RFB950000-01 - Bid Addendum #1.pdf
PDF 2 MB Posted
- Solicitation number
- RFB950000-01
- Issued by
- Harrison County, Iowa
About this file
Bid Addendum #1 for RFB 950000-01 - MPCF Diesel Tank Replacement
This Addendum No. 1, issued May 29, 2026, by the State of Iowa Department of Administrative Services, modifies the original project documents for the replacement of four existing diesel tanks with one 20,000-gallon double-wall aboveground diesel storage tank at Mount Pleasant Correctional Facility. The addendum incorporates revised mechanical drawings (M300 and M500) that add a swing check valve to tank discharge and specify diesel fuel requirements per ASTM D975 Grade No. 2-D S15 ultra-low sulfur diesel with maximum B5 biodiesel content, fuel stabilizer packages suitable for 24-month storage, and sulfur content not exceeding 15 ppm. The updated bid schedule sequences work to utilize the existing tank for storage during construction and removes existing diesel tanks in two separate mobilization phases (south tanks July-August 2026 and north tanks January 2027). The contract summary has been updated to assign contractors responsibility for public and private utility locates. Bid submission deadline is Thursday, June 11, 2026 at 2:00 p.m. through the IMPACS Electronic Procurement System, with bid opening at 3:00 p.m. via video conference. The pre-bid meeting was held May 20, 2026, with construction operations anticipated to commence July 15, 2026 and substantial completion targeted for January 22, 2027, spanning approximately 230 days including preconstruction, permitting, procurement, and closeout phases.
Bid security equal to five percent of the total bid amount is required in the form of a bid bond, certified check, or cashier's check. The contract will be awarded to the lowest responsive and responsible bidder on the ConsensusDOCS 802 Form of Agreement, with successful contractors required to submit subcontractor and supplier lists within 48 hours of bid opening and obtain project-specific certificates of insurance and performance/payment bonds prior to execution. All construction workers must complete background checks and PREA training prior to site access. Work hour restrictions limit operations to 6:00 a.m. to 4:30 p.m., Monday through Friday, and the facility will remain occupied throughout construction requiring coordination with existing operations. The contractor is responsible for all temporary diesel tank provision (5,000 gallons), existing tank decommissioning, lead abatement work at connection points and generator room, SWPPP measures, soil stabilization and seeding, providing 2,000 gallons of diesel for testing, and all associated permits and inspections. No set-asides, disadvantaged enterprise restrictions, or incumbent contractors are identified. The project manual and all contract documents are available for download through IMPACS.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB950000-01 - Notice to Bidders.pdf | ||
| RFB950000-01 - Bid Form.pdf | ||
| RFB950000-01 - Drawings.pdf | ||
| RFB950000-01 - Project Manual (Reduced Size).pdf | ||
| Project Manual - Full Size.html | HTML file | |
| 1389791-event.pdf | ||
| MPCF Diesel Tanks Replacement & Spill Containment Drawings.html | HTML file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 1 for RFB 950000-01
Project Name: MPCF Water Main Replacement
RFB #: 950000-01
DAS Project #: 9500.00
Date: 5/29/2026
Bid Due: Thursday, June 11th, 2026 at 2:00 pm
Addendum No. 1 Items:
1. See KCL Engineering Addendum #1 dated 5/29/2026
a. Drawing M300 – MECHANICAL SCHEMATIC
i. ADD Swing Check Valve to Tank Discharge per the Drawing
b. Drawing M500 – MECHANCIAL SCHEDUEL TANK BID DOCUMENTS
i. Add diesel requirements per the Drawing
2. See updated Bid Schedule replacing specification section 00 3113R.1 Preliminary Schedule
Example
a. Updated to sequence using the existing tank for required storage needs, and removing the diesel tanks in two separate mobilizations
3. See updated specification section 01 1200R – Contract Summary
a. Updated to include contractor responsibility for public and private locates
4. See attached Meeting Minutes & Sign-in Sheet from May 20th Pre-Bid Meeting.
END OF ADDENDUM
State of Iowa – Department of Administrative Services
DOC MPCF Diesel Tanks Replacement and Spill Containment RFP950000-01
Addendum #1
May 29, 2026
This addendum is issued to modify, clarify, or amend the original Project Drawings and Specifications and is hereby made part of the Contract Documents. The Contractor shall be responsible for incorporating items in this Addendum to the Work. The following shall take precedence over anything to the contrary in the Drawings or Specifications.
Mechanical Drawings:
1. Drawing M300 – MECHANICAL SCHEMATIC – REV 1:
a. ADD Swing Check Valve to tank discharge per the drawing.
b. Reissue drawing in full
c. Refer to attached full size sheet M300.
2. Drawing M500 – MECHANICAL SCHEDULES TANK BID DOCUMENTS – REV 1:
a. ADD diesel requirements per the drawing.
b. Reissue drawing in full
c. Refer to attached full size sheet M500.
End of Mechanical Addendum.
