This Request for Proposal (RFP) is issued by the Michigan Department of Transportation (MDOT) for preventative maintenance work on M-57 (Cleveland Road) in Washington Township, Gratiot County. The project consists of a 1.5-inch uniform cold mill and single-course hot mix asphalt (HMA) overlay for the entire pavement width, with pavement markings placed to match the current lane configuration. The scope includes 14,000 square yards of cold milling, 1,155 tons of HMA 5EML High Stress asphalt, and various pavement marking items including reflective polyurea striping and channelizing devices. The RFP was issued on March 11, 2025, with a bidder question deadline of March 14, 2025, and a proposal submission deadline of March 21, 2025, at 3:00 p.m. Eastern Time. The anticipated contract start date is May 12, 2025, with work completion required by August 8, 2025. Work must be completed within four consecutive workdays, weather dependent, excluding weekends. The contract will be awarded to the responsive and responsible bidder with the lowest price who meets all mandatory requirements, which include current MDOT prequalification in Hot Mix Asphalt/Bituminous Patching and Pavement Marking categories.
Pricing must be submitted on Schedule B with a lump sum mobilization fee and unit-based pricing for milling, HMA, pavement markings, traffic control devices, and witness logs. Bidders must maintain performance and lien bonds each equal to 100 percent of the total contract price and comply with prevailing wage requirements as specified in attachments. The contractor must maintain a minimum of one lane of traffic in each direction at all times and may be assessed liquidated damages of $500 to $4,000 per day based on contract amount if work is not completed by the deadline. Required insurance includes $1,000,000 commercial general liability per occurrence, $5,000,000 umbrella coverage, and $1,000,000 automobile liability. The contractor must comply with all federal, state, and local laws, maintain prevailing wage standards, and provide comprehensive project management including a program manager, emergency contacts, and preconstruction meetings. All proposals become public record upon receipt, and the State reserves the right to conduct site visits, interviews, reference checks, and request additional price concessions during evaluation. Qualified disabled veteran-owned businesses are eligible for consideration under MCL 18.1261(8).
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 4 - ORS-002120_MDOT_M57_Issued.03.11.25.pdf | ||
| Addenda 1 - Bidder Q&A M-57 Mill_Fill.pdf | ||
| Attachment 2 - WHD-9917 FEB 9 2024.pdf | ||
| Attachment 1 - M-57 Proposal.pdf | ||
| Attachment 3 - WHD-9918 FEB 9 2024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement proposal instructions Department of Transportation
HMA COLD MILL AND OVERLAY M-57 (CLEVELAND ROAD)
WASHINGTON TOWNSHIP, GRATIOT COUNTY
Request for Proposal No. 250000001767 Solicitation Manager Name: Anna Swanson Direct Phone: 517-230-2063 Email: swansona1@michigan.gov
This is a Request for Proposal (RFP) for:
The work shall consist of a 1.5’’ uniform cold mill and single course HMA overlay for the entire width of the pavement from the POB to POE. At crossroads and intersections, the milling and resurfacing limits shall be defined as a straight line along curb face to curb face or along existing pavement joint where mainline meets the approach. Once the paving operation is completed, the proposed pavement markings will be placed to match the current lane configuration.
RFP Timeline
| Event |
| Time |
| Date |
| RFP issue date |
| N/A |
| Tuesday, March 11, 2025 |
| Deadline for bidders to submit questions about this RFP |
| 3:00 p.m. Eastern |
| Friday, March 14, 2025 |
| Anticipated date the State will post answers to bidder questions on www.michigan.gov/SIGMAVSS |
| 3:00 p.m. Eastern |
| Tuesday, March 18, 2025 |
| Proposal deadline* |
| 3:00 p.m. Eastern |
| Friday, March 21, 2025 |
| Anticipated contract begin date |
| N/A |
| Monday, May 12, 2025 |
*A bidder’s proposal received at 3:00:01 p.m. Eastern is late and subject to disqualification.
This RFP is subject to change. Check www.michigan.gov/SIGMAVSS for current information.
1. PROPOSAL PREPARATION. The State recommends reading all RFP materials prior to preparing a proposal, particularly these Proposal Instructions and the Vendor Questions Worksheet. Bidders must follow these Proposal Instructions and provide a complete response to the items indicated in the table below. References and links to websites or external sources may not be used in lieu of providing the information requested in the RFP within the proposal. Include the bidder’s company name in the header of all documents submitted with your proposal. Note that all documents and information submitted as part of a proposal will become public record immediately upon receipt by the State. Proposals received by the State may be posted on the State’s publicly available website after bidders are notified of the award recommendation.
RFP Structure and Documentation
| Document |
| Description |
| Bidder Response Instructions |
| Cover Page |
| Provides RFP title and number, important dates, and contact information for Solicitation Manager |
| Informational |
| Proposal Instructions |
| Provides RFP instructions to bidders |
| Informational |
| Vendor Questions Worksheet |
| Questions to bidders on background and experience |
| Bidder to complete and submit by proposal deadline |
| Schedule A – Statement of Work |
| Statement of work |
| Bidder to complete and submit by proposal deadline |
| Schedule B – Pricing |
| Pricing for goods and services sought by the State through this RFP |
| Bidder to complete and submit by proposal deadline |
| Attachment 1 – M-57 Proposal |
| Project Package |
| Informational |
| Attachment 2 - WHD-9917 FEB 9 2024 |
| Current prevailing wages |
| Informational |
| Attachment 3 - WHD-9918 FEB 9 2024 |
| Current prevailing wages |
| Informational |
| Attachment 4 - ORS-002120_MDOT_M57_Issued.03.11.25 |
| Current prevailing wages |
| Informational |
| Contract Terms |
| Provides legal terms for a contract awarded through this RFP |
| Deemed accepted by bidder unless information required in the Evaluation Process section of this document is submitted by proposal deadline |
2. CONTACT INFORMATION FOR THE STATE. The sole point of contact for the State concerning this RFP is listed on the Cover Page. Contacting any other State personnel, agent, consultant, or representative about this RFP may result in bidder disqualification.
