RFP 25_009 Q AND A HMS TRACK REPAVING.pdf

PDF 175 KB Posted

Attached to
25-009 RFP HMS TRACK REPAVING
Solicitation number
PE-67610-NONST-2025-000000044
Issued by
Henry County, Georgia

About this file

This document is a Questions and Answers (Q&A) file related to Request for Proposals (RFP) 25-009 for the repaving of the athletic track located at Huntington Middle School in the Houston County School District, Georgia. The school district is seeking proposals for this track repaving project, but has not determined an estimated cost or construction cost range at this time. No other details about the project scope, timeline, or contract terms are provided in the Q&A.

The document does not contain any information about pricing, set asides, incumbents, funding sources, or other salient details related to this contract opportunity. The Q&A file solely addresses the lack of a defined budget or cost estimate for the proposed track repaving work.

View the file

Other files

File Type Posted
25_009 AMENDMENT 1.pdf PDF
RFP 25_009 AWARD MEMO.pdf PDF
RFP 25_009 APPENDIX 2 CORE SAMPLE REPORT.pdf PDF
RFP 25_009 HMS TRACK.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HOUSTON COUNTY SCHOOL DISTRICT

REQUEST FOR PROPOSALS

For

HMS Track Repaving

RFP NUMBER 25-009

Questions and Answers

1. Question: What is the estimated cost or budget?

Answer: No estimated budget has been determined at this time.

2. Question: Construction cost estimate or a construction cost range for the project:

Answer: No construction cost estimate or construction cost range has been determined at this time.