This is Addendum No. 1 to Request for Proposal 26-009-FH issued by the City of Altamonte Springs, Florida (Seminole County) for CraneRIDES Operator Services, dated February 11, 2026. The addendum extends the proposal submission deadline from February 17, 2026 at 11:00 a.m. ET to February 24, 2026 at 11:00 a.m. ET, providing respondents with an additional one-week extension. The City seeks a qualified contractor to provide turnkey autonomous vehicle shuttle operator services, including vehicle procurement and deployment, charging infrastructure installation and maintenance, daily operations with staffing, and integration of real-time tracking and mobile applications. The service will operate along a 4.4-mile fixed-route corridor with six currently established ADA-accessible stops, expandable to twelve permanent stops, operating seven days per week from 7:00 a.m. to 9:00 p.m. Monday through Friday and 10:00 a.m. to 2:00 p.m. and 4:00 p.m. to 10:00 p.m. on weekends. The contract award is scheduled for the City Commission's regularly scheduled March 2026 meeting, with an effective date of July 1, 2026 and a transition period from April 6 through June 30, 2026. The initial contract term spans one year with options to extend for four additional one-year terms, not to exceed five years total, contingent upon mutual agreement.
The addendum clarifies critical service requirements and operational parameters through thirteen questions and corresponding answers. Key clarifications include confirmation that service uptime requirements maintain a minimum 95% standard, establishment of operating hours as specified above, and confirmation that the City will integrate standardized transit data feeds (GTFS and GTFS-RT) while the selected vendor supports integration and coordination efforts with partner agencies including FDOT and Seminole County. The contractor bears responsibility for identifying infrastructure needs to support operations, including charging and storage infrastructure, and must provide operational approaches and technical solutions that safely serve the project area with appropriate redundancy and continuity of operations, including fallback strategies when desired signal integrations or connectivity are unavailable. The City retains responsibility for ADA compliance maintenance and route signage, while the vendor is responsible for relaying ADA concerns or issues to the City. Temporary route modifications remaining within contracted scope may be handled operationally through coordination with the City, though modifications that change the contractual scope, deliverables, or requirements may require a contract amendment or change order. Compensation will be structured on an hourly basis consistent with actual hours worked, with proposals required to submit annual fixed fees for each of the five contract years and a grand total amount for the entire contract period, though specific budget ranges or award values are not disclosed.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP-26-009-FH
CraneRIDES Operator Services
Addendum No. 1
DATE: February 11, 2026 TO: All Respondents and Interested Parties FROM: Fabio Henao, CPO
Be advised of the following changes, additions, deletions, information, and/or clarifications to the subject solicitation. Only written questions answered in writing by formal Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Questions received after the due date for questions will not be given any consideration. Respondents are reminded to review the original solicitation and all issued addenda, if applicable. Respondents must acknowledge all issued addenda, if any. Failure to acknowledge may result in the Respondent’s submittal being deemed non-responsive.
The Solicitation is hereby changed accordingly:
A. THE DUE DATE FOR THE PROPOSALS IS HEREBY EXTENDED AS LISTED BELOW:
From: February 17, 2026, by 11:00 a.m. ET
TO: FEBRUARY 24, 2026, BY 11:00 A.M. ET
B. QUESTIONS RECEIVED:
Q1: What is the desired timeline for the start of on-demand service and all associated requirements like GTFS-Flex?
A1: There is no timeline at the moment for on-demand services. The requirements and expectations for on-demand service, including any GTFS-Flex-related deliverables are addressed in the Solicitation Exhibits, including Exhibit A and Exhibit D. Bidders shall base their response on those Exhibits.
Q2: When is the East Altamonte route expansion expected to be added to the route network?
A2: There is no timeline at the moment for the East Altamonte route expansion. The implementation shall be in accordance with the contact and the requirements identified in the Solicitation Exhibits. Bidders should assume the City will coordinate final implementation timing with the selected vendor. The Bidder should include the operational and capital cost and project plan associated with the operation of the East Altamonte Route in addition to main CraneRIDES route.
Q3: Under Quality of Service, service uptime of 99% is mentioned, but under Service Uptime and Continuity, a minimum of 95% uptime is required. Can the City please clarify the discrepancy between the two?
A3: Quality-of-service performance requirements shall maintain a minimum 95% uptime.