3. MODIFICATIONS. The State may modify this RFP at any time. Modifications will be posted on www.michigan.gov/SIGMAVSS. This is the only method by which the RFP may be modified.
4. QUESTIONS. Bidder questions about this RFP must be emailed to the Solicitation Manager Anna Swanson at swansona1@michigan.gov no later than the time and date specified on the Cover Page. In the interest of transparency, only written questions are accepted. Answers to questions will be posted on www.michigan.gov/SIGMAVSS. Submit questions using the format below; a Microsoft Excel format or similar is suggested.
| Q # |
| Document and Section |
| Page # |
| Bidder Question |
5. DELIVERY OF PROPOSAL.
Electronic – The bidder must submit its proposal, all attachments, and any modifications or withdrawals electronically through www.michigan.gov/SIGMAVSS. The price proposal should be saved separately from all other proposal documents. The bidder should submit all documents in a modifiable (native) format (examples include but are not limited to Microsoft Word or Excel and Google Docs or Sheets). In addition to submitting documents in a modifiable format, the bidder may also submit copies of documents in PDF. Attachment file size is limited to 6 MB per document. Bidder’s failure to submit a proposal as required may result in disqualification. The proposal and attachments must be fully uploaded and submitted prior to the proposal deadline. Do not wait until the last minute to submit a proposal, as the SIGMA VSS system requires the creation of an account and entry of certain information, in addition to uploading and submitting the materials. The SIGMA VSS system will not allow a proposal to be submitted after the proposal deadline identified in the solicitation Closing On/Closing Date fields (Summary view/Detail view), even if a portion of the proposal has been uploaded.
Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 284-0540 or (888) 734-9749. The Solicitation Manager will not provide assistance related to the submittal of the proposal and all attachments on the day of the proposal deadline. Responsibility for a complete submission lies with the bidder. Note that all documents and information submitted in any manner as part of a proposal will become public record immediately upon receipt by the State. Proposals received may be posted by the State on the State’s publicly available website after bidders are notified of the award recommendation.
6. MANDATORY MINIMUM REQUIREMENTS. To avoid disqualification, the bidder must be currently listed as a MDOT Prequalified Contractor in the following category(s):
Cb Hot Mix Asphalt/Bituminous Patching N3 Pavement Marking The list of Prequalified Contractors may be found at https://mdotjboss.state.mi.us/PSVR/PrequalifiedContractors.htm.
Only proposals meeting the mandatory minimum requirements will be considered for evaluation.
7. EVALUATION PROCESS The State will evaluate each proposal on a PASS/FAIL basis based on the following criteria:
| Criteria |
| Pass/Fail |
| 1. |
| Responses to Vendor Questions are complete and acceptable |
| 2. |
| Responses on Schedule A are complete and acceptable |
| 3. |
| Schedule B is complete |
The State may utilize all bidder information to determine fair market value for goods or services sought. If applicable, the State’s evaluation will include consideration of a bidder’s qualified disabled veterans/service-disabled veteran owned business(QDV/SDVOB) status under MCL 18.1261(8). Additional information on the SDVOB preference is available at: Michigan.gov/SDVOB.
The State may but is not required to conduct an on-site visit to tour and inspect the bidder’s facilities; require an oral presentation of the bidder's proposal; conduct interviews, research, reference checks, and background checks; and request additional price concessions at any point during the evaluation process.
8. NOTICE OF DEFICIENCY. The State reserves the right to issue a Notice of Deficiency to bidders if the State determines after the proposal deadline that a portion of the RFP was deficient, unclear, or ambiguous. Failure to respond to a Notice of Deficiency timely may be cause for disqualification.
9. CLARIFICATION REQUEST. The State reserves the right to issue a Clarification Request to a bidder to clarify its proposal if the State determines the proposal is not clear. Failure to respond to a Clarification Request timely may be cause for disqualification.
10. RESERVATIONS. The State reserves the right to:
a. Disqualify a bidder for failure to follow these instructions.
b. Discontinue the RFP process at any time for any or no reason. The issuance of an RFP, your preparation and submission of a proposal, and the State’s subsequent receipt and evaluation of your proposal does not commit the State to award a contract to you or anyone, even if all the requirements in the RFP are met.
c. Consider late proposals if: (i) no other proposals are received; (ii) no complete proposals are received; (iii) the State received complete proposals, but the proposals did not meet mandatory minimum requirements or technical criteria; or (iv) the award process fails to result in an award.
d. Consider an otherwise disqualified proposal if no other proposals are received.
e. Disqualify a proposal based on: (i) information provided by the bidder in response to this RFP; (2) the bidder’s failure to complete registration on www.michigan.gov/SIGMAVSS ; or (3) if it is determined that a bidder purposely or willfully submitted false or misleading information in response to the RFP.
f. Consider prior performance with the State in making its award decision.
g. Consider overall economic impact to the State when evaluating proposal pricing and in the final award recommendation. This includes but is not limited to: considering principal place of performance, number of Michigan citizens employed or potentially employed, dollars paid to Michigan residents, Michigan capital investments, job creation, tax revenue implications, and economically disadvantaged businesses.
h. Consider total-cost-of-ownership factors (e.g., transition and training costs) when evaluating proposal pricing and in the final award recommendation.
i. Refuse to award a contract to any bidder that has failed to pay State taxes or has outstanding debt with the State.
j. Enter into negotiations with one or more bidders on price, terms, technical requirements, or other deliverables.
k. Award multiple, optional-use contracts, or award by Contract Activity.
l. Evaluate the proposal outside the scope identified in the Evaluation Process section of this document if the State receives only one proposal.