TANK 1 TANK 2 TANK 3 TANK 4
PLANT HEADER
PLANT HEADER WALL
NEW DIESEL
TANK 1
LDA
LSH
LSHH
90%
95%
INTERSTITIAL
LEAK DETECTION
LT
FILL CONNECTION
VTAVTA
NORMAL VENT
EMERGENCY VENT
AUTOMATIC SHUTOFF VALVE
SWING CHECK
VALVE
SUPPLY
RETURN
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/2
/2
:3 :1
P
M
M300
09/02/21
26027
D O
C M
P C
F D
IE
S
E L
T A
N K
S R
E P
L A
C E
M E
N T
S
P
IL
L C
O N
T A
IN
M
E N
T M
T
P L E
A S
A N
T C
O R
R E
C T
IO
N
A L
F A
C
IL
IT
Y
MECHANICAL
SCHEMATIC
N.T.S.
DEMO SCHEMATIC
N.T.S.
NEW PIPING SCHEMATIC
# Revision Date
100% CD 04/27/2026
1 ADDENUDM 1 05/27/2026
NOTES:
1. SWING CHECK VALVE:
A. BODY: BRONZE
B. SEAT RING: BRASS
C. DISC VITON
D. CAP: BRONZE
E. FULL BORE VALVE
F. MANUFACTURER: OPW SWING CHECK VALVE MODEL 175
OR EQUIVALENT
100% CD 04/27/2026
0 100%CD 04/29/26
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/2
/2
:1 :2
P
M
M500
09/02/21
26027
D O
C M
P C
F D
IE
S
E L
T A
N K
S R
E P
L A
C E
M E
N T
S
P
IL
L C
O N
T A
IN
M
E N
T M
T
P L E
A S
A N
T C
O R
R E
C T
IO
N
A L
F A
C
IL
IT
Y
MECHANICAL
SCHEDULES TANK BID
DOCUMENTS
NOTES:
1. ALL THREADED PIPE SHALL BE SEAMLESS (TYPE S)
2. BRONZE BODY VALVES MAY BE USED FOR PIPE SIZES 1/4" - 2" IN LIEU OF SOCKET WELDED VALVES.
3. NO BACKING RING
VALVE SELECTION
BONNEY FORGE OR
EQUIVALENT
APOLLO OR EQUIVALENT JAMESBURY OR EQUAL
CONSTRUCTION
BODY: A106B
API TRIM 8
BALL VALVE
CONNECTION AND RATING
CLASS 800 SOCKETWELDED ENDS CLASS 150 FLANGED ENDS
PIPE SIZE (NPS) 2" AND SMALLER 2 1/2" AND LARGER
NG1
CARBON STEEL SEE RATING BELOW ASME B31.1 ASME B16.34
VALVE SPECIFICATION: SPECIFICATION MATERIAL:
PRESSURE CLASS: DESIGN CODE:
CARBON STEEL ASME B16.34 ASME B31.1 1 9/23/2025
PIPE MATERIAL: DESIGN/CONSTRUCTION CODE: REVISION: DATE REVISED:
THERMOWELLS: MATERIAL INSERTION THERMOWELLS - ASTM A105 - 3000 PSIG PRESSURE CLASS - SEAL WELDED WELLS
MATERIAL FLEXITALLIC STYLE CGI - TYPE 304 STAINLESS - FLEXICARB FILLER
GASKETS:
CONSTRUCTION SPIRAL WOUND - SUITABLE FOR RAISED-FACE OR FLAT-FACE FLANGES
WASHER: CONSTRUCTION F436
FLANGE NUTS: CONSTRUCTION HEAVY HEX - A194 GRADE 2H
FLANGE BOLTS:
CONSTRUCTION
ALLOY STEEL, AISI 4140/4142 QUENCHED AND TEMPERED, A193 GRADE B7, STUD - FULL LENGTH
MATERIAL FORGED CARBON STEEL - ASTM A105
WALL THICKNESS SAME AS ADJOINING PIPEFLANGES:
CONSTRUCTION CLASS 150 - WELD NECK - ASME B16.5
MATERIAL FORGED CARBON STEEL - ASTM A105 --
WALL THICKNESS SAME AS ADJOINING PIPE --
UNIONS:
CONSTRUCTION
CLASS 3000 - B16.11 - FLAT FACE WITH SPIRAL WOUND GASKET
DESIGN NOT PERMITTED
OTHER WHERE FLANGE REQUIRED WHERE FLANGE REQUIRED
PIPING JOINTS:
TYPE SOCKET WELDED (5) BUTTWELD - END PREP PER B16.25
MATERIAL SOCKET WELDED FITTING - ASTM A105 - SEAMLESS BUTTWELD FITTING - ASTM A234 GRADE B -...