Q4: What are the expectations of the required LED lighting features on the exterior?
A4: Bidders shall address lighting/visibility features as part of the Project Aesthetics requirement and provide renderings and narrative describing the proposed treatment (including embedded lighting, as applicable).
Q5: Do all vehicle requirements, like passenger capacity, apply to future fleets for use cases like on-demand? If not, are there any vehicle requirements applicable to on-demand?
A5: Vehicle requirements (including any future fleet and/or on-demand service needs) are defined in the Solicitation scope requirements, including Exhibit A. Bidders must include vehicle specifications, operational assumptions, and any supporting systems/infrastructure needed to deliver the service. Requirements outlined in the RFP are the requirements at the current state for the entire fleet.
Q6: How does the City define redundancy requirements for signal phases?
A6: Seminole County maintains the traffic signals within the project area. The City cannot require Seminole County to install, modify, or add third-party equipment at County-maintained signal locations. Proposers shall not assume that additional signal equipment, communication devices, or other infrastructure will be installed by the County to support the service.
It is the Contractor’s responsibility to provide an operational approach and technical solution that safely serves the project area with appropriate redundancy and continuity of operations. The proposed solution shall account for existing field conditions and third-party constraints and include fallback/safe-mode strategies to maintain safe operations when desired signal integrations or connectivity are not available.
Q7: What are the anticipated hours of operation for the 7-day service schedule?
A7: Operating days and service expectations are defined clearly in the scope requirements in Exhibit A. Bidders shall include the proposed staffing plan, service delivery approach, and hours of operation consistent with those requirements and stated here: Monday through Friday from 7:00AM to 9:00PM and weekends from 10:00AM to 2:00PM and 4:00PM to 10:00PM.
Q8: Will the City contract with FDOT and Seminole County for integration or would that fall to the vendor?
A8: The City will manage coordination with partner agencies (including FDOT and Seminole
County) as needed. The selected vendor will be responsible for supporting integration and coordination efforts required to deliver the services described in the RFP scope and contract requirements.
Q9: Please confirm that the City plans to integrate standardized transit data feeds (e.g., GTFS and GTFS-RT) to support their internal website updates such as service alerts and detours.
A9: Yes. GTFS-related deliverables are included in the Solicitation package. Bidders shall comply with the requirements in Exhibit D and any associated scope requirements in Exhibit A.
Q10: Please confirm that temporary route modifications for construction, extensions, or special events are expected to utilize routes mapped as part of the initial core service launch, and that any additional routing not previously mapped will require a change order.
A10: Temporary route modifications that remain within the contacted scope may be handled operationally through coordination with the City. Modifications that change the contractual scope, deliverables, or requirements may require a contract amendment/ change order consistent with the Solicitation and resulting agreement. The Proposer/Contractor is responsible for maintaining continuous service delivery. During special events or other conditions that result in roadway or access closures, the Contractor shall implement an alternate “event route” or detour routing necessary to maintain safe, reliable operations and passenger access to the extent practicable. The Contractor is responsible for proactively identifying potential conflicts (including planned road closures, event impacts, and temporary access restrictions), coordinating with the City as needed, and ensuring the service remains operational.
Temporary routing changes made to preserve operations during events and closures may be implemented without a contract amendment provided the change remains within the intent of the service and does not materially change the contract scope, fleet requirements, or pricing. Changes that materially modify the scope, service area, service level, or contractual deliverables may require a contract amendment/change order in accordance with the Solicitation and resulting agreement.
Q11: Are all stations ADA compliant? If not, who is responsible for assuring compliance?
A11: ADA requirements and any associated station/stop responsibilities will be maintained by the City. The vendor is responsible for relaying ADA concerns or issues along the route and/or stops with the City.
Q12: Is the City responsible for all route signage?
A12: The City is responsible for all route signage.
Q13: Is the proposer financially responsible for capital and recurring costs of upgraded or new installation for storage and charging infrastructure?
A13: All bidders must identify all infrastructure needed to support operations (including charging and storage needs) and include those assumptions and responsibilities clearly in their proposal. Allocation of responsibilities will be governed by the contract and the Scope of Services. If specific cost responsibility is not explicitly stated in the scope, bidders should clearly state assumptions in their pricing and approach.
Q14: Will the City accept a two-week deadline extension request?
A14: The City will accept a one-week deadline extension.