11. AWARD RECOMMENDATION. The contract will be awarded to the responsive and responsible bidder who receives a PASS for each criterion and has the lowest price.
The State will publish an Award Recommendation and Evaluation Synopsis, by posting a Notice of Intent to Award (NIA1) on www.michigan.gov/SIGMAVSS
12. DEBRIEF MEETING AND BID PROTEST. The State will post an Award Recommendation and Evaluation Synopsis which will provide instructions on how to request a debrief meeting.
If you wish to initiate a protest of the award, you must submit your written protest to Michael Meddaugh at meddaughm@michigan.gov no later than 3:00 p.m., three (3) business days after posting the Award Recommendation and Evaluation Synopsis on SIGMA VSS. The State reserves the right to adjust this timing and will publish any change.
Additional information about the protest process is available at DTMB - Programs and Policies (michigan.gov) under the “Bidder Protests” link.
13. STATE ADMINISTRATIVE BOARD. Contracts equal to $500,000 or greater than require approval by the State Administrative Board. The State Administrative Board’s decision is final; however, its approval does not constitute a contract. The award process is not complete until the awarded contractor receives a contract fully executed by all parties.
14. GENERAL CONDITIONS. The State will not be liable for any costs, expenses, or damages incurred by a bidder participating in this solicitation. The bidder agrees that its proposal will be considered an offer to do business with the State in accordance with its proposal, including the Contract Terms, and that its proposal will be irrevocable and binding for a period of 180 calendar days from date of submission. If a contract is awarded to the bidder, the State may, at its option, incorporate any part of the bidder’s proposal into a contract. This RFP is not an offer to enter into a contract. This RFP may not provide a complete statement of the State’s environment or contain all matters upon which agreement must be reached. The bidder understands that their proposal will become public record immediately upon receipt by the State. Other than verified trade secrets, proposals submitted via www.michigan.gov/SIGMAVSS are the State’s property.
15. THE FREEDOM OF INFORMATION ACT. As a public record, all portions of the bidder’s proposal and resulting contract are subject to disclosure as required under Michigan’s Freedom of Information Act (FOIA), MCL 15.231, et seq.
a. NO ADVICE. The State will not advise a bidder as to the nature or content of documents entitled to protection from disclosure under FOIA or other laws, as to the interpretation of such laws, or as to the definition of trade secret or financial or proprietary information. Nothing contained in this provision will modify or amend requirements and obligations imposed on the State by FOIA or other applicable law.
b. The State has the final authority to determine whether the materials are exempt from disclosure under FOIA. Bidder forever releases the State, its departments, subdivisions, officers, and employees from all claims, rights, actions, demands, damages, liabilities, expenses and fees, which arise out of or relate to the disclosure of all or a portion of bidder’s proposal submitted under this RFP. Bidder must defend, indemnify and hold the State, its departments, subdivisions, officers, and employees harmless, without limitation, from and against all actions, claims, losses, liabilities, damages, costs, attorney fees, and expenses (including those required to establish the right to indemnification), arising out of or relating to any FOIA request, including potential litigation and appeals, related to the portion of bidder’s proposal submitted under this RFP that bidder has identified as a trade secret, or financial or proprietary information. The State will notify bidder in writing if indemnification is sought. The State is entitled to: (i) regular updates on proceeding status; (ii) participate in the defense of the proceeding; (iii) employ its own counsel; and to (iv) retain control of the defense, or any portion thereof, if the State deems necessary. Bidder will not, without the State’s written consent (not to be unreasonably withheld), settle, compromise, or consent to the entry of any judgment in or otherwise seek to terminate any claim, action, or proceeding. If a State employee, official, or law is involved or challenged, the State may control the defense of that portion of the claim. Any litigation activity on behalf of the State, or any of its subdivisions under this Section, must be coordinated with the Department of Attorney General. An attorney designated to represent the State may not do so until approved by the Michigan Attorney General and appointed as a Special Assistant Attorney General.
vendor questions worksheet Provide a detailed response to each question. “You” and “company” refers to the bidder.
| Information Sought |
| Bidder Response |
1. Contact Information
Bidder’s sole contact person during the RFP process. Include name, title, address, email, and phone number.
Person authorized to receive and sign a resulting contract. Include name, title, address, email, phone number and vendor customer code in SIGMA VSS.
2. Company Background Information
Legal business name and address. Include business entity designation, e.g., sole proprietor, Inc., LLC, or LLP.
What state was the company formed in?
Phone number.
Website address.
Number of years in business.
Number of employees.
Legal business name and address of parent company, if any.
Has there been a recent change in organizational structure (e.g., management team) or control (e.g., merger or acquisition) of your company? If the answer is yes: (a) explain why the change occurred and (b) how this change has affected your company.
| Discuss your company’s history. Has growth been organic, through mergers and acquisitions, or both? |
| DO NOT COMPLETE THIS SECTION |
Has bidder ever been debarred, suspended, or disqualified from bidding or contracting with any entity, including the State of Michigan? If yes, provide the date, the entity, and details about the situation.
Has your company been a party to litigation against the State of Michigan? If the answer is yes, then state the date of initial filing, case name and court number, and jurisdiction.
Within the last 5 years, has your company or any of its related business entities defaulted on a contract or had a contract terminated for cause? If yes, provide the date, contracting entity, type of contract, and details about the termination or default.