WALL THICKNESS SAME AS ADJOINING PIPE SAME AS ADJOINING PIPEFITTINGS:
CONSTRUCTION CLASS 3000 - SOCKETWELD - B16.11 BUTTWELD - ASME B16.9 (3)
PIPE PIPE SIZE (NPS) 2" AND SMALLER 2 1/2" AND LARGER
ASME B36.10M MATERIAL ASTM A53 GRADE B, SEAMLESS
PIPE: WEIGHT/SCHEDULE XS SCH 40
PIPE SIZE (NPS) 2" AND SMALLER 2 1/2" AND LARGER
NG1 NATURAL GAS (150PSIG OR LESS) 150 PSIG AT 150°F
PIPING SPECIFICATION PROCESS: DESIGN CONDITIONS:
Location Outdoor installation
Installation Code NFPA 30 and adopted IFC
Listing UL 142 listed and labeled
Construction Double-wall steel
Capacity (Nominal) 20,000 gallons (Inside diameter of tank @ 10' dia x 34' long)
Tank Type Aboveground, Horizontal, Cylindrical
Application Backup fuel for central steam plant
Qty 1
Service No. 2 Diesel Fuel (Class II Combustible)
Item Specification / Requirement
General Information
Anchorage Provide anchor bolt reactions and recommendations
Foundation Loads Vendor to provide empty and full weights
Wind/Seismic Design ASCE 7 (Mt. Pleasant, Iowa)
Outer Tank Material Carbon steel secondary containment shell
Inner Tank Material ASTM A36 or ASTM A516 carbon steel
Corrosion Allowance Minimum 1/16 inch
Specific Gravity 0.85 (diesel typical)
Design Temperature -20°F to 120°F
Design Pressure Atmospheric
Item Specification / Requirement
Design Criteria
Grounding Lugs 2 required
Ladder and Platform See specification for requirements for integral ladder and platform
Painting and Coating Painting and Coating shall be to manufacturer's standard
Interstitial Leak Detection Continuous monitoring with alarm
High-High Shutdown 95% automatic fill shutdown device
High Level Alarm 90% capacity (local + remote alarm)
Level Transmitter 4–20 mA or Modbus output to DCS/BMS
Level Gauge Direct-reading, visible to delivery operator
Manway Minimum 24-inch diameter, top center of tank, provide a ladder into the tank
Drain Valved and capped; controlled discharge only
Return Inlet Sized per fuel demand (120 gpm); anti-siphon protection required
Supply Outlet Sized per fuel demand (120 gpm); anti-siphon protection required
Emergency Vent Sized per NFPA 30 and UL 142 listing
Normal Vent Sized per NFPA 30 and UL 142 listing
Fill Connection Lockable cap; size by vendor; spill containment provided
Item Specification / Requirement
Nozzles & Appurtenances
Labeling Diesel Fuel – Combustible; No Smoking signage
API 650 Alignment Vendor to state alignment with applicable API 650 provisions where not in conflict with UL 142
Secondary Containment Integral double wall; interstitial monitoring required
SPCC Applicability Evaluate per EPA 40 CFR 112
NEC Compliance Electrical classification per NFPA 70
NFPA 30 Compliance Overfill protection, venting, and installation per NFPA 30
UL Listing UL 142 certification required
Item Specification / Requirement
Codes & Regulatory Compliance
Inspection/Test Procedures Factory test documentation
Ladder and Platform Connection and Layout Details
Coating System Data Exterior coating and painting specifications
Foundation Load Data Empty and full tank weights
Overfill Protection Cut Sheet Alarm and shutoff documentation
Leak Detection Cut Sheet Manufacturer data and alarm details
Vent Sizing Documentation Normal and emergency vent basis
General Arrangement Drawing Dimensions, nozzle schedule, elevations
UL 142 Documentation Provide certificate and nameplate photo
Item Specification / Requirement
Required Vendor Submittals
DIESEL TANK SPECIFICATIONS
# Revision Date
100% CD 04/27/2026
Date: 04/29/26
# Revision Date
0 100%CD 04/29/26
DIESEL REQUIREMENTS:
1. FUEL OIL: ASTM D975 GRADE NO. 2-D S15 ULTRA-LOW SULFUR DIESEL FUEL.
2. MAXIMUM B5 BIODIESEL
3. FUEL STABILIZER PACKAGE INCLUDED
4. FUEL SHALL BE SUITABLE FOR STORAGE PERIODS UP TO 24 MONTHS AND
INCLUDE CORROSION INHIBITORS, ANTI-OXIDANT PACKAGE AND COLD-FLOW
IMPROVERS.
