RFP 2017 - 04 Outsourcing Res Net Wired and Wireless Addendum VIII 01.09.17.pdf

PDF 14 KB Posted

Attached to
RFP 2017-04 Outsourcing Res-Net-Wired and Wireless
Solicitation number
BD-17-1103-1103C-SSU-11212
Issued by
Essex County, Massachusetts

About this file

This document is an addendum to Salem State University's RFP 2017-04 for outsourcing the university's ResNet - wired and wireless network. The addendum consists of questions submitted by vendors after a site visit, as well as additional drawings requested during the visit. The questions cover topics such as providing approximate building dimensions and scale, availability of dark fiber, and the status of outside plant information. The RFP is seeking an outsourced solution to equip and manage the university's existing student housing network.

The RFP is being issued by Salem State University, located in Massachusetts. No additional details on pricing, set-asides, incumbents, funding requirements, or other salient information are provided in this addendum document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Salem State University RFP 2017-04 Outsourcing ResNet- Wired and Wireless Addendum VIII: Post Onsite Walk-through Questions Date: January 9, 2017

1. Overview

This addendum consists of questions that have been submitted to Salem State University after the vendor site visit and additional drawings that were requested during the vendor site visit.

2. Questions

- Q: Can you provide the approximate scale of the floor plan or dimensions for the buildings?

o A: This information has been requested, will provide as soon as possible.

- Q: Can we expect to receive the Outside Plant information soon as well?

o A: Provided on 1/6/17.

- Q: During the site visit it was noted that dark fiber is available at two locations from a specific provider. Could you document that information for us please?

o A: LightTower (our current ISP) has dark fiber available in Building 1 (Bertolon School of Business); and is currently working to install in the Auditorium (will be available by Spring 2017).