This document is a Request for Proposals (RFP) for the Durango Air Tanker Base HVAC Repairs project. The U.S. Forest Service is seeking a contractor to provide all materials, labor, equipment, and expertise necessary to complete this project, which has an estimated value between $15,000 to $30,000. The work includes replacing two furnace units, one condensing unit, and electronic filter systems, as well as implementing system repairs to allow for designated temperature control in each room or area. The project also includes an optional line item for replacing two unit heaters and an AC/heating unit in the warehouse. The period of performance is 60 days after the notice to proceed, with a site visit scheduled for August 14, 2024 and proposal due date of September 1, 2024. This procurement is a total small business set-aside.

View the file

Other files

File Type Posted
SF-30 - 1240LT24R0054 0003.pdf PDF
RFP 1240LT24R0054 - Amended Version.pdf PDF
SF30 1240LT24R0054 0002.pdf PDF
1240LT24R0054 P0001.pdf PDF
J1 - SOW.pdf PDF
J4 - Contractor Experience Questionaire.docx DOCX document
J2 - Wage Determination.pdf PDF
J5 - Contractor Questions and Answers Template.doc DOC document
J3 - Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

E-MAIL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

U.S Forest Service (USDA) CSA Intermountain 8 324 25Tth St Ogden, UT 84401-2310

40LT

U.S. Forest Service (USDA)

Attn: Elizabeth Ratcliff elizabeth.ratcliff@usda.gov

a. NAME

Elizabeth Ratcliff

b. E-MAIL:

elizabeth.ratcliff@usda.gov

1x 08/14/2024

1240LT24R0054

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Project Title: Durango Air Tanker Base HVAC Repairs The contractor shall provide all materials, labor, equipment, tools, transportation, supervision, expertise, and other incidentals necessary, except as otherwise provided, to successfully complete this project.

Set Aside: Total Small Business Set-Aside (FAR 19.5) Magnitude: Between $15,000 to $30,000 Location: 240 Co Rd 309A, Ignacio, CO, 81303 37.163184°, -107.747169° Period of Performance: 10/7/2024 to 12/6/2024 (60 Days After NTP) Site Visit/Pre-Bid Meeting: 8/14/2024 10:00 AM to 12:00 PM MDT Contractor Questions Due No Later Than: 8/27/2024 12:00 PM MDT Use document titled

"Contractor Questions and Answers Template" to write down your questions and send it to elizabeth.ratcliff@usda.gov before 8/27/2024 12:00 PM MDT.

Request for Proposal Solicitation Close Date: 9/1/2024 12:00 PM MDT Instructions to Bidders: See Section L.

Evaluation/Award Factors: See Sections L&M.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

60 60 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

09/01/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ _____________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

1 12:00 PM MDT

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. E-MAIL ADDRESS/TELEPHONE NO. (Include area code)

16. POINT OF CONTACT (POC) NAME, ADDRESS, EMAIL & TELEPHONE No.:

CODE FACILITY CODE

TOTAL

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

OFFER (Must be fully completed by offeror)

19. ACKNOWLEDGEMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

U.S Forest Service (USDA) CSA Intermountain 8 324 25Tth St Ogden, UT 84401-2310

40LT

31a. NAME OF CONTRACTING OFFICER (Type or print)

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Invoice Processing Platform (IPP) All Invoices Must Be Submitted Electronically Through The Invoice Processing Platform (IPP) Website: www.ipp.gov

SAM UEID NO.: _________________

SAM REGISTRATION EXPIRATION DATE: ________________

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 48

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1240LT24R0054

0001 1 LS

0002 1 LS

1001 1 LS

Mobilization

Office HVAC System Repairs

Warehouse Unit Heater & AC/Heating Replacement

(Option Line Item)

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 1240LT24R0054 Project Name: Durango Air Tanker Base HVAC Repairs

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

Item/Sub Number Description Quantity Unit of

Issue Unit Price Total Item Amount

Base Bid Line Items:

0001 Mobilization 1 LS 0002 Office HVAC System Repairs 1 LS Optional Bid Line Items:

1001 Warehouse Unit Heater Replacement (Subject to Availability of Funds) 1 LS

Grand Total:

B.2 SCHEDULE NOTES

a) Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.

b) One award will be made from this solicitation, contractors must submit pricing for all items.

c) All bond costs shall be included in mobilization costs.

