Attachment 1 - M-57 Proposal.pdf

PDF 420 KB Posted

Attached to
PMC M-57, Gratiot County, Washington Twp, HMA State and local contract opportunity
Solicitation number
RFP 591 250000001767 2
Issued by
Gogebic County, Michigan

About this file

This is a project proposal document from the Michigan Department of Transportation (MDOT) for a pavement mill and overlay project on M-57 in Washington Township, Gratiot County. The project involves a 1.5-inch uniform cold mill and single-course HMA overlay across approximately 2,250 feet of roadway from Station 768+99.00 to Station 791+49.00. Key work items include cold milling of 14,000 square yards of HMA surface, placement of 1,155 tons of 5EML high-stress HMA, installation of permanent and temporary pavement markings, and comprehensive traffic control measures. Work must begin no earlier than May 12, 2025, and be completed by August 8, 2025, within 4 consecutive workdays (weather dependent), excluding permanent pavement marking placement. The contractor must provide seven calendar days' notice to Jason Potts at 989-737-0211 before beginning work. Maintaining traffic is essential, with detailed specifications requiring shoulder and lane closures per established typicals and a maximum 0.5-mile closure length at any one time. Traffic must be maintained at a minimum of one lane in each direction, with the work zone speed limit set to 45 mph.

This is a maintenance-funded project with no allowance for overpayment or extras; all material, labor, and mobilization costs must be included in the bid price as a lump sum. MDOT reserves the right to reject any unqualified bids and may request a site and plan review meeting with the low bidder before award. Lane closures are restricted during specified holiday periods (Memorial Day, Independence Day, and Labor Day) and are limited to specific timeframes between 6:00 a.m. and 5:59 p.m. on weekdays, with no weekend work permitted unless approved by the Engineer. The contractor must comply with the MDOT 2020 Standard Specifications for Construction, preserve all government corners, contact MISS DIG at least three working days before excavation, maintain access to recreational properties, and coordinate with multiple utility providers including Consumers Energy, DTE Energy, Frontier Communications, and others listed for potential conflicts.

View the file

Other files for this state and local contract opportunity

Other files attached to PMC M-57, Gratiot County, Washington Twp, HMA, newest first.
File Type Posted
Attachment 4 - ORS-002120_MDOT_M57_Issued.03.11.25.pdf PDF
Attachment 2 - WHD-9917 FEB 9 2024.pdf PDF
Attachment 3 - WHD-9918 FEB 9 2024.pdf PDF
RFP 25-1767 PMC M-57 Cleveland Road.docx DOCX document
Addenda 1 - Bidder Q&A M-57 Mill_Fill.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOG OF PROJECT

M-57 C.S. 29021

J.N. 25-29002

PROGRESS SCHEDULE

Work may begin immediately after receiving approval from MDOT. Work must begin no earlier than May 12th, 2025, and be completed by August 8th, 2025. Work must be completed within 4 consecutive workdays, weather dependent, except for the placement of the permanent pavement markings. The workdays do not include Saturday and Sunday. Notice must be provided to Jason Potts at 989-737-0211 seven (7) calendar days prior to the beginning of any work.

JOB LOCATION

M-57 This project takes place on M-57 beginning approximately 950 feet west of Romney Rd where the center left turn lane merge begins. The project continues approximately 2250 feet east to the pavement joint at the sleeper slab on the west end of the US-127 overpass, which is approximately 450 east of the US-127 SB interchange ramps in Washington Township, Gratiot County.

Begin Station P.O.B = Station 768+99.00 C.S. = 29021 C.S. Mile Point 13.319 / P.R. 0497406 Mile Point 13.319

End Station P.O.E = Station 791+49.00 C.S. = 29021 C.S. Mile Point 13.745 / P.R. 0497406 Mile Point 13.745

DESCRIPTION OF WORK

The work shall consist of a 1.5’’ uniform cold mill and single course HMA overlay for the entire width of the pavement from the POB to POE. At crossroads and intersections, the milling and resurfacing limits shall be defined as a straight line along curb face to curb face or along existing pavement joint where mainline meets the approach. Once the paving operation is completed, the proposed pavement markings will be placed to match the current lane configuration.

Traffic will be maintained as described in the Maintaining Traffic section contained in this proposal.

ESTIMATED QUANTITIES

The quantities included in the summations below are approximate and for reference only.

The contractor will be responsible for verifying quantities before bidding by site inspection and plan review. If any major discrepancies are noted, contractor must contact Jacob Peterson at

(989) 573-0537.

