RFI-2 Responses.pdf
PDF 697 KB Posted
- Attached to
- Virgin Islands Renewable Energy Systems Federal contract opportunity
- Solicitation number
- W50S93-20-B-5002-0004
About this file
This document contains responses to a Request for Information and details for a related federal contract opportunity. The Request for Information responses provide replacement specifications for solar panels, inverters, and roofing materials due to certain original products no longer being available. The responses also clarify that conduit runs and directional boring will be determined on-site, and that roof life cycles will not impact the proposed solar system. The related federal contract opportunity is to install renewable energy systems on Virgin Islands buildings. It specifies the solicitation and contract numbers, describes the scope as installing solar photovoltaic and battery storage systems, provides proposal submission instructions, and names the Department of the Army Michigan Army National Guard as the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI-4 Responses.pdf | ||
| ADDENDUM 001 USVI Energy Project (004).pdf | ||
| RFI-3 Responses.pdf | ||
| W50S93-20-B-5002-0004.pdf | ||
| RFI-1 Responses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. W50S93-20-B-5002
PROJECT TITLE/LOCATION: Virgin Islands Construct Renewable Energy Systems
REQUEST FOR INFORMATION FORM
Question No.
Date Received
REFERENCE
QUESTION GOVERNMENT RESPONSE
Page Section Para.
1 Sunmodule by Solarworld is no longer available. See attachment for Q-cell specs
2 Polaris wind turbine is no longer available, working on specs for replacement
3 Building 110 need spec sheets for standing seam roof to match up S-5 clamp
4 Building 100 and 107 what type of roof membrane, manufacturer, warranty, and age of roof
5 Enphase inverters are single phase 120/240, PV system is tying in to a 3 phase 120/208
6 Who is responsible for determining location of underground conduit runs
Can we use directional boring for underground wire runs?
Solar system will be on roof for 25yrs and roofs may have to be replaced if they are near the end of their life cycle?
Offeror can recommend a similar or equivalent solar system.
PV coponents including panels and inverters must meet the Buy America Act
The wind turbine is no longer part of this project.
The conduit runs should follow the drawings. However, exact locations will be determined by Contractor and COR/ BCE on-site
Directional boring can be used, once the specifications are met.
The current life cycle of the roof is not to be considered by the contractor.
Propose inverters that will work with current electrical system.
Building 100 and 107 are both concrete roofs
Spec sheets for standing seem roof are unavailable.