The document is a Request for Proposal (RFP) issued by the City of Commerce, Georgia for the 2024 LMIG Street Paving project. The City is seeking qualified professional service providers to provide experienced labor for 2024 LMIG Street paving, including all necessary labor, construction equipment, fuel, materials, and other requirements for successful project completion. The work must conform to the project specifications and all applicable local, state, and federal codes and regulations. The contract term is 180 consecutive calendar days from the Notice to Proceed. Sealed bids are due by 2:00 PM on June 13, 2024 at the Commerce City Hall, and will be publicly opened and read aloud the same day. The City reserves the right to reject any and all submittals.

The RFP provides detailed requirements for the project scope, site inspections, project schedule, proposal format, and the selection process. Pricing must be submitted as a lump sum for the total project. The City will evaluate proposals based on references, overall cost and pricing, the vendor's approach, and company background. The selected vendor will be required to provide performance bonds, insurance, and comply with anti-discrimination and immigration requirements.

View the file

Other files

File Type Posted
Vendor Master.pdf PDF
RFP 24_004 ADDENDUM _3.pdf PDF
FY24 LMIG Street List.pdf PDF
Tally Sheet 24_004.pdf PDF
RFP 24_004 ADDENDUM _2.pdf PDF
RFP 24_004 ADDENDUM _1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 24-004

SUBJECT: Request for Proposal for 2024 LMIG Street Paving

The City of Commerce is soliciting competitive sealed bids from qualified professional service providers to provide experienced labor for 2024 LMIG Street in the City of Commerce.

The Contractor shall provide the necessary labor, construction equipment, fuel, materials, and etc.

required for the successful completion of the project. All Work shall conform to the Project Specifications and all applicable local, state and federal codes and regulations. Contract time shall be 180 consecutive calendar days from the date of the Notice to Proceed.

Attached hereto are the general conditions, technical specifications, and submittal format:

The written requirements contained in this Request for Proposal (RFP) shall not be changed or superseded except by a written addendum from The City of Commerce. Failure to comply with the written requirements for this RFP may result in disqualification of the submittal by The City of Commerce.

Sealed Bids will be received no later than 2:00 P.M. local time at the Commerce City Hall, 27 Sycamore Street, Commerce, GA 30529, on Thursday, June 13, 2024. Bids received after the stated time will not be accepted. Proposals will be opened publicly and read aloud on Thursday, June 13, 2024, at 2:00 P.M. local time. The City of Commerce reserves the right to reject any and all submittals, to waive any technicalities or irregularities and to award contracts based on the highest and best interest of the city.

The City of Commerce does not discriminate on the basis of disability in the admission or access to its programs or activities. Any requests for reasonable accommodation required to fully participate in any open meeting, program or activity should be directed to City Hall at 706-335-3164.

The City of Commerce will select the bid that, in its sole discretion, is the most responsive and responsible to the City. The City is not liable for any cost incurred by vendors in the preparation of this bid.

We look forward to your bid and appreciate your interest in the City of Commerce.

City of Commerce P.O. Box 348

27 Sycamore Street Commerce, GA 30529 Phone: (706) 335-1893

Email: ccase@commercega.gov

CITY OF COMMERCE, GEORGIA

REQUEST FOR QUALIFICATION

FOR

2024 LMIG Street Paving

SECTION I - REQUEST FOR PROPOSAL OVERVIEW

1.0 PURPOSE

The City of Commerce is accepting sealed proposals from qualified vendors for LMIG STREET

RESURFACING PROJECT 2024.

1.1 RFP TIMETABLE

1.1.1 RFP Available May 8, 2024

1.1.2 Deadline for questions June 4, 2024

1.1.3 Submittal deadline June 13, 2024 @ 2:00 pm EST

1.2 RFP SUBMISSION

One (1) original, one (1) copy, and one (1) fully executable electronic copy (PDF) of the complete signed submittal must be received by submittal deadline (see 1.1). Proposals must be submitted in a sealed envelope stating on the outside, the vendor's name, address, the RFP # and title to:

City of Commerce P.O. Box 348

27 Sycamore Street Commerce, GA 30529

Attention: Finance Director

Hand delivered copies may be delivered to the above address ONLY between the hours of 8:30 a.m.

and 4:30 p.m. ET, Monday through Friday, excluding holidays observed by the City of Commerce.