This project is a Maintenance funded project, which means that there will be absolutely no overpayment or extras. All material, labor, and mobilization shall be included in the bid.

M-57 C.S. 29021

J.N. 25-29002

MDOT will have the low bid reviewed and approved for funding. MDOT reserve the right to reject any bid that appears to be unqualified. Before award, MDOT may request a site and plan review meeting with the low bid contractor.

Items of Work (for information only):

Mobilization, Max 1 LSUM Cold Milling HMA Surface 14,000 Syd HMA, 5EML, High Stress 1155 Ton

Maintaining Traffic Items:

Channelizing Device, 42 inch, Fluorescent, Furn 80 Ea Channelizing Device, 42 inch, Fluorescent, Oper 80 Ea Lighted Arrow, Type C, Furn 2 Ea Lighted Arrow, Type C, Oper 2 Ea Minor Traf Devices 1 LSUM Sign Cover 10 Ea Sign, Type B, Temp, Prismatic, Furn 425 Sft Sign, Type B, Temp, Prismatic, Oper 425 Sft Traf Regulator Control 1 LSUM Pavt Mrkg, Wet Reflective, Type R, Tape, 6 inch, Yellow, Temp 720 Ft Pavt Mrkg, Wet Reflective, Type R, Tape, 6 inch, White, Temp 396 Ft Permanent Pavement Markings:

Pavt Mrkg, Ovly Cold Plastic, Lt Turn Arrow Sym 4 Ea Pavt Mrkg, Ovly Cold Plastic, Rt Turn Arrow Sym 4 Ea Pavt Mrkg, Wet Reflective Polyurea, 6 inch, Yellow 5,950 Ft Pavt Mrkg, Wet Reflective Polyurea, 6 inch, White 4,660 Ft Witness, Log, $1,250.00 1,250 Dlr Recessing Pavt Mrkg, Longit 10,610 Ft

MAINTAINING TRAFFIC

Construction Influence Area (CIA) The CIA includes the right-of-way of the following roadways, within the approximate limits described below:

1. On M-57 from approximately 0.13 miles east of South Union Rd to 0.2 miles west of South Baldwin Rd.

2. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately 1/4 mile in advance of the work zone or as far as the construction or detour signing extends.

M-57 C.S. 29021

J.N. 25-29002

Traffic Restrictions Traffic shall be maintained according to Sections 104.07, 104.11, and 812 of the 2020 Standard Specifications for Construction, including any Supplemental Specifications, and as specified herein. Maintaining traffic will be accomplished with shoulder and lane closures utilizing the following maintaining traffic typicals:

100-GEN-KEY

101-GEN-SPACING-CHARTS

102-GEN-NOTES

103-GEN-SIGN

104-GEN-AB

107-GEN-SPEED

110-TR-NFW-2L

112-TR-CLT

*WZD-100-A

*WZD-125-E

*indicates Special Detail

Sign covers shall be placed over any regulatory, warning, or construction signs that are not applicable during construction.

Do not work, deliver material, or close lanes during the holiday periods as defined in Table 1.

Cover or remove “45 where workers present” signing during the holiday periods as defined in Table 1.

Table 1: 2025 Holiday Periods

Holiday Start Date and Time End Date and Time

Memorial Day 3:00 P.M., Friday, May 23rd 6:00 AM, Tuesday, May 27th

Independence Day 3:00 PM, Wednesday, July 2nd 6:00 AM, Monday, July 7th

Labor Day 3:00 PM, Friday, August 29th 6:00 AM, Tuesday, September 2nd

Perform work and lane closures within the allowable time frames as shown in Table 2, unless otherwise approved by the Engineer. Traffic switch operations on freeways may take place within the allowable times listed below in the traffic restriction tables and/or as otherwise approved by the Engineer. Additional lane, ramp, and/or roadway closures and shifts may be implemented during maintaining traffic stage and traffic switch operations with prior Engineer approval.

https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=67f64e52-8d1e-43fa-80c6-67291cc005a2&fileName=100-GEN-KEY.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=6dfdabdf-c842-4cf5-8187-5f7d8565fd86&fileName=101-GEN-SPACING-CHARTS.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=10487024-3ab5-4ed6-a61c-90479a9b3abb&fileName=102-GEN-NOTES.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=65bd8527-32ef-4479-91bd-f5489d67b8d9&fileName=103-GEN-SIGN.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=db492f06-7ee8-450f-9850-a28522ea2ebd&fileName=104-GEN-AB.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=57d49b8b-15bc-4652-87e6-8773a7bd1ea3&fileName=107-GEN-SPEED.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=79fd8944-e0b9-4e38-9b4b-6aa23b667408&fileName=112-TR-CLT.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=fc81bf1d-94e9-401c-9f92-ffac23f11ca2&fileName=WZD-100-A%20-%208in.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=dde79207-ba89-41d8-b425-c7483d1bd9ea&fileName=WZD-125-E%20-%208in.pdf

M-57 C.S. 29021

J.N. 25-29002

Perform traffic switch operations within the allowable “traffic restriction tables” as shown below.