5. SULFUR CONTENT: LESS THAN OR EQUAL TO 15 PPM
6. FUEL SHALL BE FREE OF WATER, SEDIMENT, AND CONTAMINENTS.
7. FUEL SHALL COMPLY WITH ALL FEDERAL, STATE, AND LOCAL REGULATIONS.
100% CD 04/27/2026
1 ADDENUDM 1 05/27/2026
Activity Name Original
Duration
Start Finish
9500.00 MPCF Diesel Tank Replacement - Bid Schedule - Addendum #1 230 28-Apr-26 26-Mar-27
Preconstruction 54 28-Apr-26 14-Jul-26
McGough Receive 100% CD Set 1 28-Apr-26* 28-Apr-26
McGough Compile Front-End Specs 5 29-Apr-26 05-May-26
McGough Issue Final Docs to Procurement 2 06-May-26 07-May-26
Project Goes Live 1 08-May-26 08-May-26
Bidding 23 11-May-26 11-Jun-26
Pre-Bid Meeting 1 20-May-26 20-May-26
McGough Issue Addendum 01 1 26-May-26 26-May-26
Bids Due 0 11-Jun-26
Issue NOI to Award 5 12-Jun-26 18-Jun-26
802 Contract Execution 10 16-Jun-26 29-Jun-26
Contractor Kickoff Meeting 1 19-Jun-26 19-Jun-26
Permitting 10 30-Jun-26 14-Jul-26
Procurement 115 30-Jun-26 11-Dec-26
Submit / Review / Approve Submittals 20 30-Jun-26 28-Jul-26
Procure Diesel Tank 95 29-Jul-26 11-Dec-26
Procure Misc. Pipe Specialties 5 29-Jul-26 04-Aug-26
Procure Piping 15 29-Jul-26 18-Aug-26
Construction 136 15-Jul-26 29-Jan-27
Mobilization 2 15-Jul-26 16-Jul-26
Decommissioning & Demolition - Phase 1 (Two South Tanks) 15 17-Jul-26 06-Aug-26
Install SWPPP Measures 2 17-Jul-26 20-Jul-26
Isolate / Lockout Existing Tanks 2 17-Jul-26 20-Jul-26
Clean Existing Tanks 5 21-Jul-26 27-Jul-26
Lead Abatement 2 28-Jul-26 29-Jul-26
Remove Existing Diesel Tanks From Site 2 30-Jul-26 31-Jul-26
Remove Concrete Supports & Foundations 2 03-Aug-26 04-Aug-26
Site Inspection (Environmental Sampling) 2 05-Aug-26 06-Aug-26
Foundation 28 07-Aug-26 16-Sep-26
Survey / Site Grading / Foundation Excavation / Haul of Spoils 5 07-Aug-26 13-Aug-26
Subgrade Inspection 1 14-Aug-26 14-Aug-26
Spread Footings 2 17-Aug-26 18-Aug-26
Foundation Walls / Anchor Bolt Verification 3 19-Aug-26 21-Aug-26
Backfill 2 24-Aug-26 25-Aug-26
Cure Time 15 26-Aug-26 16-Sep-26
Tank / Piping / Structure 16 14-Dec-26 08-Jan-27
Set Tank 1 14-Dec-26 14-Dec-26
Install Access Platform 1 15-Dec-26 15-Dec-26
Install Control Panel & Provide Power From Generator Room to Control Panel 5 15-Dec-26 21-Dec-26
Piping From Tanks to Existing Pump 5 16-Dec-26 22-Dec-26
Control Wiring From Control Panel to Tank & Associated Accessories 5 22-Dec-26 30-Dec-26
Pipe Pressure Testing / Flushing / Cleaning 2 23-Dec-26 28-Dec-26
Initial Partial Fill For Testing 1 29-Dec-26 29-Dec-26
Inspections & Approvals - System Pressure Test / Leak Detection Test / Overfill Protection Test / Alarm Verification 5 04-Jan-27 08-Jan-27
Decommissioning & Demolition - Phase 2 (Two North Tanks) 15 11-Jan-27 29-Jan-27
Isolate / Lockout Existing Tanks 2 11-Jan-27 12-Jan-27
Clean Existing Tanks 5 13-Jan-27 19-Jan-27
Lead Abatement 2 20-Jan-27 21-Jan-27
Remove Existing Diesel Tanks From Site 2 22-Jan-27 25-Jan-27
Remove Concrete Supports & Foundations 2 26-Jan-27 27-Jan-27
Site Inspection (Environmental Sampling) 2 28-Jan-27 29-Jan-27
Closeout 40 01-Feb-27 26-Mar-27
Punch List 5 01-Feb-27 05-Feb-27
Punch List Corrections 5 08-Feb-27 12-Feb-27
Substantial Completion 0 12-Feb-27
Contractor Submit Closeout Docuements 30 15-Feb-27 26-Mar-27
Final Completion 0 26-Mar-27
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027 2028 2029
9500.00 MPCF Diesel Tank Replacement - Bid Schedule - Addendum #1
Preconstruction
McGough Receive 100% CD Set
McGough Compile Front-End Specs
McGough Issue Final Docs to Procurement
Project Goes Live
Bidding
Pre-Bid Meeting
McGough Issue Addendum 01
Bids Due
Issue NOI to Award
802 Contract Execution
Contractor Kickoff Meeting
Permitting
Procurement
Submit / Review / Approve Submittals
Procure Diesel Tank
Procure Misc. Pipe Specialties
Procure Piping
Construction
Mobilization
Decommissioning & Demolition - Phase 1 (Two South Tanks)
Install SWPPP Measures
Isolate / Lockout Existing Tanks
Clean Existing Tanks
Lead Abatement
Remove Existing Diesel Tanks From Site
Remove Concrete Supports & Foundations
Site Inspection (Environmental Sampling)
Foundation
Survey / Site Grading / Foundation Excavation / Haul of Spoils
Subgrade Inspection
Spread Footings
Foundation Walls / Anchor Bolt Verification
Backfill
Cure Time
Tank / Piping / Structure
Set Tank
Install Access Platform
Install Control Panel & Provide Power From Generator Room to Control Panel
Piping From Tanks to Existing Pump
Control Wiring From Control Panel to Tank & Associated Accessories
Pipe Pressure Testing / Flushing / Cleaning
Initial Partial Fill For Testing