State your gross annual sales for each of the last 5 years.
If receiving a contract under this RFP will increase your gross revenue by more than 25% from last year’s sales, explain how the company will scale-up to manage this increase.
Describe partnerships and strategic relationships you think will bring significant value to the State.
State the physical address of the place of business that would have primary responsibility for this account if bidder is awarded a contract under this RFP.
| Bidder affirms that any business types identified on its SIGMA VSS profile, including those eligible for Geographically Disadvantaged Business Enterprise (GDBE) and Michigan Supplier Community Program (MiSC), are valid. |
| Choose an item. |
| 3. Qualified Disabled Veteran/Service-Disabled Veteran-Owned Business Program |
| Under MCL 18.1261, a “qualified disabled veteran” means a business entity that is 51% or more owned by 1 or more veterans with a service-connected disability. A “service-connected disability” means a disability incurred or aggravated in the line of duty in the active military, naval, or air service as described in 38 USC 101(16). Are you a qualified disabled veteran? |
| Choose an item. |
| To demonstrate qualification as a qualified disabled veteran, you must provide: |
(a) Proof of service and conditions of discharge (DD214 or equivalent);
(b) Proof of service-connected disability (DD214 if the disability was documented at discharge or Veterans Administration Rating Decision Letter or equivalent if the disability was documented after discharge); and
(c) Legal documents setting forth the ownership of the business entity.
In lieu of the documentation identified above, you may provide proof of certification by the National Veterans Business Development Council.
Enter the names of documents submitted with your proposal to demonstrate status as a qualified disabled veteran.
4. Participation in RFP Development or Evaluation
| Did your company, an employee, agent, or representative of your company, or any affiliated entity participate in developing any component of this solicitation? For purposes of this question, business concerns, organizations, or individuals are affiliates of each other if, directly or indirectly: (1) either one controls or has power to control the other or (2) a third-party controls or has the power to control both. Indicia of control include, but are not limited to, interlocking management or ownership, identity of interests among family members, shared facilities or equipment, and common use of employees. |
| Choose an item. |
If you enter “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
| If you are awarded a contract under this solicitation, in order to provide the goods or services required under a resulting contract, do you intend to partner or subcontract with a person or entity that assisted in the development of this solicitation? |
| Choose an item. |
If you enter “YES,” you are not eligible for contract award. An awarded vendor may not partner or subcontract with anyone to provide goods and services required under a resulting contract if that subcontractor or partner assisted in the development of this solicitation.
| Will your company, or an employee, agent, or representative of your company, participate in the evaluation of the proposals received in response to this RFP? |
| Choose an item. |
If you enter “YES”, you are not eligible for contract award or to work as a subcontractor for the awarded vendor.
| 5. State of Michigan Experience and Prior Experience |
| DO NOT COMPLETE THIS SECTION |
Does your company have experience working with the State of Michigan? If so, please provide a list (including the contract number) of the contracts you hold or have held with the State for the last 10 years.
Describe at least 3 relevant experiences from the last 5 years supporting your ability to successfully manage a contract of similar size and scope for the work described in this RFP.
Experience 1
Company name.
Contact name.
Contact role at time of project.
Contact phone.
Contact email.
City.
State.
Zip.
1. Project name and description of the scope of the project.
2. What role did your company play?
3. How is this project experience relevant to the subject of this RFP?
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
Experience 2
Company name.
Contact role at time of project.
City.
1. Project name and description of the scope of the project.
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
Experience 3
Company name.
Contact role at time of project.
City.
1. Project name and description of the scope of the project.
Dollar value.
Start and end date (mm/yy – mm/yy)
Status (completed, live, other – specify phase)
Results obtained.
6. Standard Contract Terms
| Bidder must affirm agreement with the attached Contract Terms. If not in agreement, written exceptions in accordance with the Evaluation Process section of the Proposal Instructions must be provided with Bidder’s proposal. |
| ☐ Agree to Contract Terms |
☐ Do Not Agree with Contract Terms (attach written exceptions)
| 7. Michigan Economic Impact |
| DO NOT COMPLETE THIS SECTION |
Number of employees currently employed at locations within the State of Michigan.
Number of additional employees to be employed at locations within the State of Michigan if awarded this Contract (if any)
Minimum wage paid to employees employed at locations within the State of Michigan.
Average wage paid to employees employed at locations within the State of Michigan.
Percentage of employees employed at locations within the State of Michigan that are covered by employer-provided health insurance.
8. Labor, Antidiscrimination and Environmental Laws Compliance
Bidder must disclose any violations of state or federal labor, antidiscrimination and employment laws and regulations received within the past five years.
Bidder must disclose any violations of state or federal environmental laws and regulations received within the past five years.
9. Other
| Classification of Employees. I certify that the company has properly classified its employees in accordance with federal/state labor and employment laws. |
| Choose an item. |
| Abusive Labor Practices. The Contractor certifies that it will not furnish any Deliverable that was produced fully or partially by forced labor, forced or indentured child labor, or indentured servitude. |
| Choose an item. |
| Certification of Michigan Business- Public Act 431 of 1984, Sec. 268. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Business Tax Corporate Income Tax Return. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, filed a Michigan Income Tax return showing income generated in, or attributed to the State of Michigan. I certify that the company has, pursuant to the provisions of Sec 268 of Public Act 431 of 1984, withheld Michigan Income Tax from compensation paid to the company’s owners and remitted the tax to the Michigan Department of Treasury. |
| Choose an item. |
| Iran Linked Business- Public Act 517 of 2012. I certify that the Company is not an Iran-Linked business as defined by Public Act 517 of 2012. |
| Choose an item. |
| Clean Corporate Citizen. I certify that the Company is a Clean Corporate Citizen as defined by the Environmental Protection Act, 1994 PA 451. |
| Choose an item. |
| Convict Labor. The Contractor certifies that if using convict labor, it is complying with all applicable state and federal laws and policies. |
| Choose an item. |
| SOM Debt/Tax Payment. All SOM tax/debts. I certify that all applicable State of Michigan taxes are paid, and that no outstanding debt is owed to the State of Michigan. |
| Choose an item. |
| Authorization to Verify Information Provided by Vendor. I authorize the State to verify that all information provided in this registration, in bidding and contracting documents, and any attachments or supplement documents and processes are accurate. |
| Choose an item. |
| 10. Response to State Requests |
| Bidder agrees to respond, by established deadlines, to all requests from the State including but not limited to, clarification requests, notices of deficiency, and proposed changes to Contract Terms. |
| Choose an item. |
Contractor must enter company name here.
