevant examples from the past ten (10) years for each of the following criteria:
• Building ASME Equipment – Offerors are to include documents showing their past experience supplying ASME qualified normal fluid piping systems and ASME coded pressure vessels for superfluid helium service.
• Working with Specialized Cryogenic Instrumentation - Offerors are to include documentation showing experience of instrumenting cryogenic systems with specialized cryogenic thermometry, vacuum feedthroughs, liquid helium level probes; integrating cryogenic control valves with piping and vacuum components.
• Supplying Cryogenic Equipment of Similar Scale and Complexity – Offerors are to include documentation showing past experience of supplying vacuum insulated, multi-line, distribution modules for cryogenic helium at the level of scale and complexity similar to PIP-II Tunnel Transfer Line.
Each example shall include the following:
• Customer name;
• Project Name and Location;
• Project Description;
• Total Contract Amount;
• Contracted project schedule duration;
• Project Start and Completion Date. If a current project, please provide the Percent (%) complete and the projected completion date.
• Examples of documentation
3. Management Control Plan
Provide documentation to demonstrate the ability to ensure the required quality standard throughout the entire execution of the project. Examples of documentation developed for past projects (within the last five years) viz. Quality Control Plan, Manufacturing Inspection Plan, Factory Acceptance Verification Matrix, which demonstrate the ability of performing inspection and testing will be considered for the technical evaluation.
4. Delivery Schedule and Milestones Offerors are to submit a Gantt chart or similar document showing a detailed schedule that meets the milestones timeline and lot-wise delivery timeline as defined in Statement of Work (Exhibit A).
B. Part II – BUSINESS MANAGEMENT & PRICE PROPOSAL The Business Management and Price proposal submitted shall include, at a minimum, the following documentation:
1. Price Proposal
The proposed pricing of each TTL Module and each TTL Warm Manifold shall be specified on the Request For Proposal Form provided herein. THE OFFEROR MUST SUBMIT THEIR
PRICING USING THE FORM PROVIDED HEREIN.
If a subcontract is awarded to the offeror, payment shall be issued upon delivery, inspection, testing (if applicable) and acceptance of each TTL Module and TTL Warm Manifold as defined on the Request for Proposal Form, pursuant to the General Terms and Conditions, and the Statement of Work as identified herein.
The proposed pricing shall be a firm-fixed price (FFP) for the work as identified herein, and the price proposal shall be valid for 90 days from the final proposal due date. An Offeror allowing less than the minimum acceptance period as identified herein may be rejected without further consideration for an award.
All pricing must be submitted in USD, and no allowances shall be made for currency conversion during the term of the subcontract. As a FFP contract, no adjustments for fluctuation in currency will be allowed under this subcontract.
Economic price escalation language will not be accepted or considered.
FFDG may consider a proposal nonresponsive if the prices proposed are materially unbalanced.
A proposal is considered materially unbalanced when the price of one or more line items in a submission is significantly overstated or understated, even though the total price may be acceptable when reviewing using cost or price analysis techniques. This would include a reasonable doubt that the proposal will result in the lowest overall cost to FFDG, even though it may be the lowest evaluated proposal, or if it is so unbalanced as to be tantamount to allowing an advance payment.
When applicable, FFDG will reimburse the subcontractor for actual costs (e.g., freight, pre-pay and add) incurred. No allowance shall be made for overhead and profit; any invoice containing overhead, profit, surcharges, handling costs, etc., will be rejected.
1.1. Duties/Tariffs
FFDG recognizes that international shipments may be subject to additional charges related to duties and tariffs. Accordingly, proposed pricing shall exclude duties and tariffs. Shipping terms shall be DAP with the Subcontractor responsible for all shipping and handling costs to Batavia, Illinois. FNAL will be responsible for payment of any duties. FNAL will provide its designated customs broker information to the Subcontractor following award and prior to shipment.