Inspections & Approvals - System Pressure Test / Leak Detection Test / Overfill Protection Test / Alarm Verification
Decommissioning & Demolition - Phase 2 (Two North Tanks)
Isolate / Lockout Existing Tanks
Clean Existing Tanks
Lead Abatement
Remove Existing Diesel Tanks From Site
Remove Concrete Supports & Foundations
Site Inspection (Environmental Sampling)
Closeout
Punch List
Punch List Corrections
Substantial Completion
Contractor Submit Closeout Docuements
Final Completion
9500.00 MPCF Diesel Tank Replacement - Bid Schedule - Addendum #1
PROJECT 9500.00 CONTRACT SUMMARY 01 1200 - 1
SECTION 01 1200
CONTRACT SUMMARY
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Project Information B. Project Summary C. Bid Scope Summary D. Work Hour Restrictions E. Access to Site F. Coordination with Occupants G. Rules for Construction Workers H. Bid Package Instructions
1.02 PROJECT INFORMATION
A. Facility Name/Location: Mount Pleasant Correctional Facility 1200 Grand Ave, Mt. Pleasant, Iowa 52641
B. DAS Project #: 9500.00 C. Owner: State of Iowa, Department of Administrative Services, Hoover State Office Building, Level 3, 1305 East Walnut Street, Des Moines, IA 50319 D. Owner’s Representative: Brandon Adams, Iowa Department of Administrative Services, 109 SE
13th Street, Des Moines, IA 50319 E. Construction Manager: Aaron Ledeboer, McGough, 217 E. 2nd Street, Suite 120, Des Moines, Iowa 50309
1.03 PROJECT SUMMARY
A. The project includes the replacement of four existing diesel tanks with one twenty-thousand-gallon above ground diesel tank.
B. Target date to provide substantial completion is January 2027
1.04 BID SCOPE SUMMARY
A. Scope Applicable to All Bid Packages:
1. The Contractor’s Work includes all labor, supervision, materials, equipment, services, supplies, tools, facilities, transportation, hoisting, storage, receiving, licenses, inspections, certifications, overhead, profit, or other items required or reasonably inferable to properly and timely perform and complete all work and services to be performed by the Contractor pursuant to this Agreement. Unless specifically stated otherwise, incidental work required to accomplish the work of this Bid Package shall be included the bid. This would include, but not be limited to, temporary facilities, protection of the work, security of equipment, materials, and work in progress, etc. Contractor’s Work shall be performed in accordance with the Drawings, Specification Divisions 00 and 01, and Specification sections applicable to each Contractor’s scope.
2. Contractor is responsible for all labor and equipment to unload, account for all material delivered, stock, and delivery for this scope of work. Storage and delivery of materials and equipment at the Site shall be permitted only to the extent approved in advance by the Construction Manager, and if anything so stored obstructs the progress of any portion of the work, it shall be promptly removed or relocated by the Contractor without reimbursement.
3. On site supervision by Prime Contractor at all times work by that contractor or their subcontractors/suppliers is taking place.
PROJECT 9500.00 CONTRACT SUMMARY 01 1200 - 2
4. Provide all temporary facilities required for this scope of work including trailer, trailer power, telephone, secured storage, temporary power for work, temporary and task lighting for work, etc. as determined necessary by Contractor. Coordinate location of trailers, material storage and utility lines with Construction Manager. Limited space is available, and permission to bring any such facility or excess materials on to the site shall be approved by the Construction Manager.
5. Contractor shall provide all equipment and tools for Contractor’s own cleanup. Clean up shall be done at end of every shift or more frequently if required for the Contractor to perform their work, for other Contractors to perform their work, as required by the Owner’s operations, and at the discretion of the Construction Manager.
6. All turf, landscaping, and subgrade disturbances caused by equipment traffic or other activities related to the Contractor’s scope shall be repaired or restored to proper conditions by the Contractor.
7. Protect adjacent existing building elements from damage from Scope of work. Repair existing building elements damaged during Contractor’s Scope of work.
1.05 WORK HOUR RESTRICTIONS
A. Work hours are from 06:00 AM to 04:30 PM, Monday through Friday unless arrangements are made in advance.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to areas noted on Drawings.
