RFI-1 Responses.pdf
PDF 48 KB Posted
- Attached to
- Virgin Islands Renewable Energy Systems Federal contract opportunity
- Solicitation number
- W50S93-20-B-5002-0004
About this file
This document contains responses to requests for information (RFI) related to a federal contract opportunity for renewable energy systems in the Virgin Islands. The RFI responses clarify that no roof penetrations will be allowed and offerors can propose similar solar panel and microinverter brands that meet specifications and legal requirements. Additionally, the selected contractor will have access to existing underground utility drawings.
The related federal contract opportunity is issued by the Department of the Army Michigan Army National Guard to install solar renewable energy systems in the Virgin Islands. Offerors are to submit bids by mail or in person by the specified due date. The solicitation has been amended to remove a 20kW wind turbine requirement from the statement of work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI-3 Responses.pdf | ||
| W50S93-20-B-5002-0004.pdf | ||
| RFI-4 Responses.pdf | ||
| ADDENDUM 001 USVI Energy Project (004).pdf | ||
| RFI-2 Responses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.REGARDING CONCRETE ROOFTOPS WILL IT BE ALLOWED TO MAKE PENETRATIONS OR
ARE WE ONLY SUPPOSED TO USED BALLASTED RACKING SYSTEM?
Contractor will NOT be allowed to make penetrations in the roof.
2. AS PER PROVIDED DRAWINGS, THEY ARE USING "SUNMODULE" SOLAR PANELS
WHICH ARE NOT AVAILABLE. CAN WE PROPOSE OTHER BRAND THAT COMPLIES WITH
SPECIFICATIONS AND BAA ACT?
YES, Offerors can propose similar brands that complies with specifications and BAA Act.
3. AS PER DRAWINGS THEY ARE USING AN OLDER VERSION OF MICRO-INVERTERS. CAN
WE UPGRADE TO THE ENPHASE IQ7?
Yes, offerors can upgrade to newer versions.
4.CAN WE OBTAIN ACCESS TO EXISTING UNDERGROUND UTILITY DRAWINGS?
The contractor that is selected will have access to existing underground utility drawings. F