A. A traffic switch is defined as a change in the existing (original or staged) traffic configuration which requires multiple (more than one) lane lines and/or edge lines to be relocated in a new location and the old lines to be removed either between construction stages, or maintenance of traffic stages.

B. Table 2: Traffic Restrictions Memorial Day to Labor Day

Closure Type Start Time

End Time

M Tu W Th F Sa Su

Shoulder Closures 00:00 23:59 ∞ ∞ ∞ ∞ ∞ ∞ ∞

Lane Closures

00:00 05:59 0 0 0 0 0 0 0 06:00 14:59 1 1 1 1 1 0 0 15:00 19:59 1 1 1 1 0 0 0 20:00 23:59 0 0 0 0 0 0 0

∞ = Closure is allowed, and the frequency is not limited during the project timeframe # = The number of times closures can take place during the project timeframe.

The Contractor shall maintain a minimum of one lane of traffic in each direction at all times on M-57. (And all intersecting roads and ramps.) Additional traffic regulators shall be used at unsignalized intersections and driveways, as directed by the Engineer. Payment for these items shall be included in the lump sum price for the project.

There is to be no more than 1 closure allowed at any one time.

A. The maximum closure length is 0.5 miles from the POB to POE unless otherwise approved by the engineer.

When a lane is closed, place channelizing devices at cross streets and major drives to form a radius that clearly defines the approaches to the through and turning traffic.

A speed reduction will be used. Set the work zone speed limit on M-57 to 45 miles per hour (mph).

All lanes shall be flush with each other at the end of each workday with no vertical edges along

EOM.

No weekend work unless approved by the Engineer. Weekend work is defined as 3:00 pm on Friday through Sunday. All lanes and shoulders shall be open to traffic unless work is in progress which prohibits opening of lanes due to safety or other reasons approved by the engineer.

M-57 C.S. 29021

J.N. 25-29002

The storage restrictions in section 812.03.G.5 of the 2020 Standard Specifications for Construction will be strictly adhered to. The Contractor shall not park any vehicle or store any material on public recreational property.

Daily maintenance of traffic control items will not be paid for separately but will be included in the lump sum price for the project.

GENERAL NOTES

SPECIFICATIONS FOR CONSTRUCTION

The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.

RECREATIONAL PROPERTIES

The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times.

Noncompliance, even without the knowledge and approval of MDOT personnel, can result in penalties up to and including termination of the construction contractor and loss of federal funding for the project. Should there be any questions regarding this requirement, contact the MDOT Environmental Section at (517) 373-8350.

MISS DIG/UNDERGROUND UTILITY NOTIFICATION

Contact MISS DIG System, Inc. for the protection of underground utilities and in conformance with MCL 460.721 et seq, by phone at 811 or 800-482-7171 or via the web at either elocate.missdig.org for single address or rte.missdig.org, a minimum of 3 working days prior to excavating, excluding weekends and holidays.

PRESERVATION OF BOUNDARY MONUMENTS

All government corners on this project shall be preserved, whether shown or not. It may be necessary to place or adjust monument boxes, as required.

OLD ROAD PLANS

The following old road plans were referred to in the design of this project.

JN 100141A

JN 45822

STATIONING

Stationing on this project was taken from old plans & right of way maps and is not necessarily accurate.

M-57 C.S. 29021

J.N. 25-29002

PLAN SCALE

The final plans submitted with the proposal are not to scale. Fabricate proposed signs and structures shown on plan sheets in accordance with Typical Plans, Standards, and/or Details at locations described.

NOTES APPLYING TO STANDARD PLANS

Where the following items are called for on the plans, they are to be constructed according to the Standard Plan or Special Detail given below opposite each item unless otherwise indicated.