B. Provide access to and from site as required by law and Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permission of Owner and permit if required.
C. Facility will be occupied at all times during duration of work. Contractor personnel shall conduct themselves in an agreeable manner at all times. Failure to do so may result in removal from the work site.
1.07 OWNER OCCUPANCY
A. Owner intends to occupy the Project upon Substantial Completion.
B. Cooperate with Owner to minimize conflict and to facilitate Owner’s operations.
C. Schedule the Work to accommodate Owner occupancy.
1.08 RULES FOR CONSTRUCTION WORKERS
A. The staff of the State of Iowa has a responsibility to protect the public by providing a secure environment. All work site rules must be followed to the letter, at all times.
B. All construction workers must have a background check completed prior to entering the campus to perform work.
C. Hot Work Permit Processes and Fire Watch, when necessary, will be adhered to for this project.
D. All State properties are tobacco free. No smoking will be permitted or tolerated on campus unless in designated areas.
E. You are permitted access only to the work site and no other area of the institution.
F. No drugs, alcohol, or firearms are allowed on the work site.
G. Do not leave money, drugs, alcohol, or firearms in your personal vehicle.
H. Company and personal vehicles are to be parked and locked in designated or authorized area of the work.
I. Secure all tools at the end of the day.
J. Maintain control of all tools, supplies, and debris at all times during the work.
PROJECT 9500.00 CONTRACT SUMMARY 01 1200 - 3
K. Never leave keys in any vehicle. If a security officer finds keys in a vehicle, they are under orders to turn them in to a security supervisor.
L. Do not give anything to residents or take anything from residents; if they offer, inform your supervisor.
M. Secure all tools at the end of each day. Never leave tools unattended. All tools shall be checked in at the beginning of the day and checked out at the end of the day. If security officers find loose tools, they are under orders to turn them in to their supervisor.
N. All delivery vehicles must go directly to the job site. Extra time should be anticipated for all deliveries. Provide 24-hour notice to the facility of deliveries.
O. During an emergency, follow the instructions of the security staff.
P. Contractor shall wear clothing of a different color, pattern, fashion, etc. as to distinguish themselves from inmates.
1.09 BID PACKAGE INSTRUCTIONS
A. Bid Package #01 – Above Ground Diesel Tank Replacement: Trade Contractor shall include all of the following, but not limited to, as part of the contract:
1. All work on the contract documents and specifications complete; material and labor including all freight, unloading and installation for a complete scope.
2. All employees are subject to background checks and must pass the background checks in order to work on the premises.
3. All employees onsite will be required to attend PREA (Prison Rape Elimination Act) training and take the mandatory assessment following the training.
4. Demolition and removal of existing foundation extent is unknown. Any concrete deviations from the limits documented in the construction documents are to be documented and any excess time required due to unforeseen conditions are to be tracked on a time and material basis.
5. Contractor is responsible for filling out Iowa DIAL Aboveground Storage Tank Change of Information Form.
6. Contractor is responsible for providing a temporary 5,000 gallon diesel tank, protecting existing conditions where temporary tank is to be placed, temporary connections from the temporary tank to the existing facility connections, protecting the temporary diesel tank, and temporary connections throughout the construction process, and removing the existing diesel from the existing tanks into the temporary tank. Existing diesel is to be filtered before placing into the temporary tank. Contractor is responsible for all required permits, registration and inspections associated with the temporary diesel tank.
Temporary tank to be operational the same day existing tanks are decommissioned. The facility is required to be on generator power at all times.
7. Contractor is responsible for cleaning the inside of the existing diesel tanks prior to removal to salvage. Follow all applicable codes and guidelines for extent of cleaning diesel tanks. Contractor to follow all safety protocols required for a confined space
8. Contractor is to provide crane pick plans to Construction Manager a week prior to mobilization of cranes.
9. The Contractor shall retain a licensed abatement subcontractor or have trained certified employees to perform the required lead abatement work per Section 00 3126 – Existing Hazardous Material Information. The intent of the lead abatement is to be limited to the existing connection points of the diesel tanks to be able to pick the tanks whole to transport for scraping and disposal. Lead abatement is also required for getting power out of the existing generator room for the new control panel.
10. Transportation and removal of the existing diesel tanks are the responsibility of the contractor.
11. Contractor is responsible for all SWPPP measures as outlined in the contract documents.
12. Contractor is responsible for soil stabilization for soil not disturbed for more than 14 days.
13. Contractor is responsible for seeding all disturbed soil after completion of construction activities. Work may be required to be complete in the Spring of 2027.
PROJECT 9500.00 CONTRACT SUMMARY 01 1200 - 4
14. Contractor is responsible for coordinating specific tank requirements for anchors, and any other specific requirements that modify what is currently shown in the contract documents.
15. Contractor is responsible for providing 2,000 gallons of diesel for testing and inspection of tanks per the contract documents
16. Contractor is responsible for providing manufacture testing and inspection services as outlined in the contract documents.
