This document is a Request for Bidding Interpretation (RFBI) related to Contract 23-203110, the Central Utility Plant Interconnect project for the Department of State Hospitals at the Metropolitan State Hospital in Norwalk, California. The project comprises labor, materials, and services for the demolition of an existing 66kV outdoor substation and 12kV switchgear, and the installation of new 5kV switchgear, utility metering, and equipment pads. The project has a duration of 909 calendar days. Prospective bidders are required to attend a mandatory pre-bid site tour on October 16, 2024. Bids are due by 2:00 PM on November 14, 2024, and will be publicly opened on November 15, 2024. The State's estimated cost for the project is $2,064,800.

The successful bidder will be required to furnish payment and performance bonds, each in the amount of 100 percent of the contract price. The project is subject to Disabled Veteran Business Enterprise (DVBE) participation requirements. Contractors must possess a valid C-10 or B license to bid on the project. Additionally, contractors must submit copies of Valid Certificate of Reported Compliance (CRC) for any fleet vehicles used in the completion of the work.

View the file

Other files

File Type Posted
RFBI_4.pdf PDF
13292_-_RFBI_2.pdf PDF
13292_-_Pre_Bid_Sign_In_Sheets.pdf PDF
RFBI_5.pdf PDF
13292_-_Bid_Package_R3.pdf PDF
13292_-_Approved_Drawings_with_Issue_Date_R3.pdf PDF
13292_-_Project_Manual_Book_I.R3.pdf PDF
Addendum_1.pdf PDF
13292_-_RFBI_1.pdf PDF
13292_-_Project_Manual_Book_II_R3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESDMSTR: REV. 6.3.2021 Appendix 00 21 00.1 Project Number: 000000000013292

REQUEST FOR BIDDING INTERPRETATION (RFBI)

(Email no later than November 1, 2024, 5:00 p.m.)

PMDB RFBI No.: _______________ Requestor RFBI No.: ___________ Request Date:

To: Jose Enriquez, Project Director From (Bidder):

Project Management and Development Branch Real Estate Services Division Phone: 916-597-8847 Contact: __________________________ Phone: ___________________________ Fax: _____________________________

Email: jose.enriquez@dgs.ca.gov Email: ___________________________

All RFBIs received prior to deadline identified above, and responses from the State will be published on http://www.caleprocure.ca.gov. Click on “Start Search.” In the event name field, enter the project number and click search. While viewing the Event Details, click on “View Event Package” to view RFBI responses.

Project No.: 000000000013292 Project Name: Central Utility Plant Interconnect DSH - Metropolitan Location: Metropolitan State Hospital in Norwalk, CA

Drawing Reference: ____________________ Project Manual Reference: ___________________________

Question:

Bidder’s Authorized Signature: ______________________________________________________ [ ] Check here if additional pages attached Page 1 of ____ mailto:name@dgs.ca.gov

10/29/2024 minco construction refaat mina

3108632199

3105167404 mina@mincoconstruction.com n/a

5.article 7 7-2-1 in 5 .article 7 duration of project is 909 days bonding company ask if they can issue performance and payment bond for two years extendable to 909 days when the two years expires

JoEnriqu Rectangle

JoEnriqu Text Box

JoEnriqu Line

JoEnriqu Text Box Responded By: Project Director I/DGS-RESD-PMDB

JoEnriqu Text Box Response:

JoEnriqu Text Box Title:

JoEnriqu Line

JoEnriqu Text Box Response date: November 04, 2024

JoEnriqu Line

JoEnriqu Text Box Signature:

JoEnriqu Line

JoEnriqu Text Box The bonds will need to be issued for the entire length and value of the contract, renewable bonds are not possible.

2024-11-04T12:11:36-0800
Jose Enriquez

File details come from the government source that posted it. Updated .