1.2. Milestone Payments
FFDG may, at its discretion, consider milestone payments as part of the award determination process. If an offeror wishes to propose milestone payments, such requests must be clearly identified in the original pricing proposal and accompanied by detailed terms and justification. Milestone payment proposals will be evaluated as part of the overall proposal review.
FFDG reserves the right to accept, negotiate, or decline milestone payments if they are not deemed to be in the best interest of FNAL. FNAL may reject any proposal that includes milestone payments if such terms are determined to introduce undue risk, administrative burden, or misalignment with project objectives.
2. Subcontractor Annual Representations & Certifications (SARC), Form SARC The SARC certification submitted by the successful Offeror will be incorporated into the subsequent subcontract. If an offering entity is a joint venture, association, consortia, or partnership, each member entity must submit an individual Representations and Certifications Form (Exhibit G).
3. Proposal Certifications, Form PUR-466 The PUR-466 certification submitted by the successful Offeror will be incorporated into the subsequent subcontract. All sections are required to be completed and must be signed by a company official (Exhibit H).
14. DESCRIPTION OF WORK
The selected subcontractor shall provide all labor, materials, tools, equipment, and supervision required to complete all work to fabricate the twenty-seven (27) TTL Modules and twenty-six (26) Warm Manifolds as defined as follows:
• Exhibit A: ED0038433 PIP-II CDS TTL Fabrication SoW
• Exhibit B: Drawings (Provided Upon Request)
The awarded offeror shall deliver the specified quantities of TTL Modules and Warm Manifolds in full compliance with the fabrication requirements outlined in the referenced specifications and drawings. All fabrication shall follow the approved quality control plan and will be subject to the acceptance criteria defined herein.
15. FNAL-FURNISHED PROPERTY AND MATERIALS
Fermilab will provide the awarded subcontractor with documents, components, instrumentation, and subassemblies identified in Section 4.1.2 of the Statement of Work (Exhibit A) for integration with the Tunnel Transfer Line (TTL) Modules and TTL Warm Manifolds.
These items are government-owned and Fermilab-supplied. Title to all Fermilab-furnished property remains with the Government.
The subcontractor shall:
• Use the property exclusively in performance of this subcontract;
• Inspect and accept the property upon receipt in accordance with the applicable procedures outlined in
Sections 6 and 7 of the SOW;
• Store the property securely and in accordance with all industry and project-specific requirements;
• Maintain adequate property control records and make such records available to Fermilab upon requests;
and
• Notify Fermilab promptly of any loss, damage, or conditions that may affect the integrity or usability of the property
For all components that FNAL will supply to the subcontractor, the subcontractor shall be responsible for clearing all customs and import procedures at the receiving port of entry. Offeror shall include the expected cost of this administrative clearance in their response to FNAL Request for Proposal. The value of FNAL- Supplied components for proposal purposes will be provided upon request to the Procurement Specialist (Seth Fryar, sfryar@fnal.gov) and will be provided in USD.
The subcontractor assumes risk of loss or damage to Fermilab-furnished property upon delivery, except for reasonable wear and tear or as otherwise provided under this subcontract. Any unused Fermi-lab furnished materials will be cataloged and returned to Fermilab or otherwise disposed of in accordance with Fermilab’s written instructions.
16. DELIVERY TERMS
A shipping readiness review will be required prior to each shipment as described in the Statement of Work (Exhibit A).
Delivery terms shall be FOB Destination Fermilab Dock Batavia, IL 60510 for domestic offerors, which shall include shipping/freight costs within their firm-fixed-price proposal submission.
Delivery terms shall be DAP, Batavia IL per Incoterms 2020 for non-domestic vendors. Non-domestic offerors will be provided with FFDG’s Customs Clearance Broker Information upon subcontract award.
The Subcontractor shall handle and transport the assembled and fully tested 27 TTL Modules and 26 TTL Warm Manifolds to Fermilab site in strict adherence to the Statement of Work (Exhibit A., Section 10, Shipping and Handling).