17. Contractor is responsible for public and private locates coordinated with MPCF
PART 2 - PRODUCTS – NOT USED
PART 3 - EXECUTION – NOT USED
END OF SECTION
State of Iowa - Department of Administrative Services 109 SE 13th St.
Des Moines, Iowa 50319 P: (515) 281-7260
Project: 9500.00 DOC MPCF Spill Containment for Diesel Tanks
1200 East Washington St.
Mount Pleasant, Iowa 52641
RFB Pre-Bid Minutes: Meeting #1
Meeting Date May 20, 2026 Meeting Time 11:00 am - 12:00 pm Central Time (US & Canada)
Meeting Location Mount Pleasant Correctional Facility
Overview Meeting to allow prospective bidders to visit the site, when possible, and learn more about the project.
Notes
Attachments
Scheduled Attendees
Name Company Phone Number Email Attendance
Eric Heynen KCL Engineering P: (515) 724-7938 eheynen@kclengineering.com Present
Jacob Price KCL Engineering P: (563) 299-7722 jprice@kclengineering.com Present
Aaron Ledeboer McGough Construction aaron.ledeboer@mcgough.com Present
Jeremy Howk Mount Pleasant Correctional Facility
P: (319) 385-9511 jeremy.howk@iowa.gov Present
Tony Kempker Mount Pleasant Correctional Facility
P: (319) 385-9511 ext.
anthony.kempker@iowa.gov Absent
Brandon Adams State of Iowa - Department of Administrative Services brandon.adams@das.iowa.gov Present
Introduction
No. Mtg Origin Title Assignment Due Date Priority Status
1.1 1 Introductions Open
Description Attendees
Attachments MPCF Diesel Tank - Prebid Sign-in Sheet - 5.20.26.pdf
Official Documented Meeting Minutes
• See attached sign-in sheet
Project Overview
State of Iowa - Department of Administrative Services Page 1 of 5 Printed On: May 21, 2026 11:02 AM CDT
2.1 1 Project Description Open
Description Replacing (4) existing diesel tanks with (1) 20,000 gallon double walled diesel tank. Work includes removal of existing tanks and foundations. Contractor to provide 5,000 temporary diesel tank for facilities use during construction.
• Base bid o Demolition and removal of existing foundation extent is unknown. Any concrete deviations from the limits documented in the construction documents are to be documented and any excess time required due to unforeseen conditions are to be tracked on a time and material basis.
o Contractor is responsible for filling out Iowa DIAL Aboveground Storage Tank Change of Information Form.
o Contractor is responsible for providing a temporary 5,000 gallon diesel tank, protecting existing conditions where temporary tank is to be placed, temporary connections from the temporary tank to the existing facility connections, protecting the temporary diesel tank, and temporary connections throughout the construction process, and removing the existing diesel from the existing tanks into the temporary tank. Existing diesel is to be filtered before placing into the temporary tank. Contractor is responsible for all required permits, registration and inspections associated with the temporary diesel tank. Temporary tank to be operational the same day existing tanks are decommissioned. The facility is required to be on generator power at all times.
o Contractor is responsible for cleaning the inside of the existing diesel tanks prior to removal to salvage.
Follow all applicable codes and guidelines for extent of cleaning diesel tanks. Contractor to follow all safety protocols required for a confined space o Contractor is to provide crane pick plans to Construction Manager a week prior to mobilization of cranes.
o The Contractor shall retain a licensed abatement subcontractor or have trained certified employees to perform the required lead abatement work per Section 00 3126 – Existing Hazardous Material Information. The intent of the lead abatement is to be limited to the existing connection points of the diesel tanks to be able to pick the tanks whole to transport for scraping and disposal. Lead abatement is also required for getting power out of the existing generator room for the new control panel.
▪ Lead abatement is also required on the concrete foundations. Contractor to remove concrete foundations in a manor that does not put employees at risk of lead exposure.
o Transportation and removal of the existing diesel tanks are the responsibility of the contractor.
o Contractor is responsible for all SWPPP measures as outlined in the contract documents.
o Contractor is responsible for soil stabilization for soil not disturbed for more than 14 days.
o Contractor is responsible for seeding all disturbed soil after completion of construction activities. Work may be required to be complete in the Spring of 2027.
o Contractor is responsible for coordinating specific tank requirements for anchors, and any other specific requirements that modify what is currently shown in the contract documents.
o Contractor is responsible for providing 2,000 gallons of diesel for testing and inspection of tanks per the contract documents o Contractor is responsible for providing manufacture testing and inspection services as outlined in the contract documents.
• Alternates o No alternates
• Unit prices
Meeting #1 - RFB Pre-Bid Project: 9500.00 DOC MPCF Spill Containment for Diesel Tanks
State of Iowa - Department of Administrative Services Page 2 of 5 Printed On: May 21, 2026 11:02 AM CDT o No unit prices requested
Official Documented Meeting Minutes
• Additional consideration will be taken on keeping existing tank operational until new tank is operational. Addendum #1 will address sequence of this potential plan.