FILL OUT COMPLETE PRICING

INFORMATION BEFORE SUBMITTING BID

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

ElizabethRatcliff Highlight

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK GENERAL

SPECIFICATIONS

DURANGO AIR TANKER BASE HVAC REPAIRS

SCOPE OF WORK:

This project base bid item includes replacing two high efficiency furnace units, one 4-ton condensing unit, electronic filter systems, and to propose and implement system repairs so that each room or a designated area can have a designated set temperature. The system will be modified to fit the needs of the current building users and optimized to be efficient in doing so.

This project optional bid item includes replacing two-unit heaters in the warehouse and replacing the warehouse office AC/Heating unit in kind or approved equivalent. All old warehouse units shall be left in working condition and on site for the government.

BACKGROUND:

The Durango Air Tanker Base has had issues arise with parts of a complicated HVAC system. The two gas powered furnaces have mostly failed as well as issues have begun with one of the older condensing units. This has resulted in temperature control devices being removed or rewired, dampers not working correctly, large zonal heating and cooling differences and general maintenance intervals being missed. The operations room located on the south-east corner of the building (05 in drawings) sees excessive heat due to large windows while the Heli-tack office (16 in drawings) sees fridged cold temperature due to minimal solar exposure.

Offices have minimal control of temperature and fluctuate wildly with the outside temperature. These problems need to be resolved to improve working conditions and temperature fluctuations on equipment. The warehouse has minimal issues with heating and cooling, but the units have begun to show signs of age and could be replaced.

CONTRACTOR REQUIREMENTS -

TECHNICAL REQUIREMENTS / TASKS:

The project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight, delivery, and all necessary valid licenses and permits required to complete work identified in this contract. This includes possessing a valid electrical license, and plumbing license in the state of Colorado.

The contractor is responsible to comply and provide documentation with the most current of the following codes during construction:

• International Building Code (IBC)

• International Fire Code (IFC)

• International Plumbing Code (IPC)

• International Mechanical Code (IMC)

• International Existing Building Code (IEBC)

• National Electrical Code (NEC)

The Contractor must follow all requirements set forth in the attached technical specifications (specs) and must work with CO/COR when questions arise regarding the drawings and specs.

GENERAL REQUIREMENTS:

1. The contractor shall field verify all dimensions and product information.

a. The dimensions provided by the government are only approximations and they are not responsible for their precision or accuracy. This includes but is not limited to blueprints, drawings, schedules, and statements of work.

2. All trash, waste, and construction debris generated shall be disposed of offsite.

3. Provide a one-year warranty for all labor and work contained herein.

a. Extended warranties and guarantees for equipment and products shall be passed along.

BASE BID LINE ITEMS – OFFICE HVAC SYSTEM REPAIRS

0001 Mobilization:

The Contractor is required to move personnel, equipment, material, and incidentals to the project before beginning work at the project site. All project staging locations on site for materials and equipment must be discussed and agreed upon.

0002 Office HVAC System Repairs

1. Remove and replace both condensing natural gas fired furnace units.

a. Units must be at a minimum equivalent to the same BTU/HR input and output and be able to provide enough heating for its designated Zones.

b. Dispose of old units offsite

2. Remove and replace older condensing unit.

a. Unit must match other existing 4 Ton Payne Model PA15NC04800GAAAA or approve equivalent.

b. Dispose of old unit offsite

3. Repair or replace any other failed system components.

4. Propose and implement system repairs so that each room or a designated area can have a designated set temperature.

a. Utilize existing duct work and motorized dampers to make changes to flow patterns or ventilation.

i. Changes can be made to ductwork if deemed necessary.