Schedule A – statement of work contract activities Request for Proposal (RFP) No. 250000001767
M-57 (CLEVELAND ROAD) HMA COLD MILL AND OVERLAY
WASHINGTON TOWNSHIP, GRATIOT COUNTY
This schedule identifies the anticipated requirements of any Contract resulting from this RFP. The term “Contractor” in this document refers to a bidder responding to this RFP, as well as the Contractor who is awarded the contract. The term “bidder” is used to identify where specific responses to the RFP are required.
The Contractor must respond to each requirement or question and explain how it will fulfill each requirement. Attach any supplemental information and appropriately reference within your response.
IMPORTANT NOTE TO CONTRACTORS/BIDDERS: There are specific requirements for which acceptance must be simply acknowledged through a checkbox(es), and others that require further explanation. Click one checkbox and complete the entries as identified.
SCOPE
The preventative maintenance work shall consist of 1.5” cold milling with a 1.5” HMA overlay from the Point of Beginning (POB) to the Point of End (POE). Once the paving operation is completed, the proposed pavement markings will be marked to match the current lane configuration.
1. Requirements
1.1. General Requirements
The Contractor must provide the following services: All work must be conducted in accordance with the Michigan Department of Transportation 2020 Standard Specifications for Construction.
MDOT 2020 Standard Specifications for Construction [WEB]-linked (michigan.gov)
1.2. Specific Requirements
See all attachments and referenced documents for specific requirements for the project.
1.3. Maintenance of Traffic Requirements
The Contractor shall maintain a minimum of one lane of traffic in each direction at all times on M-57 (and all intersecting roads and ramps). Additional traffic regulators shall be used at unsignalized intersections and driveways, as directed by the Engineer. Payment for these items shall be included in the lump sum price for the project.
There is to be no more than one (1) closure allowed at any one time.
| ☐ |
| I have reviewed the above Section 1 requirements and agree with no exception. |
| ☐ |
| I have reviewed the above Section 1requirements and have noted all exception(s) below. |
List all exception(s):
2. Service Requirements
2.1. Timeframes
Work may begin immediately after receiving approval from MDOT. Work must begin no earlier than May 12th, 2025, and be completed by August 8th, 2025. Work must be completed within four (4) consecutive workdays, weather dependent, except for the placement of the permanent pavement markings. The workdays do not include Saturday and Sunday. Notice must be provided to Jason Potts at 989-737-0211 seven (7) calendar days prior to the beginning of any work.
2.2. Work Hours
The Contractor must provide Contract Activities during the State’s normal working hours Monday – Friday 6:00 a.m. to 6:00 p.m. Eastern Time and possible night and weekend hours depending on the requirements of the project. Additional traffic restrictions are provided in the Log of Project section of Attachment 1 – M-57 Proposal.
2.3. Project Prevailing Wage Requirements
The Contractor (and its Subcontractors) must pay all mechanics and laborers employed directly on the site of the work, unconditionally and at least once a week, and without subsequent deduction or rebate on any account, the full amounts accrued at time of payment, computed at wage rates not less than those stated in the advertised specifications as prevailing wages based on locality, regardless of any contractual relationship which may be alleged to exist between the Contractor or subcontractor and the laborers and mechanics.
Contractor must post the scale of wages to be paid in a prominent and easily accessible place at the site of the work.
| ☐ |
| I have reviewed the above Section 2 requirements and agree with no exception. |
| ☐ |
| I have reviewed the above Section 2 requirements and have noted all exception(s) below. |
List all exception(s):
3. Acceptance
3.1. Acceptance, Inspection, and Testing
The MDOT Program Manager or designee will determine final acceptance of the work performed and ensure conformance to the MDOT 2020 Standard Specifications for Construction.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
4. Staffing
4.1. Contractor Program Manager
The Contractor’s Program Manager will be the primary contact specifically assigned to the Contract and will respond to State inquiries regarding the Contract Activates.
The Contractor must notify the Contract Administrator at least 14 calendar days before removing or assigning a new Contractor Program Manager.
Superintendent Contact Information:
Name
Title
Office Phone
Mobile Phone
Email Address
4.2. Emergency Contact and 24/7 Telephone Number
The Contractor must specify two emergency contacts who must be available 24 hours a day 7 days a week to receive emergency work orders or if the Project Manager cannot be reached.
Primary Emergency Contact Information:
Name
Title
24/7 Phone Number
Secondary Emergency Contact Information:
Name
Title
24/7 Phone Number
4.3. Disclosure of Subcontractors
If the Contractor intends to utilize subcontractors, the Contractor must disclose the following:
· The legal business name; address; telephone number; a description of subcontractor’s organization and the services it will provide; and information concerning subcontractor’s ability to provide the Contract Activities.
· The relationship of the subcontractor to the Contractor.