• Additional consideration will be taken with the facility on leaving the existing tank foundations below grade (just removing exposed stem walls). Addendum #1 will address this consideration.
• Any disposal of existing diesel to be the contractors responsibility
• Type of diesel to provide for testing and inspection to be addressed & clarified in Addendum #1
2.2 1 Project Schedule Open
Description
• Contract(s) Issued: 6/16 - 6/29
• Submittals: 6/30 - 7/28
• Construction: - 7/15 - 1/8/27
• Closeout: 30 days after substantial completion
A pull-plan session will be held with the successful bid package contractors to finalize the construction schedule.
State Holidays: New Year's Day, Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day, Thanksgiving and day after Thanksgiving, Christmas Day
2.3 1 Site Rules Open
Description
• Onsite supervision by Prime Contractor is required at all times when work by that contractor or their subcontractors/suppliers is taking place.
• Contractors shall provide daily logs for each day they are on site.
• Construction progress meeting will be established once construction starts.
• It is of the utmost importance to show respect and courtesy to all staff at all times.
• Clean all debris, materials, and bring all finishes back to existing conditions in the area they were working in prior to moving to the next area.
• No smoking, vaping or smokeless tobacco use onsite.
• Temporary facilities o Okay to use facilities inside of power house
• Demolished equipment
• Tool control
• Cell phones
• Background checks & PREA training
• Work hours: 6:00 am - 4:30 pm
• View Specification 01 1200 - Contract Summary for more information.
o Review for specific project requirements
RFB Overview
State of Iowa - Department of Administrative Services Page 3 of 5 Printed On: May 21, 2026 11:02 AM CDT
3.1 1 Bid Submission Open
Description
• Bids are due 6/11/26 at 2:00 pm
• The Bid shall be submitted to the Issuing Officer through the IMPACS Electronic Procurement System.
o Link and information is in the project manual o Contractors will need to register prior to bidding o Bidders will need to register regardless of whether it has already done business with the State of Iowa.
o Bidders should complete the registration process and ensure the ability to log in as soon as possible to ensure Bids can be submitted on the due date.
o Please make sure the electronic documents submitted contain any required signatures. Digital signatures will be accepted.
• Bid Opening will be held via conference call on 6/11/26 at 3:00 pm
• Contractor shall reference section 00 0116 for the bid submittal checklist o Bid Proposal Information o Non Discrimination Clause Information o Contractor Targeted Small Business Enterprise Pre-Bid Contract Information o Bid Security – 5% of total Bid amount
• Apparent low bidder will be required to submit subcontractor/supplier list 48hrs after the bid opening
3.2 1 Bid Schedule Open
Description
• Questions/Substitutions Due in Writing to Construction.Procurement@das.iowa.gov: Thursday 5/28/26 at 2:00 pm
• Addendum Issued: Friday 5/29/26
• Bids Due: 6/11/26 at 2:00 pm
• Tentative NOI Issued: 6/15/26
3.3 1 Administrative Details Open
Description
• Contractors will sign a modified ConsensusDocs 802. Example in the project manual.
• Project-specific Certificate of Insurance must be provided prior to contract execution. Follow example in the project manual and limits in the 802.
• Project-specific P&P bonds must be provided prior to contract execution.
• Successful contractor must turn in their list of subcontractors and suppliers within 48 hours of the bid.
• DAS will provide tax exempt certificates upon request.
• Procore will be used for all project management, at no cost to the trade contractor.
o Submittals, Invoicing, RFIs, ASIs, PRs, RFQs o Contracts, Change Orders and Certificates of Substantial and Final Completion will also use Docusign
• Contractor Schedule of Values shall be broken out as specified in the project manual.
o SOV must contain a closeout line item for at least 1% of the total contract value.
o This line item can only be invoiced once the certificate of final completion has been signed by all parties.
State of Iowa - Department of Administrative Services Page 4 of 5 Printed On: May 21, 2026 11:02 AM CDT
3.4 1 Pre-Bid Site Visits Open
Description Coordinate with Aaron Ledeboer (McGough) for any additional site visits
Questions
4.1 1 Questions Open
Description Submit all questions in writing to construction.procurement@das.iowa.gov.
Official Documented Meeting Minutes
• Dimensions of existing tanks?
o Measure during site walk or scale on drawings
• Control panel o Intent of control panel is it is to be provided with diesel tank along with the controls/sensors/valves for the safety features of the tank
• Check-valve for anti-siphon required?
o Addendum #1 to provide additional context to requirements
• E-stop for automatic valve to stop filling?
o Addendum #1 to provide additional context to requirements
• Tie-in of anti-siphon to E-stop?
o Design team to consider and provide context to requirements in Addendum #1
These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.
Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.
State of Iowa - Department of Administrative Services Page 5 of 5 Printed On: May 21, 2026 11:02 AM CDT