ii. Replacement of some dampers will be necessary.

b. This system must provide heating and cooling adequate to keep a consistent temperature range in each room or designated area.

i. Work with COR and Building Point of Contract to define heating and cooling zones.

c. Remove “comfort ventilator” panels to simplify system controls for building occupants.

d. Work with COR on modifications to the system to achieve the end goal of a functioning efficient low maintenance easy to operate HVAC system.

e. Test and balance the new system. Provide a TAB (Testing, Adjusting and Balancing) report to the

COR.

f. Provide training and system maintenance /instruction booklet on the new equipment to maintenance personnel.

i. See Submittals for more information on System Maintenance and Instructions

OPTIONAL BID ITEM – WAREHOUSE UNIT HEATER & AC/HEATING REPLACEMENT

1001 Warehouse Unit Heater Replacement:

1. Replace both Warehouse Reznor Unit Heaters with in-kind unit.

a. Units at a minimum must match BTH/HR output and input.

2. Replace one wall mounted AC/Heating unit in Office Space with in-kind unit.

a. Units at a minimum must match Tonnage and BTU/HR output and input.

3. Leave all three old units on site in current working condition for government.

SUBMITTALS/DELIVERABLES:

Prepare and submit Action Submittals required in the SOW in this contract, if applicable, and as indicated at the end of this subsection.

1. Collect information into a single submittal for each element of construction and type of product or equipment.

2. Mark up each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

b. Manufacturer's written recommendations.

c. Manufacturer's product specifications.

d. Manufacturer's installation instructions.

e. Manufacturer's catalog cuts.

f. Wiring diagrams showing factory-installed wiring.

g. Compliance with recognized trade association standards.

h. Compliance with recognized testing agency standards

Submittals/Deliverables Submittal No.

Deliverable Objective Due

1 Proposed Project Plan

Defining the responsibilities, timeline, risks, and milestones of contract objectives.

No later than fifteen (15) business days after contract award

2 Contractor Licensures

Provide all necessary licensures (electrical, plumbing, and general contractors license) to the COR.

No later than five (5) business days after contract award.

3 Warranty Items Provide the USFS with any warranty paperwork pertinent to products installed and work completed (Craftsmanship, Furnaces, Condensers, Dampers, and any other applicable warranty)

No later than five (5) business days after final walkthrough is complete.

4 System Maintenance and Instructions

Provide a written PDF document that contains the following items:

• System specifications (including model numbers, filter types, flow rates, etc.)

• Intervals for maintenance items across the system (i.e. filter changes, vent cleaning, recharges, etc.)

• Instructions for changing heat in each zone.

• Instructions for turn the system on and off.

No later than five (5) business days after final walkthrough is complete.

SITE INFORMATION AND EXECUTION -

SITE LOCATION:

From Durango, Colorado head south on Highway 160 for 8 miles. Turn right onto CO-172 S and continue for 5.7 miles. Turn right on Airport Road and continue for .8 miles. Turn right onto County Road 309A and continue for .2 miles until you turn right into the Durango Air Tanker Base. The location is 240 Co Rd 309A, Ignacio, CO, 81303 37.163184°, -107.747169°.

MAGNITUDE:

Between $15,000 to $30,000

SITE CONDITIONS:

The elevation of the site is approximately 6,500 feet above mean sea level. The construction site can experience heavy snowfall and cold temperatures in the winter.

UTILITIES:

Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. At Substantial Completion, restore these facilities to condition existing before initial use. The following are available for use by the contractor: water, electrical power services, and bathrooms. The following are not available: telephone service. The contractor is expected to provide whatever phone service is deemed necessary for the duration of the project.

STAGING AND STORAGE:

1. Coordinate on-site staging and storage requirements with the Center Point of Contact or the Contracting

Officer Representative (COR).

2. When government owned furniture, cabinets, or appliance must be moved they must remain indoors.

o Damaged to any government owed property that is not detailed in this contract will be replaced at the expense of the contractor.