Vendors are responsible for informing any commercial delivery service, if used, of all delivery requirements and for ensuring that the required address information appears on the outer wrapper or envelope used by such service. The Submittal must be signed by a company officer who is legally authorized to enter into a contractual relationship in the name of the vendor.

1.3 CONTACT PERSON & INQUIRES:

1.3.1 Vendors are encouraged to contact Christy Case at ccase@commercega.gov to clarify any part of the RFP requirements, or any questions regarding submittals. All questions that arise must be submitted prior to the submittal due date (see 1.1) and shall be directed to the contact person in writing via email.

1.3.2 Any unauthorized contact shall not be used as a basis for responding to this RFP and may result in the disqualification of the vendor's submittal. Vendors may not contact any elected official or other City of Commerce employee to discuss the proposal process or proposal opportunities. Contact of this nature will result in immediate disqualification of the vendor.

1.4 ADDITIONAL INFORMATION/ADDENDA

The City of Commerce will issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the due date. Vendors should not rely on any representations, statements or explanations other than those made in this RFP or in any addendum to this RFP. Where there appears to be a conflict between the RFP and any addenda issued, the last addendum issued will prevail.

Addenda will be published at www.commercega.gov under the “Doing Business Here” tab. Vendors are encouraged to check this site regularly for immediate access to issued addenda. RFP information can also be requested as stated above (1.3).

Vendors must acknowledge any issued addenda by including the Addenda Acknowledgement Form with the submittal. Proposals which fail to acknowledge the vendor’s receipt of any addendum will result in the rejection of the offer if the addendum contains information which substantively changes the Owner’s requirements

1.5 LATE SUBMITTAL, LATE MODIFICATIONS AND LATE WITHDRAWALS

Submittals received after the due date and time will not be considered. Modifications received after the due date will not be considered. The City of Commerce assumes no responsibility for the premature opening of a proposal not properly addressed and identified, and/or delivered to the proper designation.

1.6 REJECTION OF PROPOSALS

The City of Commerce may reject any and all submittals and reserves the right to waive any irregularities or informalities in any submittal or in the submittal procedure. Submittals received after said time or at any place other than the time and place will not be considered.

1.7 MINIMUM RFP ACCEPTANCE PERIOD

Valid submittals shall not be withdrawn for a period of 90 days from the date specified for receipt of submittals.

1.8 NON-COLLUSION AFFIDAVIT

By submitting a response to this RFP, the vendor represents and warrants that such proposal is genuine and not a sham or collusive or made in the interest or in behalf of any person not therein named and that the vendor has not directly or indirectly induced or solicited any other vendor to put in a sham proposal, or any other person, firm or corporation to refrain from submitting and that the vendor has not in any manner sought by collusion to secure to that vendor any advantage over any other vendor.

By submitting a proposal, the vendor represents and warrants that no official or employee of the City of Commerce has, in any manner, an interest, directly or indirectly in the proposal or in the contract which may be made under it, or in any expected profits to arise there from.

1.9 COST INCURRED BY VENDORS

All expenses involved with the preparation and submission of the RFP to the City of Commerce, or any work performed in connection therewith is the responsibility of the vendor(s).

http://www.commercega.gov/

1.10 RFP OPENING

At the time and place fixed for opening the bids, the total bid amount of all bids will be made public for the information of all bidders and other interested parties, who may be present in person or by a representative. After the RFP due date and time stated herein, a tally sheet will be available on the City’s website.

1.11 TAXES

Selected vendor will be provided with The City of Commerce Sales and Use Tax Certificate of Exemption number upon request.