Driveway Openings & Approaches and Concrete Sidewalks R-29-J

TRAFFIC AND SAFETY STANDARDS

Pavement Arrow and Message Details PAVE-900-H

Longitudinal Line Types and Placement PAVE-905-F

Pavement Markings for Non-Signalized Intersections PAVE-930-E

Left Turn Lane Markings PAVE-935-F

Right Turn Lane and Island Pavement Markings PAVE-940-E

Intersection, Stop Bar and Crosswalk Markings PAVE-945-E

PUBLIC UTILITIES

Consumers Energy 1945 West Parnall Road, P12-208A Jackson, Michigan 49201 Ph: 517-788-0817(W) Attn: Pete Mulhearn

Consumers Energy 1325 Wright Avenue Alma, Michigan 48801 Ph: 517-285-4629(W) Attn: Erica Baumann

Consumers Energy 2400 Weiss Street Saginaw, Michigan 48602 Ph: 989-791-5918(W) Attn: Ben Lewis

Electric

Electric

Gas https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=a54fc5bd-623f-41c3-8bac-49298c106194 https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=baac7af0-d2bf-49fd-8ea1-cd35cfb3c567&fileName=PAVE-900-H.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=16bc4850-a345-4155-b923-2926cd10f2d2&fileName=PAVE-905-F.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=6f1f729d-2c31-4a63-ade9-b293ee323146&fileName=PAVE-930-E.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=cd20c811-17d9-4a18-8daf-60694ccafe02&fileName=PAVE-935-F.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=c6f8abbc-cf39-41f4-8139-3bab11b0f0ef&fileName=PAVE-940-E.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=9a98f4bd-bb08-4fd1-8dd7-680ae0b50a04&fileName=PAVE-945-E.pdf

M-57 C.S. 29021

J.N. 25-29002

Consumers Energy 1945 West Parnall Road, P23-228 Jackson, Michigan 49201 Ph: 517-788-0998(W) Attn: Timothy Coppernoll

Gas

DTE Energy / MichCon Gas 609 Bjornson Big Rapids, MI 49307 Ph: 231-592-3244(W) Attn: Larry Bourke

Gas

DTE Energy / MichCon Gas One Energy Plaza,1722 WCB Detroit, Michigan 48226-1221 Ph: 313-235-1080(W) Attn: Greg Blosser

Gas

Frontier Communications 345 Pine Avenue Alma, Michigan 48801 Ph: 989-763-3129(W) Attn: Chris Stanton

Telecom

Fulton Township 3425 W Cleveland Rd Middleton, Michigan 48856 Ph: 989-236-5102(W) Attn: Phil Foster

Storm

Gratiot County Drain Commissioner 904 East Center Street Ithaca, Michigan 48847 Ph: 989-875-5207(W) Attn: Bernard Barnes

County Drain

Point Broadband Fiber 617 E. Lake St Stanton, Michigan 48888 Ph: 989-330-6384(W) Attn: Josh White

Telecom

M-57 C.S. 29021

J.N. 25-29002

Tri-County Electric Coop.

7973 E. Grand River Avenue Portland, Michigan 48875 Ph: 517-647-1214(W) Attn: Val Wohlscheid

Electric

Windstream KDL 800 N. Durand Rd Corunna, MI 48817 Ph: 812-253-1553 (W) Attn: Chris Rogers

Telecom

Wolverine Power Supply 10125 W Watergate Road, P O Box 229 Cadillac, Michigan 49601 Ph: 231-775-5700(W) Attn: Ron Sneller

Electric

M-57 US-127SB Interchange_West_TitleSheet
M-57 Mill & Fill US-127 Interchange_LOG
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING
M-57_TYP_001
M-57_TYP_002
Insert from: "103-GEN-SIGN.pdf"
103-GEN-SIGN
103-GEN-SIGN
103-GEN-SIGN
103-GEN-SIGN
103-GEN-SIGN
Insert from: "25-2902_M-57 Log.pdf"
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING
Insert from: "25-2902_M-57 Log.pdf"
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING
Insert from: "25-29002_Log of Project.pdf"
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING
Insert from: "25-29002_Log of Project.pdf"
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING
Insert from: "25-29002_Log of Project.pdf"
GENERAL NOTES
SPECIFICATIONS FOR CONSTRUCTION
The improvements covered by these plans shall be done in accordance with the MDOT 2020 Standard Specifications for Construction.
RECREATIONAL PROPERTIES
The Contractor shall not park any vehicles or store any equipment on public recreational property. Access to the recreational properties must also be maintained at all times. Noncompliance, even without the knowledge and approval of MDOT personnel, ca...
MISS DIG/UNDERGROUND UTILITY NOTIFICATION
PRESERVATION OF BOUNDARY MONUMENTS
OLD ROAD PLANS
STATIONING