· Whether the Contractor has a previous working experience with the subcontractor. If yes, provide the details of that previous relationship.
· A complete description of the Contract Activities that will be performed or provided by the subcontractor.
Bidder must provide detailed information as requested in the above requirement(s).
The legal business name, address, telephone number of the subcontractor(s).
A description of subcontractor’s organization and the services it will provide and information concerning subcontractor’s ability to provide the Contract Activities.
The relationship of the subcontractor to the Bidder.
Whether the Bidder has a previous working experience with the subcontractor.
If yes, provide the details of that previous relationship.
A complete description of the Contract Activities that will be performed or provided by the subcontractor.
Of the total bid, the price of the subcontractor’s work.
Bidder must provide information based on the work performed by all subcontractors
Total percentage of work that will be performed by subcontractors:
| ☐ |
| I have reviewed the above Section 4 requirements and agree with no exception. |
| ☐ |
| I have reviewed the above Section 4 requirements and have noted all exception(s) below. |
List all exception(s):
5. Project Management
5.1. Project Control
The Contractor will carry out this project under the direction and control of the MDOT Program Manager. The MDOT Program Manager for this project is Name and Title: Brian Atkinson, Operations Engineer Business Address: 1212 Corporate Dr, Mt Pleasant, MI 48858 Email Address: atkinsonb@michigan.gov Telephone Number: 989-621-0192
5.2. Project Plan
Within 10 days of Contract execution, the Contractor must submit a project plan to the Program Manager for final approval. The plan must include: (a) the Contractor's organizational chart with names and title of personnel assigned to the project; and (b) the project schedule showing sub-projects, tasks, and resources required.
5.3. Reporting
The Contractor must submit, to Brian Atkinson, the following written reports: Progress Schedule.
5.4. Meetings
The Contractor must attend a preconstruction meeting with the Program Manager. The Program Manager will determine the time, and place for the preconstruction meeting. The meeting will be conducted after project award and may be rescheduled if there are delays in the award of the project.
The State may request other meetings as it deems appropriate.
| ☐ |
| I have reviewed the above Section 5 requirements and agree with no exception. |
| ☐ |
| I have reviewed the above Section 5 requirements and have noted all exception(s) below. |
List all exception(s):
6. Pricing Pricing is firm for the entire length of the Contract.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
7. Ordering
7.1. Authorizing Document
The appropriate authorizing document for the Contract will be a State issued Purchase Order Contract.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
8. Invoice and Payment
8.1. Invoice Requirements
All invoices submitted to the State must indicate: (a) date of service; (b) vendor-generated invoice number; (c) purchase order/contract number; (d) quantity; (e) description of the Contract Activities (pay item); (f) unit price; and (g) total price.
Overtime, holiday pay, and travel expenses will not be paid.
8.2. Payment Methods
As required by MCL 18.1283, the State will only disburse payments under this Contract through Electronic Funds Transfer (EFT).
The Contractor is responsible for ensuring current banking information is entered in the State vendor website: AdvantageVSS - SIGMA VSS.
8.3. Procedure
All invoices must be submitted within 30 days of final work acceptance at the specific location. All invoices must be submitted via e-mail to the MDOT Program Manager, Brian Atkinson at atkinsonb@michigan.gov.
| ☐ |
| I have reviewed the above Section 8 requirements and agree with no exception. |
| ☐ |
| I have reviewed the above Section 8 requirements and have noted all exception(s) below. |
List all exception(s):
9. Liquidated Damages Late or improper completion of the Contract Activities will cause loss and damage to the State and it would be impracticable and extremely difficult to fix the actual damage sustained by the State. Therefore, if Contract Activities are not completed by the date identified in the Statement of Work, the State is entitled to collect liquidated damages in accordance with the Table 108-1 of the 2020 Standard Specifications for Construction for each day Contractor fails to remedy the late or improper completion of the Work.
Table 108-1: Schedule of Liquidated Damages For Department Oversight
| Original Contract Amount |
| Amount per |
Calendar Day
| From More Than |
| To and Including |
| $0 |
| $100,000 |
| $500 |
| $100,000 |
| $500,000 |
| $800 |
| $500,000 |
| $1,000,000 |
| $1,000 |
| $1,000,000 |
| $5,000,000 |
| $1,500 |
| $5,000,000 |
| $15,000,000 |
| $2,000 |
| Over $15,000,000 |
| $4,000 |
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
10. Bonds The Contractor must furnish performance and lien bonds each for not less than 100% of the total contract price. The bonds must be on forms provided by MDOT. The bonds must meet the requirements of Michigan law and MDOT and include other items such as the Powers of Attorney and Endorsement as specified by MDOT. The same surety responsible for writing the performance bond must write the lien bond. It is the Contractor’s responsibility to ensure that the lien bond conforms with the terms of MCL 570.101 et seq.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Enter company name here Schedule B - Pricing
Request For Proposal No. 250000001767
M-57 (CLEVELAND ROAD) HMA COLD MILL AND OVERLAY
WASHINGTON TOWNSHIP, GRATIOT COUNTY
The Contractor must provide a pricing schedule for the proposed Contract Activities using the format listed below.The pricing schedule should be submitted in a modifiable format (e.g., Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
1. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
2. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.
Quick payment terms: % discount off invoice if paid within days after receipt of invoice.
3. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| M-57 Pay Item |
| Unit of Measure |
| Quantity |
| Unit Cost |
| Total |
| Mobilization, Max |
| LSUM |
| 1 |
| $ |
| $ |
| Cold Milling HMA Surface |
| Syd |
| 14,000 |
| $ |
| $ |
| HMA, 5EML, High Stress |
| Ton |
| 1,155 |
| $ |
| $ |
| Total Milling and HMA |
| $ |
| Pavt Mrkg, Ovly Cold Plastic, Rt Turn Arrow Sym |
| Ea |
| 4 |
| $ |
| $ |
| Pavt Mrkg, Ovly Cold Plastic, Lt Turn Arrow Sym |
| Ea |
| 4 |
| $ |
| $ |
| Pavt Mrkg, Wet Reflective Polyurea, 6 inch, Yellow |
| Ft |
| 5,950 |
| $ |
| $ |
| Pavt Mrkg, Wet Reflective Polyurea, 6 inch, White |
| Ft |
| 4,660 |
| $ |
| $ |
| Witness Log, $1,250.00 |
| Dlr |
| 1,250 |
| $ 1.00 |
| $ 1,250.00 |
| Recessing Pavt Mrkg, Longit |
| Ft |
| 10,610 |
| $ |
| $ |
Total Pavement Marking
| Channelizing Device, 42 inch, Fluorescent, Furn |
| Ea |
| 80 |
| $ |
| $ |
| Channelizing Device, 42 inch, Fluorescent, Oper |
| Ea |
| 80 |
| $ |
| $ |
| Lighted Arrow, Type C, Furn |
| Ea |
| 2 |
| $ |
| $ |
| Lighted Arrow, Type C,Oper |
| Ea |
| 2 |
| $ |
| $ |
| Minor Traf Devices |
| LSUM |
| 1 |
| $ |
| $ |
| Sign Cover |
| Ea |
| 10 |
| $ |
| $ |
| Sign, Type B, Temp, Prismatic, Furn |
| Sft |
| 425 |
| $ |
| $ |
| Sign, Type B, Temp, Prismatic, Oper |
| Sft |
| 425 |
| $ |
| $ |
| Traf Regulator Control |
| LSUM |
| 1 |
| $ |
| $ |
| Pavt Mrkg, Wet Reflective, Type R, Tape, 6 inch, Yellow, Temp |
| Ft |
| 720 |
| $ |
| $ |
| Pavt Mrkg, Wet Reflective, Type R, Tape, 6 inch, White, Temp |
| Ft |
| 396 |
| $ |
| $ |
Total Traffic Control Devices
| GRAND TOTAL |
| $ |
Listed quantities are estimates only from prior usage. Exact quantities are unknown. The State is not obligated to purchase in these listed quantities.
Standard Contract terms This STANDARD CONTRACT (“Contract”) is agreed to between the State of Michigan (the “State”) and [Insert Company Name] (“Contractor”), a [Insert State & Entity Status, e.g., a Michigan corporation or a Texas limited liability company]. This Contract is effective on May 12, 2025 (“Effective Date”), and unless terminated, will expire on August 8, 2025 (the “Term”).
The parties agree as follows:
1. Duties of Contractor. Contractor must perform the services and provide the deliverables (the “Contract Activities”) described in a Statement of Work, the initial Statement of Work is attached as Schedule A – Statement of Work .An obligation to provide delivery of any commodity is considered a service and is a Contract Activity.
Contractor must furnish all labor, equipment, materials, and supplies necessary for the performance of the Contract Activities unless otherwise specified in a Statement of Work.
Contractor must: (a) perform the Contract Activities in accordance with this Contract, including the Statement of Work contained in Schedule A and the 2020 Standard Specifications for Construction; however, in the case of a conflict, Schedule A will control; (b) meet or exceed the performance and operational standards, and specifications of the Contract; (c) provide all Contract Activities in good quality, with no material defects; (d) not interfere with the State’s operations; (e) obtain and maintain all necessary licenses, permits or other authorizations necessary for the performance of the Contract; (f) cooperate with the State, including the State’s quality assurance personnel, and any third party to achieve the objectives of the Contract; (g) return to the State any State-furnished equipment or other resources in the same condition as when provided when no longer required for the Contract; (h) assign to the State any claims resulting from state or federal antitrust violations to the extent that those violations concern materials or services supplied by third parties toward fulfillment of the Contract; (i) comply with all State physical and IT security policies and standards which will be made available upon request; and (j) provide the State priority in performance of the Contract except as mandated by federal disaster response requirements. Any breach under this paragraph is considered a material breach.
Contractor must also be clearly identifiable while on State property by wearing identification issued by the State, and clearly identify themselves whenever making contact with the State.
2. Notices. All notices and other communications required or permitted under this Contract must be in writing and will be considered given and received: (a) when verified by written receipt if sent by courier; (b) when actually received if sent by mail without verification of receipt; or (c) when verified by automated receipt or electronic logs if sent by facsimile or email.
| If to State: |
| If to Contractor: |
Anna Swanson MDOT-Contract Services Division 425 West Ottawa Street Lansing, MI 48933 Swansona1@michigan.gov 517-230-2063 [Name] [Street Address] [City, State, Zip] [Email] [Phone]
3. Contract Administrator. The Contract Administrator, or the individual duly authorized for each party, is the only person authorized to modify any terms of this Contract, and approve and execute any change under this Contract (each a “Contract Administrator”):
| State: |
| Contractor: |
Anna Swanson MDOT-Contract Services Division 425 West Ottawa Street Lansing, MI 48933 Swansona1@michigan.gov 517-230-2063 [Name] [Street Address] [City, State, Zip]
4. Program Manager. The Program Manager for each party will monitor and coordinate the day-to-day activities of the Contract (each a “Program Manager”):
| State: |
| Contractor: |
Brian Atkinson 1212 Corporate Drive Mt. Pleasant, MI 48858 atkinsonb@michigan.gov
(989) 621-0192 [Name] [Street Address] [City, State, Zip]
5. Performance Guarantee. Contractor must at all times have financial resources sufficient, in the opinion of the State, to ensure performance of the Contract and must provide proof upon request. The State may require a performance bond (as specified in a Statement of Work) if, in the opinion of the State, it will ensure performance of the Contract.