1.12 VENDOR INFORMATION

All submissions shall include a completed vendor master form and current W-9. Vendors whose place of business is other than the State of Georgia may be required to provide the Purchasing Agent with copies of your state’s regulations and/or laws concerning the application of certain vendor preference requirements to vendors whose place of business is in the applicable state.

Failure to provide this information will result in the disqualification of the vendor from submitting a proposal.

1.13 INSURANCE

Selected vendor will be required to provide proof of liability and workman’s compensation insurance before work can begin on this City’s project. Workman’s Compensation Insurance should be as required by the State of Georgia. General Liability should cover $1,000,000 per incident. The vendor, if awarded a contract, shall maintain insurance coverage reflecting the minimum amounts and conditions specified by the City. In the event the vendor is a government entity or a self-insured organization, different insurance requirements may apply.

The vendor shall procure and maintain for the life of the Contract/Agreement Worker’s Compensation Insurance covering all employees with limits meeting all applicable state and federal laws. This coverage shall include Employer’s Liability with limits meeting all applicable state and federal laws. This coverage shall extend to any subcontractor that does not have their own Worker’s Compensation and Employer’s Liability Insurance. A thirty (30) day notice of cancellation is required and must be provided to the City of Commerce via Certified Mail.

1.14 TERMINATION

Federal, State, and other Local government agencies may terminate this agreement in the event funds are not appropriated for it in future periods; provided, however, that funds are also not appropriated for equipment or services that replace those contracted for under this agreement.

Customer shall be obligated for any future annual period if Company is not notified in writing at least thirty (30) days prior to the beginning for the annual period for which non-appropriation is being claimed.

1.15 ANTI-DISCRIMINATION

By submitting a response to this RFP, all perspective contractors certify to The City of Commerce they will conform to the provisions of the Federal Civil Rights Act of 1964, as amended, in every contract of over $10,000 the provisions in 1.15.1 and 1.15.2 below apply:

1.15.1 During the performance of this contract, the contractor agrees as follows:

1.15.1.1 The contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex or national origin, except where religion, sex or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.

1.15.1.2. The contractor, in all solicitations or advertisements for employees placed by or on behalf of the contractor, will state that such a contractor is an equal opportunity employer.

1.15.1.3. Notices, advertisements, and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.

1.15.1.2 The contractor will include the provisions of 1.15.1 above in every subcontract or purchase order of over $10,000 so that the provisions will be binding upon each subcontractor or vendor.

1.16 ILLEGAL IMMIGRATION REFORM AND ENFORCEMENT ACT OF 2011

Vendors submitting a response to this RFP must complete the Contractor Affidavit under O.C.G.A.

§13-10-91(b) (1) which is provided with the RFP package to verify compliance with the Illegal Immigration Reform and Enforcement Act of 2011.

1.16.1 The form must be signed by an authorized officer of the contractor or their authorized agent.

1.16.2 The form must be notarized.

1.16.3 The contractor will be required to have all subcontractors and sub-subcontractors who are engaged to complete physical performance of services under the final contract executed between the City of Commerce and the contractor complete the appropriate subcontractor and sub-subcontractor affidavits and return them to the City of Commerce a minimum of five (5) days prior to any work being accomplished by said subcontractor or sub-subcontractor. A format for this affidavit can be provided to the contractor if necessary.

1.17 SUBMISSION REQUIREMENTS

To facilitate evaluation of Proposals please submit the following:

1.17.1 One (1) fully executable electronic copy of the response (in Word or .pdf format) and any Technical Requirements (in Excel format).

1.17.2 Two (2) paper versions of the bid. The original shall be clearly marked “original”.

1.17.3 The proposals shall be prepared with a straightforward, concise delineation of the vendor’s capabilities to satisfy the requirements of this RFP.

1.18 ACCEPTANCE

Submission of any proposal indicates acceptance of the conditions contained in the RFP unless clearly and specifically noted otherwise in the Bid.