3. It is the contractor’s responsibility to have all items safely stored and locked when staff are not on site.

CONSTRUCTION WASTE AND DISPOSAL FACILITIES:

1. Provide waste-collection in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.

BUILDING PROTECTION:

1. Dust containment systems must be in place to eliminate excess air pollution within the buildings.

2. Access to fire protection devices must be always clear and operational during the duration of the project.

o If fire detection system is not online or projection devices cannot be reached temporary systems must be set up (i.e., extra fire extinguishers, temporary smoke/CO alarms)

3. Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

o Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

o Facilities should be cleaned to the state that they were found in before final payment will be made.

4. Complete the following cleaning operations before requesting inspection for certification of Substantial

Completion for Project:

o Clean project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

o Remove tools, construction equipment, machinery, and surplus material from the project site.

o Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

SCHEDULING -

PRE-BID MEETING:

1. The Government is planning a pre-bid conference, during which potential offerors may obtain a better understanding of the work required. Offerors are encouraged to submit all questions in writing at least five

(5) days prior to the conference. Questions will be considered at any time prior to or during the conference;

however, offerors will be asked to confirm verbal questions in writing. After the conference, an amendment to the solicitation containing an abstract of the questions and answers, and a list of attendees, will be disseminated.

2. To facilitate conference preparations, it is requested that the person named on the Standard Form 33 of this solicitation be contacted and advised of the number of persons who will attend. The Government assumes no responsibility for any expense incurred by an offeror prior to contract award.

3. Offerors are cautioned that, notwithstanding any remarks or clarifications given at the conference, all terms and conditions of the solicitation remain unchanged unless they are changed by amendment to the solicitation.

If the answers to conference questions, or any solicitation amendment, create ambiguities, it is the responsibility of the offeror to seek clarification prior to submitting an offer.

LOCATION OF PRE-BID MEETING:

Date: 8/14/2024 Time: 10:00 AM to 12:00 PM MST Location: 240 Co Rd 309A, Ignacio, CO, 81303 37.163184°, -107.747169°

WORKING SCHEDULE:

1. Work hours for this project are between 8:00 AM-4:30 PM Monday through Sunday.

o Working outside these hours can occur only if approved by the COR beforehand and is determined to be project critical.

SECURITY REQUIREMENTS:

1. Durango Air Tanker Base is a secure government facility located next to a FAA controlled runway and will require coordination with local personnel to gain access to the building and site.

SITE PHOTOS:

Figure 1: Internal furnace model sheet

Figure 2: Indoor Section of air conditioner model sheet.

Figure 2: Indoor section of York cooling air conditioner model sheet.

Figure 3: Electronic filter system.

Figure 4: HVAC system control connections.

Figure 6: Comfort ventilator control panel.

Figure 7: 4 Ton Payne Model PA15NC04800GAAAA outdoor unit model sheet.

Figure 8: Right furnace ducting.

Figure 9: Right side heat recovery ventilator.

Figure 10: Left furnace ducting.

Figure 11: Left side heat recovery ventilator.

Figure 12: Mechanical room overview.

Figure 13: Attic above mechanical room left side.

Figure 14: Attic looking at above mechanical room left side.

Figure 15: Attic above mechanical room right side.

Figure 16: Attic above room 7

Figure 17: Damper on one of room vents

Figure 18: Warehouse south Reznor unit heater

Figure 19: Warehouse north Reznor unit heater

Figure 20: Warehouse office AC/Heating unit inside

Figure 21: Warehouse office AC/Heating unit outside

Project Name: Durango Air Tanker Base HVAC Repairs

SECTION D - PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E - INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12

52.246-13

Inspection of Construction (AUG 1996) Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)

SECTION F - DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 60 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 60 days after NTP. The time stated for completion shall include final cleanup of the premises.

Project Name: Durango Air Tanker Base HVAC Repairs

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held virtually on Microsoft Teams.

G.2 INVOICES & PAYMENTS

All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System.

https://www.ipp.gov/index.htm Register at: https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. These items must be uploaded as Attachments, and itemized invoices must include:

1. Name and address of the Contractor (include phone number, mailing address, person to notify if there are issues with the invoice).

