This is a Request for Information (RFI) issued by the 502D Air Base Wing, Joint Base San Antonio, Lackland AFB, for market research purposes to identify qualified contractors capable of supplying an Evapco AT212-2H9 cooling tower. The requirement is for one (1) two-cell induced draft cooling tower unit for delivery only to Joint Base San Antonio, Texas, with no labor for removal or installation included. Responses must be submitted in writing to TSgt Jermayne Gordon (jermayne.gordon@us.af.mil) no later than February 13, 2026, at 4:00 PM CST in MS Word or Adobe PDF format.
The cooling tower specifications are extensive and include requirements for 304 stainless steel upper panel construction and basins with factory-welded seams, two 7 HP inverter duty TEFC fan motors per cell with AEGIS shaft grounding rings, PVC drift eliminators with 0.001% drift loss, non-corrosive PVC spray distribution systems, PVC cross-fluted fill, stainless steel framed PVC air inlet louvers, 8-inch end inlet and outlet connections (BFW/Grooved), electric basin heaters with controls (5KW per cell), vibration cut-out switches, equalizer connections, an external service platform with vertical ladder and safety cage, and a five-year total product warranty. The unit dimensions are 12'4 7/8" W x 8'5" L x 11'4" H. Respondents should indicate if they are small businesses, identify any socio-economic concerns, confirm if they are Evapco authorized resellers, and provide delivery terms and pricing. This RFI is strictly voluntary market research and does not constitute a solicitation, quote request, or promise of future contract award. NAICS code 333415 applies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Salient Characteristics Evapco Cooling Tower.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
department of the air force
502D AiR BASE WING
JOINT BASE SAN ANTONIO
| TO: | 502D Contracting Squadron |
| 1655 Selfridge Ave. | |
| JBSA – Lackland AFB, TX 78236 |
| FROM: | Company Name_________________________________ |
| Address_______________________________________ | |
| Address _______________________________________ | |
| Phone No. _____________________________________ | |
| Email Address__________________________________ | |
| POC__________________________________________ | |
| Cage Code ____________________________________ | |
| Contract Number________________________________ |
SUBJECT: Brand name (Evapco) - Remove and Replace Evapco Cooling Tower, Model # AT212-2H9
1. The Government is only conducting market research and attaining information to identify contractors that are capable of providing all items/services listed below and the cost associated to acquire these specific items/services. NAICS code: 333415 - Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment Manufacturing. All information provided is STRICTLY VOLUNTARY.
2. Is your company a small business? ______________(Yes/ No)
3. If Small Business, please identify company’s socio-economic concern(s):______________________ (HUBZone, service-disable veteran-owned small bus., women-owned small bus., etc…)
4. Please provide delivery terms and price. See salient characteristics for Items required and services needed.
| Delivery Terms |
| Unt Price |
| Clin 1 |
| Equipment |
5. Is your company an Evapco authorized Reseller? ________________(Yes/No)
6. This request for information (RFI) is strictly voluntary and is not to be interpreted as a quote in anticipation of a future contract award.
7. Salient Characteristics: The Cooling Tower Brand: Evapco Model: AT212-2H9 two (2) Cell induced draft shall be an exact replacement counterflow cooling tower and a full-featured commercial-industrial product for the purpose of supporting a replacement for the current Cooling Tower. The Cooling Tower needs to have the following characteristics:
Evapco AT212-2H9 Two (2) Cells:
· All type 304 Stainless steel upper panel construction including mechanical support assembly and fan screen.
· All type 304 stainless steel basins with factory welded seams.
· One (1) – 7 ½ HP inverter duty TEFC fan motor per cell. Fan motors are located out of moist air stream. Each motor is equipped with a factory installed AEGIS shaft grounding ring.
· PVC drift eliminators with drift loss of .001% of recirculating water rate.
· Non-corrosive SCH 40 PVC Spray Distribution System with non-clog nozzles.
· PVC cross-fluted fill, totally enclosed and protected bottom supported.
· PVC air inlet louvers, with stainless steel frames, ¾ openings to prevent trash and debris from entering the cold-water basins
· End inlet connection, BFW/Grooved, 8”
· End outlet connection, BFW/Grooved, 8”
· Vibration cut out switch per motor, factory mounted for field wiring by others
· Electric basin heater with LWCO & TSTAT (5Kw per cell)
· Equalizer connections per cell, BFW/Grooved
· External Service Platform with Vertical Ladder/Safety Cage for ease of service. Platform and ladder are shipped loose for field installation by others. Platform provides access to all drive components including fan motor.
· Five Year Total Product Warranty including Fan Motor
· Dimensions – 12’ 4 7/8” W x 8’ 5 ½” L x 11’ 4 ¼” H
7. All questions and responses to this sources sought/market research must be submitted in writing to TSgt Jermayne Gordon (jermayne.gordon@us.af.mil). Responses shall be submitted in MS Word or Adobe PDF format not later than 13 February 2026, 4:00 pm CST.
8. Respondent will not be notified of the results of the information. However, the Contracting Officer will utilize the information for technical and acquisition planning. All proprietary information not to be disseminated in Government documents must be clearly identified. Since this is a sources sought announcement only, no evaluation letters and/or results will be issued to the participants. This market survey is issued to determine the applicable planning and acquisition strategy based on responses indicating capability in responding to this requirement.
FA301620U0019
image1.png image2.jpg image20.jpg
File details come from the government source that posted it. Updated .