1.19 CITY GOVERNMENT

The City of Commerce operates under a council-manager form of government. This system of local government utilizes the strong political leadership of elected officials in the form of the City Council. The City Manager is hired to serve the council and the community and to bring the local government the benefits of training and experience in administering local projects and programs on behalf of the governing body. It is anticipated that the vendor may be required to make one or more appearances at City Council meetings to answer questions and present results. The documentation provided in this request for proposal is intended to provide a common methodology of development and basic technical skills for proposal purposes.

1.20 BONDING

1.20.1 A performance bond in the amount equal to 100% of the contract amount will be required upon contract.

1.20.2 Each bid must be accompanied with a bid bond in an amount equal to 5% of the base bid, payable to the City of Commerce and issued by a Corporate Surety authorized to do business in the State of Georgia, in order to guarantee that the bidder will enter into a contract to construct the project strictly within the terms and conditions stated in this bid and in the bidding and Contract Documents, should the construction contract be awarded to him.

SECTION II - GENERAL CONDITIONS

2.0 PURPOSE

The City of Commerce is issuing this Request for Proposal (RFP) for qualified professionals from respondents capable of completing and providing professional contractual services for the Public Works Department for 2024 LMIG Street Paving.

2.1 CONTRACT PERIOD

Any contract resulting from this RFP shall not exceed a period of 180 days from the time the notice to proceed is provided, until completion of the project; unless agreed to in writing by both parties.

The awarded contractor will be required to provide an 18 (eighteen) month warranty on all work performed. To that end it requests proposals from qualified firms that meet the specifications listed herein.

2.2 CONTRACT LABOR COST DETAILS

Project labor cost shall be submitted for the following street projects. These costs are in totality as a lump sum submitted.

2.3 CERTIFICATIONS REQUIRED

The successful contractor shall provide details of operator qualifications for all employees that will be part of the installation or construction. The operator qualifications reports are required before any construction can begin. A copy of the successful contractor’s drug and alcohol testing plan is also required along with the latest PHMSA Drug and Alcohol Testing Data. While under contract with the City of Commerce this PHMSA Drug and Alcohol Testing Data shall be submitted to the City quarterly throughout the life of the contract.

2.4 ADMINISTRATION

The project will be administered by the City of Commerce through the Finance Director being the main point of contact for all questions during the proposal period. The Public Works Superintendent, or designee, will be the main point of contact once the project is initiated.

2.5 PROCEDURES & MISC. ITEMS

2.5.1 All questions shall be submitted in writing (e-mail is acceptable) and will be communicated to all firms responding to this RFP.

2.5.2 All materials submitted in connection with this RFP will be public documents and subject to the Open Records Act and all other laws of the State of Georgia, the United States of America and the open records policies of the City of Commerce. All such materials shall remain the property of the City of Commerce and will not be returned to the respondent.

2.5.3 All respondents to this RFP shall hold harmless the City of Commerce, and any of their officers and employees from all suits and claims alleged to be a result of this RFP.

The issuance of this RFP constitutes only an invitation to present a proposal. The City of Commerce reserves the right to determine, at its sole discretion, whether any aspect of a respondent's submittal meets the criteria in this RFP. The City of Commerce also reserves the right to seek clarifications, to negotiate with any vendor submitting a response, to reject any or all responses with or without cause, and to modify the procurement process and schedule. In the event that this RFP is withdrawn or the project canceled for any reason, the City of Commerce shall have no liability to any respondent for any costs or expenses incurred in connection with this RFP or otherwise.

2.5.4 Failure to submit all the mandatory forms from this RFP package shall be just cause for the rejection of the qualification package. However, the City of Commerce reserves the right to decide, on a case by case basis, in its sole discretion, whether or not to reject such a proposal as non-responsive.

2.5.5 Any payment terms requiring payment in less than 30 days will be regarded as requiring payment 30 days after invoice or delivery, whichever occurs last. This shall not affect offers of discounts for payment less than 30 days, however. Payment will be processed after completion of all construction and the successful testing of all installed products.

2.5.6 In case of failure to deliver goods in accordance with the contact terms and conditions, The City of Commerce, after due oral or written notice, may procure substitute goods or services from other sources and hold the contractor responsible for any resulting additional purchasing and administrative costs. This remedy shall be in addition to any other remedies which the City of Commerce may have.

2.5.7 By submitting a qualification package, the vendor is certifying that they are not currently debarred from bidding on contracts by any agency of the State of Georgia, nor are they an agent of any person or entity that is currently debarred from submitting proposals on contacts by any agency of the State of Georgia.

2.5.8 Any contract resulting from this RFP shall be governed in all respects by the laws of the State of Georgia and any litigation with respect thereto shall be brought in the courts of the State of Georgia. The contractor shall comply with applicable federal, state, and local laws and regulations.

2.5.9 It is understood and agreed between the parties herein that the City of Commerce shall be bound hereunder only to the extent of the funds available, or which may hereafter become available for the purpose of this agreement.

2.5.10 It is understood and agreed that all necessary paving equipment, asphaltic concrete, painting equipment, stencils, paint products, and all other materials, equipment, and supplies, may be needed to complete the project. The work shall be executed in the best and most workmanlike manner by qualified and efficient workers, in strict conformity with the best standard practice.

3.0 PROJECT SCOPE

3.1.1 Asphalt paving, striping, and associated work on various City streets within 180 consecutive calendar days from NTP (notice to proceed) and shall include all labor, materials and incidentals necessary to construct the project.

3.1.2 A preliminary list of streets will be included in the bid packet. The amount of work may increase or decrease, and the preliminary list of streets is subject to change.

This project includes some GDOT LMIG funding. The latest GDOT Standard Specifications for Road and Bridge Construction of the Georgia Department of Transportation as amended herein, shall govern the construction of this project.

3.1.3 For resurfacing, clean, tack and overlay each listed street with 1.5” thick layer of pave topping material, per each individual as identified street specification at a total lump sum cost.

3.1.4 All warning and advance signs are to be in place alerting motorist of street resurfacing activities at all times. Temporary reflective tape shall be used on each individual listed street.

3.1.5 Have designated certify flagging personnel present on site at all times actively directing traffic.

3.1.6 Contractors must provide a 24-hour clean-up service when each project is completed.

3.1.7 All drainage structures within the limits of each project listed will be maintained throughout the duration of the project. Any debris that goes in drainage structures as a result of resurfacing or milling operation will be cleaned out at no additional cost to the City of Commerce.

3.1.8 The City will locate and identify all water valves and manholes and raise those that are justified as needed.

3.1.9 An inspection will be completed by the City of Commerce Public Works Department.

3.2 SITE INSPECTIONS

3.2.1 The Bidder is advised to examine all the locations of the work and to inform himself fully as to its conditions, the conformation of the ground, the character, quality and quantity of the products needed preliminary to and during the execution of the work; the general and local conditions and all other matters which can in any way affect the work to be done under the Contract.

3.3 Project cost shall include all material costs, travel, shipping, additional materials, etc.

3.4 Project Schedule

3.4.1 Commerce City Council awards the Proposal

3.4.2 Contract will be signed

3.4.3 Notice to proceed will be issued to vendor by Finance Director

3.4.4 Vendor to provide a projects schedule with start dates

SECTION THREE – PROPOSAL FORMAT

4.0 PROPOSAL FORMAT

In order to facilitate the analysis of responses to this RFP, vendors are required to prepare their proposals in accordance with the instructions outlined in this section. Each vendor is required to submit the proposal in a sealed package. Vendors whose proposals deviate from these instructions may be considered non-responsive and may be disqualified at the discretion of the City of Commerce. Vendors should be sure they have included an electronic copy of the response as part of their proposal. Instructions relative to each part of the response to this RFP are defined in the remainder of this section.

4.1 EXECUTIVE SUMMARY AND MANDATORY SUBMITTALS

The Executive Summary portion of the response to the RFP should be limited to a brief narrative highlighting the vendor’s proposal. The summary should contain as little technical jargon as possible and should be oriented toward non-technical personnel.

4.2 COMPANY BACKGROUND

Vendors must provide the following information about their company so that the City can evaluate the vendor’s stability and ability to support the commitments set forth in response to the RFP. The City, at its option, may require a vendor to provide additional support and/or clarify requested information. The vendor should outline the company’s background, including:

4.2.1 How long the company has been in business.

4.2.2 A brief description of the company size and organization.

4.2.3 The number of and history of other public sector installations.

4.3 CLIENT REFERENCES

Vendors should provide at least five (5) client references that are similar in size or complexity to the City of Commerce, located in the state of Georgia. Information should include at the minimum:

name of client reference, name of agency, address, telephone, and e-mail.

4.4 BID SHEET

Vendor shall supply and submit bid sheet or contract to be signed with the overall lump sum cost of the project for all streets listed in totality. This format is a minimum requirement; vendors should add additional information to give a full picture of itemized service expenses. The vendor will present, in detail, features and capabilities of the proposed products. Please reference the “Project Scope” to gain insight on what applications will be needed.

4.5 ADDENDA

If revisions become necessary, the City will provide written addenda to all vendors who have received the RFP. Said addenda will be posted on the City’s website. All addenda issued by the City must be so noted on any bids that are submitted to the City. Vendors shall contact the City to ascertain whether any addenda have been issued. Failure to do so could result in an unresponsive bid.

SECTION IV - SELECTION

5.0 FINAL SELECTION

Following review of all qualified proposals, selection of a suitable vendor, and preliminary contract negotiations, the project representative will make a recommendation to the City Council of Commerce. Following approval, the City will complete contract negotiations. The City of Commerce reserves the right to accept the response that is determined to be in the best interest of the City. The City reserves the right to reject any and or all proposals. Every vendor submitting a proposal must complete the form showing compliance with the Illegal Immigration Reform and Enforcement Act of 2011, OCGA §13-10-90(b)(1). The form is provided with this RFP.

5.1 Evaluation Method

The City will evaluate all proposals deemed responsive to this request by a committee selected by the City of Commerce. One vendor will be awarded all streets listed.

5.2 Selection Criteria

Responses to this RFP will be scored according to the following criteria:

5.2.1 References - 10 points

5.2.2 Overall Cost & Pricing - 50 Points

4.2.3 Approach to project – 20 Point

4.2.4 Company Background – 20 Points

Attachments

Street Name Start Crossroad Stop Crossroad Length

(ft) *

Length (Miles) *

Avg Width

(ft) *

Double Yellow

White Edge

Square Yards

Elizabeth Street State Street Victoria Street 1,627 0.3081 20 √ 3,615.56 Central Avenue Clayton Street Little Street 830 0.1572 18 1,660 Clayton Street Scott Street Piedmont Street 1,600 0.3030 18 √ 3,200 Belmont Park Drive 1128 address 906 address 1,296 0.2455 24 3,456 Avery Court Homer Road ML King Jr Drive 234.44 0.0444 18 469.66 Lakeview Drive University Drive Minish Drive 2,128.05 0.4030 18 √ √ 4,256.10 Minish Drive Lakeview Drive Waterworks Road 1,664.30 0.3152 18 √ √ 3,250.93 University Drive Jefferson Road Lakeview Drive 859.86 0.1629 18 √ √ 1,701.57 Wilhard Street Elm Street End of Pavement 142.19 0.0269 20 315.03 Thomas Drive State Street End of Pavement 600.38 0.1137 22 1,467.60

TOTAL 10982.22 2.07997 23,392.44

Required Forms for Submission

EXECUTION OF PROPOSAL

DATE: ___________

The potential vendor certifies the following by placing an "X" in all blank spaces:

___ That this proposal was signed by an authorized representative of the firm.

___ That the potential Contractor has determined the cost and availability of all materials and supplies associated with performing the services outlined herein.

___ That all labor costs associated with this project have been determined, including all direct and indirect costs.

___ That the potential Contractor agrees to the conditions as set forth in this Request for Proposal with no exceptions.

Therefore, in compliance with the foregoing Request for Proposal, and subject to all terms and conditions thereof, the undersigned offers and agrees, if this proposal is accepted within sixty (60) days from the date of the opening, to furnish the services/products for the prices quoted within the time frame required. The undersigned offers and agrees to furnish any or all of the items upon which prices are quoted at the price set opposite each item, in the quantities described, delivered to the point(s) specified, in accordance with the terms and conditions set forth herein. The laws of the State of Georgia shall prevail concerning all purchases and services under this contract.

I certify that I have read and understand the terms and conditions herein except as stated below. I further state that I am and/or my company is capable, able to, and will provide the requested products and/or service described herein. I am the owner or agent of the company stated below and am authorized and empowered to contract. By my signature on this RFP, I/we guarantee and certify that all items included in my bid meet or exceed specifications.

I certify that this quotation is made without prior understanding, agreement, or connection with any corporation, firm or person submitting a quotation for the same materials, supplies, equipment, or services and is in all respects fair and without collusion or fraud. I understand collusive bidding is a violation of State and Federal Law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of the quotation and certify that I am authorized to sign this quotation for the Contractor.

Business Contact Representative

Operational Contact Representative

Vendor’s Name Federal ID #

Address

Phone Fax

Email

Authorized Signature Date

Typed Name & Title

Subscribed and sworn to before me this ______ day of _______________, 20____.

Notary Public

ADDENDA ACKNOWLEDGEMENT

The vendor has examined and carefully studied the Request for Proposals and the following

Addenda, receipt of all of which is hereby acknowledged:

Addendum No. ______________

Addendum No ______________

Authorized Representative/Title Authorized Representative (Date) (Print or Type) (Signature)

Vendors must acknowledge any issued addenda. Proposals which fail to acknowledge the vendor’s receipt of any addendum will result in the rejection of the offer if the addendum contained information which substantively changes the Owner’s requirements.

GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

Name of Contracting Entity: _______________________________________ Contract No. and Name: _______________________________________ Contract Date: _______________________________________

By executing this affidavit, the undersigned person or entity verifies its compliance with O.C.G.A. § 13‐ 10‐91, stating affirmatively that the individual, firm, or corporation which is contracting with the City of Commerce has registered with, is authorized to participate in, and is authorized to use and uses the federal work authorization program commonly known as E‐Verify, or any subsequent replacement program*, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13‐10‐ 91.

The undersigned person or entity further agrees that it will continue to use the federal work authorization program throughout the contract period, and it will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the undersigned with the information required by O.C.GA. § 13‐10‐91(b).

The undersigned person or entity further agrees to maintain records of such compliance and provide a copy of each such verification to the City of Commerce at the time the subcontractor(s) is retained to perform such service.

EEV / E‐Verify User Identification Number Date of Authorization

BY: Authorized Officer or Agent Date (Name of Person or Entity)

Title of Authorized Officer or Agent

Printed Name of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME ON THIS THE

_____ DAY OF ______________________, 20__

________________________________________ [NOTARY SEAL]

Notary Public

My Commission Expires: ___________________

* or any subsequent replacement operated by the United States Department of Homeland Security or any equivalent federal work authorization program operated by the United States Department of Homeland Security to verify information of newly hired employees, pursuant to the Immigration Reform and Control Act of 1986 (IRCA), P.L. 99‐603

CITY OF COMMERCE, GEORGIA
REQUEST FOR QUALIFICATION
FOR
2024 LMIG Street Paving
1.17.1 One (1) fully executable electronic copy of the response (in Word or .pdf format) and any Technical Requirements (in Excel format).
1.17.2 Two (2) paper versions of the bid. The original shall be clearly marked “original”.
1.17.3 The proposals shall be prepared with a straightforward, concise delineation of the vendor’s capabilities to satisfy the requirements of this RFP.
SECTION II - GENERAL CONDITIONS
2.0 PURPOSE
4.0 PROPOSAL FORMAT