2. Invoice date and invoice number;

3. Contract number;

4. Taxpayer Identification number;

5. Description, unit, and price of items being invoiced, Date of services or completion;

6. Shipping and Payment Terms

Certified payrolls for Construction: Contractor and all subcontractors. Final Payment - Following completion and acceptance of the work (including return of Government-furnished property and site cleanup), Final payment will made within 30 calendar days after presentation of a properly executed invoice. Final payrolls shall be marked “Final”. Contractor Notification & Release of Claims (FS-6300-16) for Final Payment. A contractor notification and release of all claims form shall be completed by the COR and the contractor. The completed form shall be uploaded as an attachment with the Final Payment.

https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.228-71 Insurance Coverage (NOV 1996) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(End of Clause)

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Project Foreman.

(b) During the first ninety (60) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 60-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.

Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

(End of Clause)

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses: https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023)

(Whistleblower Guidance to contractor employees) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-7 System for Award Management (OCT 2018) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-12 Unique Entity Identified Maintenance (OCT 2016) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by

Kaspersky Lab Covered Entities (DEC 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or

Equipment (NOV 2021) 52.204-27 Prohibition on a Byte Dance Covered Application (JUN 2023) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-13 Time Extensions (SEP 2000) 52.214-3 Amendments to Invitations for Bids (DEC 2016) 52.214-4 False Statements in Bids (APR 1984) 52.214-5 Submission of Bids (DEC 2016) 52.214-6 Explanation to Prospective Bidders (APR 1984) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (NOV 1999) 52.214-12 Preparation of Bids (APR 1984) 52.214-15 Period for Acceptance of Bids (APR 1984) 52.214-16 Minimum Bid Acceptance Period (APR 1984) 52.214-18 Preparation of Bids – Construction (APR 1984) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

52.214-21 Descriptive Literature (APR 2002) 52.214-34 Submission of Offers in the English Language (APR 1991) 52.214-35 Submission of Offers in U.S. Currency (APR 1991) 52.215-1 Instruction to Offerors – Competitive Acquisition (NOV 2021) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215- 8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.215-19 Notification of Ownership Changes (OCT 1997) 52.216-4 Economic Price Adjustment-Labor and Material (JAN 2017) 52.216-7 Allowable Cost and Payment (AUG 2018) 52.216-8 Fixed Fee – Construction (JUN 2011) 52.216-23 Execution and Commencement of Work (APR 1984) 52.217-3 Evaluation Exclusive of Options (Apr 1984) 52.217-4 Evaluation of Options Exercised at Time of Contract Award (JUN 1988) 52.217-5 Evaluation of Options (JUL 1990) 52.217-6 Option for Increased Quantity (MAR 1989) 52.219-1 Small Business Program Representations (Feb 2024) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (SEP 2023) 52.219-14 Limitations on Subcontracting (OCT 2022) ☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements - Price Adjustment (None or Separately Specified

Pricing Method) (AUG 2018) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN 2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service & Construction Contracts (SEP

2013) 52.223-3 Hazardous Material Identification and Material Safety Data (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001)

52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(AUG 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, & Improvements (APR

1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of

Improvements) (APR 2012) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-70 Additive or Deductive Items (FEB 1988) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.204-27 Prohibition on a Byte Dance Covered Application (JUN 2023)

(a) Definitions. As used in this clause— Covered application means the social networking service TikTok or any successor application or service developed or provided by Byte Dance Limited or an entity owned by Byte Dance Limited.

Information technology, as defined in 40 U.S.C. 11101(6)—

(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—

(i) Of that equipment; or

(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;

(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but

(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.

(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.

(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.

(End of Clause)

52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 15 days.

(End of Clause)

52.225-9 Buy American Act - Construction Materials (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and https://www.acquisition.gov/far/part-2#FAR_2_101

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.

Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if– (A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

https://www.acquisition.gov/far/part-25#FAR_25_105

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.