RFB948100-01 - Addendum 02.pdf

PDF 1 MB Posted

Attached to
DOC 5JD 150 DSM ST Renovation
Solicitation number
RFB948100-01
Issued by
Polk County, Des Moines City, Iowa

About this file

Summary

This Addendum #02 to Request for Bid (RFB) 948100-01 is issued by the State of Iowa Department of Administrative Services for interior renovation services at 150 Des Moines Street in Des Moines, Iowa. The addendum, dated October 16, 2026, supersedes portions of the original bidding documents from August 20, 2026, and provides clarifications through twenty-one questions and answers addressing project scope, responsibilities across four bid packages, and technical specifications. The project involves renovation of approximately 23,000 square feet across basement and first-floor levels, including demolition, new interior partitions, ceiling systems, flooring, wall finishes, restroom facilities with ADA-compliant fixtures, HVAC modifications, electrical systems upgrades, plumbing infrastructure, fire alarm systems, and technology installations. Bids are due October 28, 2026, at 2:00 p.m., with bid opening scheduled for October 28, 2026, at 3:00 p.m. via conference call. Construction is scheduled to commence November 23, 2026, with substantial completion targeted for April 15, 2027, and final closeout by May 20, 2027. A pre-bid meeting was held on October 8, 2026, with attendance documented from the State of Iowa Department of Administrative Services, Fifth Judicial District Department of Correctional Services, Horizon Architecture, IMEG Consultants Corp., and McGough Construction. The addendum introduces Bid Package #4 as an option for a single general contract complete project scope alternative, and establishes Unit Price #01 for unforeseen existing floor preparation at rates to be determined during bidding.

The project is structured as multiple bid packages with separate pricing: Bid Package #1 addresses general construction including demolition, rough carpentry, casework, doors, hardware, and finishes; Bid Package #2 covers mechanical work encompassing plumbing and HVAC systems; Bid Package #3 addresses electrical, communications, and fire alarm systems; and Bid Package #4 provides an alternative single-contractor option for complete project scope. Two additive alternates are available: Add Alternate #01 for replacement of existing HVAC diffusers and flex ductwork, and Add Alternate #02 for a complete sound masking system. The State of Iowa is exempt from sales and use taxes, so tax should not be included in bid amounts. A stipulated cash allowance of $128,053.00 is included in Bid Package #3 for State-selected security and access control work by Security Equipment, Inc., with the architect/engineer's probable construction cost estimated at $1,006,196.73 plus the $128,053 SEI allowance for a combined total of $1,134,249.73. Bid security is required at five percent of the total bid amount, and the successful bidder must submit subcontractor and supplier lists within 48 hours of bid opening. Contractors must maintain daily logs in Procore, adhere to work hours of 7:00 a.m. to 5:00 p.m. Monday through Friday, and comply with Iowa's resident bidder preference requirements under Iowa Code 73A.21. Drawings were prepared by Horizon Architecture and IMEG Consultants Corp., with the project located in Des Moines, Iowa (Polk County).

View the file

Other files

File Type Posted
RFB948100-01 - Project Manual (Reduced Size).pdf PDF
RFB948100-01 - Addendum 03.pdf PDF
RFB948100-01 - Bid Form.pdf PDF
RFB948100-01 - Notice to Bidders.pdf PDF
RFB948100-01 - Drawings.pdf PDF
RFB948100-01 - Addendum 01.pdf PDF
1451261-event.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9481.00 5JD DOC 150 DSM ST Renovation Addendum 2 Page 1 of 3

RFB948100-01 ADDENDUM #02

DATE: October 16, 2026

PROJECT: 9481.00 DOC 5JD 150 DSM ST Renovation

BID DUE DATE: October 28, 2026 @ 2:00 pm

TO: All Contract Document Holders of Record.

This Addendum forms a part of the bidding and construction documents. This Addendum supersedes and supplements all portions of the original bidding and construction documents dated August 20, 2026, with which it conflicts. Please attach this Addendum to the Project Manual(s) in your possession.

ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE BID

FORM. FAILURE TO DO SO MAY SUBJECT BIDDER TO DISQUALIFICATION.

1. QUESTIONS/CLARIFICATIONS

a. The meeting minutes & attendance from the RFB Pre-Bid Meeting held on 10/08/2026 can be found below. Please see Exhibit A.

b. The project schedule in Section 00 31 13, Preliminary Schedule references zones for the construction sequence. The zone map can be found in Exhibit B.

Q1. Who is the authority having jurisdiction (AHJ) for this project?

A1. The State of Iowa Department of Administrative Services (DAS) is the AHJ for this project. The City of Des

Moines is not the AHJ.

Q2. Is hazardous material abatement included in the project scope?

A2. No. DAS contracted with Terracon to conduct a hazardous materials assessment and based on its findings, hired a licensed abatement contractor to remove the identified hazardous materials affected by the project scope. The hazardous materials report is available in Section 00 31 26, Existing Hazardous Material Information.

Q3. Are background checks required for this project?

A3. No. Background checks are not required for this project.

Q4. May the awarded contractors use an existing office or other area in the building as an onsite construction office?

A4. