About this file
This document is a Tenant Guidebook issued by the Capital Region Airport Commission for Richmond International Airport that establishes mandatory standards for public-facing construction walls, graphics, passenger information, and interactive engagement elements during concession development, renovation, relocation, and capital improvement projects. The guidebook applies to all concessionaire-managed construction projects with public-facing walls and establishes binding requirements that concessionaries must follow at their sole cost and expense. The document does not specify response dates, due dates, site visits, bidder conferences, award dates, or contract terms, as it functions as an operational standard rather than a procurement solicitation. Instead, it provides ongoing requirements that apply throughout the construction phase of concession projects at Richmond International Airport.
The guidebook mandates specific performance standards including the use of reusable modular temporary wall systems (unless alternative systems receive written approval), coverage of at least 75 percent of public-facing surfaces with professionally designed high-resolution graphics, inclusion of required passenger information with Commission-approved renderings, and incorporation of a minimum of three Commission-approved interactive passenger engagement elements on each public-facing wall. All construction walls, graphics, QR codes, digital links, and engagement elements must be maintained in first-class condition throughout construction. The guidebook requires joint written approval from Properties & Concessions, Marketing, and Airport Operations before fabrication or installation, with submission requirements including wall layouts, complete graphic packages, messaging content, QR-code destinations, digital links, and all three required engagement elements. Non-compliance remedies include rejection of submitted materials, removal and replacement at the concessionaire's expense, suspension of construction approvals, project delays, and administrative fees as permitted under applicable lease agreements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 1
RIC
TENANT
GUIDEBOOK
Construction Experience & Interactive Passenger Engagement
CAPITAL REGION AIRPORT COMMISSION
Richmond International Airport
FINAL DRAFT FOR COMMISSION REVIEW
PASSENGER EXPERIENCE BY DESIGN
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 2
How to Use This Guide
This guidebook establishes Richmond International Airport requirements for public-facing concession construction walls, construction presentation, passenger information, and interactive passenger engagement. It is intended for concessionaires, designers, general contractors, fabricators, marketing teams, and other project participants.
CONTROLLING REQUIREMENTS
This guidebook supplements, and does not replace, the Capital Region Airport Commission Tenant Construction Improvements Manual, applicable lease requirements, approved construction documents, or official directions issued by Airport Operations and Airport Security. If a conflict occurs, the controlling agreement, approved construction document, or official Commission requirement shall govern.
Core Requirements
• Use a reusable modular temporary construction wall system unless an alternate system is approved in writing.
• Cover at least 75% of all public-facing wall surfaces with approved, professionally designed high-resolution graphics.
• Include the required passenger information and Commission-approved concept rendering.
• Provide a minimum of three (3) Commission-approved interactive passenger engagement elements on each public-facing construction wall.
• Obtain joint written approval from Properties & Concessions, Marketing, and Airport Operations before fabrication or installation.
• Maintain walls, graphics, QR codes, digital links, and engagement elements in first-class and fully functional condition.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 3
1 | Commission Design Philosophy
The Capital Region Airport Commission believes construction should inspire anticipation and not create disruption.
Every concession development project represents an investment in the future passenger experience at Richmond International Airport.
Temporary construction walls shall be treated as an extension of the Airport’s customer experience strategy. They shall protect passengers, preserve Commission assets, maintain a professional appearance, and actively engage travelers through compelling graphics, storytelling, and interactive marketing opportunities.
GUIDING PRINCIPLE
Passenger Experience by Design
Every element of the airport environment, including temporary construction, shall reinforce this commitment.
Construction walls should introduce the future concession, build customer awareness, support recruitment, strengthen loyalty, and contribute positively to the passenger journey.
Applicability These standards apply to public-facing concession development, renovation, relocation, and capital improvement projects. Each public-facing construction wall shall be professionally designed, installed, maintained, and removed by the concessionaire at its sole cost and expense.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 4
2 | Reusable Modular Temporary Construction Walls
2.1 Performance Requirement
The Commission requires reusable modular temporary construction wall systems for public-facing concession construction projects unless an alternate barricade system is approved in writing. Proposed systems shall be suitable for occupied airport environments and satisfy Commission performance, operational, safety, security, graphic application, and aesthetic requirements.
• Protect existing airport facilities and finishes.
• Minimize disruption to passengers and airport operations.
• Reduce construction waste and support sustainable building practices.
• Provide a clean, professional surface for graphics and passenger engagement.
• Support efficient installation, relocation, reconfiguration, and removal.
2.2 Manufacturer-Neutral Examples
Examples of commercially available modular systems include:
• STARC Systems®
• SwiftWall®
• EverPanel®
• EverBlock® Modular Wall Systems
• Other Commission-approved systems providing equivalent appearance, performance, and safety.
NO ENDORSEMENT OR SOLE SOURCE
Manufacturers are listed solely as examples. Inclusion does not constitute a Commission endorsement, purchasing preference, approved-vendor designation, or sole-source requirement.
2.3 Procurement Options
• Direct purchase by the concessionaire.
• Direct purchase by the general contractor.
• Specialty subcontractor installation.
• Short-term rental or lease program.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 5
2 | Modular Walls, Continued
Protection of Commission Assets
Freestanding systems can reduce drilling, anchoring, and penetrations into terrazzo, tile, stone, and other finished surfaces.
Professional Passenger Experience
Factory-manufactured systems provide clean, uniform surfaces appropriate for an active airport environment.
Marketing Platform
Smooth surfaces support large-format graphics, renderings, brand storytelling, and interactive content.
Construction Flexibility
Systems may be expanded, relocated, or reconfigured as construction phasing changes.
Sustainability
Reusable systems reduce disposal of lumber, drywall, fasteners, and similar temporary materials.
2.4 Alternate-System Requests
The Commission may approve an alternate temporary barricade system when project conditions warrant an exception. Written requests shall demonstrate an equivalent or superior level of:
• Passenger protection
• Professional appearance
• Structural stability
• Security
• Operational compatibility
• Graphic application capability
• Protection of existing airport infrastructure
Approval of an alternate system is at the sole discretion of the Capital Region Airport Commission.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 6
3 | Construction Wall Design Standards
3.1 Appearance and Graphic Coverage
• Fully wrap public-facing walls with professionally designed, high-resolution graphics.
• Cover a minimum of seventy-five percent (75%) of all public-facing surfaces with approved graphics.
• Maintain a clean, first-class appearance throughout construction.
• Use materials suitable for a commercial airport environment.
• Keep surfaces free of tears, wrinkles, fading, peeling, and damage.
• Provide smooth surfaces capable of supporting large-format graphics and branding.
PROHIBITED CONDITIONS
Temporary paper signs, handwritten notices, exposed framing, unfinished plywood, pixelated graphics, and unapproved advertising are prohibited.
3.2 Required Passenger Information
• Approved concession name and logo.
• Prominent COMING SOON messaging.
• Full-color rendering of the Commission-approved concession concept.
• Anticipated opening timeframe, when reasonably known.
• Brief concept description.
• Brand story or history.
• Local ownership or Virginia connections, where applicable.
• Community partnerships, sustainability initiatives, or Virginia suppliers, where applicable.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 7
4 | Mandatory Interactive Passenger Engagement
MINIMUM THREE-ELEMENT STANDARD
Each public-facing construction wall shall incorporate a minimum of three (3) Commission-approved interactive passenger engagement elements. This requirement is mandatory. All three elements shall remain fully functional throughout construction and shall be maintained at the concessionaire’s sole cost and expense.
Customer Engagement Official website; rewards enrollment; mobile app; email or SMS registration; opening notifications or RSVP.
Employment Join Our Team messaging; current job openings; employment application portal; career information.
Social Media Instagram; Facebook; TikTok; LinkedIn; YouTube; other Commission-approved platforms.
Brand Discovery Menu preview; signature offerings; featured merchandise; brand story; Meet the Chef, Founder, Franchise Owner, or Operator; Virginia products.
Promotions Opening promotions; exclusive offers; loyalty incentives; legally permitted campaigns; digital coupons.
Community Engagement Community partnerships; Virginia suppliers; sustainability initiatives; charitable partnerships.
Construction Progress Project updates; opening countdown; behind-the-scenes video; “Watch Us Come to Life” content.
The listed opportunities are examples. The Commission may approve other engagement elements that support passenger experience objectives and are appropriate for the project.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 8
5 | QR Code and Digital Experience Standards
Where QR codes or other digital links are used as engagement elements, they shall:
• Direct passengers to an active and fully functional webpage or digital experience.
• Be tested before fabrication and installation.
• Remain functional throughout construction.
• Be appropriately sized and positioned for convenient passenger use.
• Be replaced or corrected immediately if damaged, inactive, or inoperable.
NON-COMPLIANCE
Broken links, inactive webpages, and non-functional QR codes constitute non-compliance.
Engagement Planning Record
Element Destination / Experience
Responsible Party Test Status
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 9
6 | Joint Commission Review and Approval
Before fabrication or installation, the concessionaire shall submit the complete package for joint review and written approval by Properties & Concessions, Marketing, and Airport Operations. No covered material may be fabricated or installed until the required written approval has been received.
Required Submittal Components
• Construction wall layout and dimensions.
• Complete graphic package.
• Architectural renderings.
• Messaging and marketing content.
• QR-code destinations and digital links.
• All three required interactive passenger engagement elements.
• Websites, promotional campaigns, loyalty programs, employment pages, and social media links, as applicable.
• Anticipated opening timeframe.
SCOPE OF JOINT REVIEW
Joint review applies to all public-facing graphics, renderings, messaging, marketing content, QR-code destinations, digital links, and interactive engagement elements. Properties & Concessions, Marketing, and Airport Operations may require revisions for consistency with Commission branding, passenger experience objectives, accessibility standards, security requirements, and operational requirements.
Submission Record
Field Tenant Entry
Concession / Concept
Project Location
Tenant Contact
Designer / Fabricator
General Contractor
Submission Date
Joint Approval Date
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 10
7 | Maintenance and Compliance
7.1 Ongoing Maintenance
• Replace damaged graphics immediately.
• Repair tears, wrinkles, peeling vinyl, fading, or other deterioration.
• Maintain all three required engagement elements in fully functional condition.
• Maintain operational QR codes and active digital links.
• Update opening dates when schedules change.
• Refresh messaging for projects exceeding ninety (90) days.
• Ensure digital content remains accurate and appropriate.
7.2 Compliance Remedies
Failure to comply may result in:
• Rejection of submitted graphics or engagement content.
• Removal and replacement of non-compliant materials at the concessionaire’s expense.
• Suspension of construction approvals or inspections.
• Delays in project acceptance or opening.
• Administrative fees or other remedies available under the applicable lease agreement.
The Commission reserves the right to require corrective action whenever construction walls fail to meet these standards or are inconsistent with Richmond International Airport passenger experience objectives.
CLOSING STANDARD
Construction walls shall serve not only as temporary barriers, but as professional, engaging, and informative customer experiences reflecting the Commission’s commitment to innovation, hospitality, and operational excellence.
RICHMOND INTERNATIONAL AIRPORT | TENANT GUIDEBOOK - Rev Sept 2026 | 11
Appendix A | Final Consistency Checklist
☐ The guidebook states that it supplements, and does not replace, the Tenant Construction Improvements Manual, lease requirements, approved construction documents, or official directions from Airport Operations and Airport Security.
☐ The conflict provision states that the controlling agreement, approved construction document, or official Commission requirement governs.
☐ Every reference describes three (3) Commission-approved engagement elements as a mandatory minimum for each public-facing construction wall.
☐ No language describes pre-opening passenger engagement as merely encouraged, suggested, preferred, or optional.
☐ All three elements are required to remain functional throughout construction.
☐ Manufacturer examples are clearly non-exclusive and do not constitute endorsement, purchasing preference, or sole-source direction.
☐ Joint review and written approval by Properties & Concessions, Marketing, and Airport Operations is required before fabrication or installation.
☐ The approval requirement covers graphics, renderings, messaging, QR-code destinations, digital links, and engagement elements.
☐ Maintenance and compliance provisions expressly apply to all three required engagement elements.
Appendix B | Tenant Pre-Fabrication Checklist
☐ Reusable modular wall system selected, or written alternate-system request prepared.
☐ Wall dimensions and public-facing surfaces confirmed.
☐ At least 75% approved graphic coverage shown.
☐ Required passenger information included.
☐ A minimum of three Commission-approved engagement elements identified for each public-facing wall.
☐ All QR codes and digital destinations tested.
☐ Complete package submitted for joint review by Properties & Concessions, Marketing, and Airport Operations.
☐ Written approval received before fabrication or installation.
| How to Use This Guide |
| Core Requirements |
| 1 | Commission Design Philosophy |
| Applicability |
| 2 | Reusable Modular Temporary Construction Walls |
| 2.1 Performance Requirement |
| 2.2 Manufacturer-Neutral Examples |
| 2.3 Procurement Options |
| 2 | Modular Walls, Continued |
| Protection of Commission Assets |
| Professional Passenger Experience |
| Marketing Platform |
| Construction Flexibility |
| Sustainability |
| 2.4 Alternate-System Requests |
| 3 | Construction Wall Design Standards |
| 3.1 Appearance and Graphic Coverage |
| 3.2 Required Passenger Information |
| 4 | Mandatory Interactive Passenger Engagement |
| Customer Engagement |
| Employment |
| Social Media |
| Brand Discovery |
| Promotions |
| Community Engagement |
| Construction Progress |
| 5 | QR Code and Digital Experience Standards |
| Engagement Planning Record |
| 6 | Joint Commission Review and Approval |
| Required Submittal Components |
| Submission Record |
| 7 | Maintenance and Compliance |
| 7.1 Ongoing Maintenance |
| 7.2 Compliance Remedies |
| Appendix A | Final Consistency Checklist |
| Appendix B | Tenant Pre-Fabrication Checklist |
File details come from the government source that posted it. Updated .