Deliverables will be subject to an acceptance period in accordance with (IAW) with the Statement of Work (Exhibit A, Section 8.2 – Site Acceptance Tests).
The Offeror must include their shipping/freight costs on the Price Submission Sheet within their proposal.
17. RESTRICTION ON DISCLOSURE AND USE OF DATA
Offerors or quoters who include in their proposals or quotations data that they do not want to be disclosed to the public for any purpose or used by FFDG except for evaluation purposes, shall –
A. Mark the title page with the following legend:
“This proposal or quotation includes data that shall not be disclosed outside FFDG and shall not be duplicated, used, or disclosed – in whole or in part – for any purpose other than to evaluate this proposal or quotation. If, however, a subcontract is awarded to this Offeror or quoter as a result of – or in connection with – the submission of this data, FFDG shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting subcontract. This restriction does not limit FFDG’s right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets (insert numbers or other identification of sheets)”, and
B. Mark each sheet of data it wishes to restrict with the following legend “Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal or quotation.”
18. EXHIBITS
A. ED0038433 PIP-II CDS TTL fabrication SoW B. Drawings Package (Provided Upon Request)
C. GENERAL TERMS AND CONDITIONS FOR SUPPLIES (1/2025)
D. Technical Questionnaire E. Price List of FNAL Supplied Components (Provided Upon Request) F. FL-55 – Small Business Subcontracting Plan G. Subcontractor Annual Representations & Certifications (SARC) H. Proposal Certifications, Form PUR-466 I. Sample Subcontract
Fermi National Accelerator Laboratory Procurement Department Finance Section 630.840.3665 sfryar@fnal.gov
DATE: 07/31/2025
DUE DATE: 08/29/2025
RFP#: 370471-DSF
REQUEST FOR PROPOSAL FORM
ITEM QTY DESCRIPTION UNIT PRICE
TOTAL
(USD) DEL. DATE
Fermilab requests your firm-fixed-price proposal for the following items per the terms and conditions referenced herein.
1 27 TTL Modules 2 26 TTL Warm Manifolds
3 1 Shipping Costs
NAICS: 332420
Size STD: 750 Employees
ANY AND ALL exceptions to specifications and/or extra charges for containers, tooling, etc. MUST be clearly indicated.
COMPANY NAME ___________________________________ MATERIALS, SUPPLIES OR SERVICES RESULTING FROM THE QUOTE ADDRESS ____________________________________ ARE FOR WORK DONE UNDER PRIME CONTRACT#DE AC02-07CH11359 TERMS NET 30 FOB/INCO; DEST/DAP WITH THE UNITED STATES DEPARTMENT OF ENERGY. ANY ITEMS SUBMITTED BY ___________________________________ COVERED BY G.S.A. CONTRACTS SHOULD ALSO BE INDICATED.
DATE SUBMITTED __________________________________
| 1. INTRODUCTION |
| 2. INVITATION TO SUBMIT PROPOSAL |
| 3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND SMALL BUSINESS SUBCONTRACTING PLAN |
| 4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION PERIOD |
| 5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD |
| 6. AMENDMENT OF SOLICITATION |
| 7. PROPOSAL DUE DATE |
| 8. LATE SUBMISSION |
| 9. EXCEPTIONS AND DEVIATIONS |
| 10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS |
| 11. ORDER OF PRECEDENCE |
| 12. SUBCONTRACT AWARD |
| 13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS |
| A. Part I – TECHNICAL PROPOSAL/EVALUATION CRITERIA |
| B. Part II – BUSINESS MANAGEMENT & PRICE PROPOSAL |
| 1.1. Duties/Tariffs |
| 1.2. Milestone Payments |
| 15. FNAL-FURNISHED PROPERTY AND MATERIALS |
| 16. DELIVERY TERMS |
| 17. RESTRICTION ON DISCLOSURE AND USE OF DATA |
| 18. EXHIBITS |
| REQUEST FOR PROPOSAL FORM |