This document is an addendum to a Request for Proposals (RFP) issued by the City of Norfolk, Virginia for Roofing and Masonry Repair and Maintenance Services. The RFP was originally issued under RFP Number 240089KG and has a bid closing date of January 11, 2024 at 11:00 PM, which remains unchanged. The addendum addresses a question regarding the requirement for the contractor to stock flooring materials. The City clarifies that there is no need for the contractor to keep an inventory of flooring, but they must ensure that all materials and supplies are available when needed for each project.
The underlying RFP is for Carpentry & Flooring Installation, Maintenance, Repairs & Related Services within the City of Norfolk. The contract term and any renewal options are not specified in the provided information.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
January 3, 2023
RFP 240089KG
ADDENDUM #1
RFP TITLE: Roofing and Masonry Repair and Maintenance
Services
Bid Closing Date: January 11, 2024, 11:00 PM (unchanged)
The following is to make is the response to questions in regard to the solicitation.
Question: Page 3-B. Scope of Work/Specifications
A.2.C- Materials and Supplies: The third paragraph- In regard to stocked flooring. Generally, we do not keep large quantities of flooring in stock, most being treated as special orders. However, we can manage within reasonable stock levels. Could you provide details on the standard style/color and the expected quantity that would need to be stored (if any)? Additionally, would the materials be paid for before being stored in our warehouse in case stocking is required.
Answer: Because each project will be different requiring different flooring and colors there will be no need for
Contractor to keep an inventory of flooring, however; it is important that once Contractor provide and estimate of a project that they are able to make sure that all materials and supplies are available during the project.
Acknowledge receipt and agreement with this addendum as part of your offer by filling in the Addenda
Acknowledged section of the Bid Cover Sheet. Signature on this addendum does not substitute for your signature on the original bid document. The original bid document must also be signed.
Sincerely, Keith B. Gordon
Keith B. Gordon
Senior Buyer
ACKNOWLEDGEMENT
Name of Firm
Signature & Title
Date