6. Insurance Requirements.
Contractor, at its sole expense, must maintain the insurance coverage identified below. All required insurance must: (a) protect the State from claims that may arise out of, are alleged to arise out of, or otherwise result from Contractor's or a subcontractor's performance; (b) be primary and non-contributing to any comparable liability insurance (including self-insurance) carried by the State; and (c) be provided by a company with an A.M. Best rating of "A-" or better, and a financial size of VII or better.
TABLE 6.1
| Required Limits |
| Additional Requirements |
Commercial General Liability Insurance
Minimum Limits:
$1,000,000 Each Occurrence $1,000,000 Personal & Advertising Injury $2,000,000 Products/Completed Operations $2,000,000 General Aggregate
Contractor must have their policy endorsed to add “the State of Michigan, its departments, divisions, agencies, offices, commissions, officers, employees, and agents” as additional insureds using endorsement CG 20 10 11 85, or both CG 20 10 12 19 and CG 20 37 12 19.
Umbrella or Excess Liability Insurance
Minimum Limits:
$5,000,000 General Aggregate Contractor must have their policy follow form.
Automobile Liability Insurance
Minimum Limits:
$1,000,000 Per Accident Contractor must have their policy: (1) endorsed to add “the State of Michigan, its departments, divisions, agencies, offices, commissions, officers, employees, and agents” as additional insureds; and (2) include Hired and Non-Owned Automobile coverage.
Workers' Compensation Insurance
Minimum Limits:
Coverage according to applicable laws governing work activities.
Waiver of subrogation, except where waiver is prohibited by law.
Employers Liability Insurance
Minimum Limits:
$500,000 Each Accident $500,000 Each Employee by Disease $500,000 Aggregate Disease
If any of the required policies provide claims-made coverage, the Contractor must: (a) provide coverage with a retroactive date before the Effective Date of the Contract or the beginning of Contract Activities; (b) maintain coverage and provide evidence of coverage for at least 3 years after completion of the Contract Activities; and (c) if coverage is cancelled or not renewed, and not replaced with another claims-made policy form with a retroactive date prior to the Contract Effective Date, Contractor must purchase extended reporting coverage for a minimum of 3 years after completion of work.
Contractor must: (a) provide insurance certificates to the Contract Administrator, containing the agreement or delivery order number, at Contract formation and within 20 calendar days of the expiration date of the applicable policies; (b) require that subcontractors maintain the required insurance contained in this Section; (c) notify the Contract Administrator within 5 business days if any insurance is cancelled; and (d) waive all rights against the State for damages covered by insurance. Failure to maintain the required insurance does not limit this waiver.
This Section is not intended to and is not to be construed in any manner as waiving, restricting or limiting the liability of either party for any obligations under this Contract (including any provisions hereof requiring Contractor to indemnify, defend and hold harmless the State).
7. Reserved.
8. Reserved.
9. Relationship of the Parties. The relationship between the parties is that of independent contractors. Contractor, its employees, and agents will not be considered employees of the State. No partnership or joint venture relationship is created by virtue of this Contract. Contractor, and not the State, is responsible for the payment of wages, benefits and taxes of Contractor’s employees and any subcontractors. Prior performance does not modify Contractor’s status as an independent contractor. Neither party has authority to contract for nor bind the other party in any manner whatsoever.
Intellectual Property Rights. If a Statement of Work requires Contractor to create any intellectual property, Contractor hereby acknowledges that the State is and will be the sole and exclusive owner of all right, title, and interest in the Contract Activities and all associated intellectual property rights, if any. Such Contract Activities are works made for hire as defined in Section 101 of the Copyright Act of 1976. To the extent any Contract Activities and related intellectual property do not qualify as works made for hire under the Copyright Act, Contractor will, and hereby does, immediately on its creation, assign, transfer and otherwise convey to the State, irrevocably and in perpetuity, throughout the universe, all right, title and interest in and to the Contract Activities, including all intellectual property rights therein.
10. Subcontracting. Contractor may subcontract work in accordance with Subsection 108.01 of the 2020 Standard Specifications for Construction.
11. Staffing. The State’s Contract Administrator may require Contractor to remove or reassign personnel providing services by providing a notice to Contractor.
12. Background Checks. Pursuant to Michigan law, all agencies subject to IRS Pub. 1075 are required to ask the Michigan State Police to perform fingerprint background checks on all employees, including Contractor and Subcontractor employees, who may have access to any database of information maintained by the federal government that contains confidential or personal information, including, but not limited to, federal tax information. Further, pursuant to Michigan law, any agency described above is prohibited from providing Contractors or Subcontractors with the result of such background check. For more information, please see Michigan Public Act 427 of 2018. Upon request, or as may be specified in a Statement of Work, Contractor must perform background checks on all employees and subcontractors and its employees prior to their assignment. The scope is at the discretion of the State and documentation must be provided as requested. Contractor is responsible for all costs associated with the requested background checks. The State, in its sole discretion, may also perform background checks.
13. Assignment. Contractor may not assign this Contract to any other party without the prior approval of the State. Upon notice to Contractor, the State, in its sole discretion, may assign in whole or in part, its rights or responsibilities under this Contract to any other party. If the State determines that a novation of the Contract to a third party is necessary, Contractor will agree to the novation and provide all necessary documentation and signatures.
14. Change of Control. Contractor will notify the State, within 30 days of any public announcement or otherwise once legally permitted to do so, of a change in Contractor’s organizational structure…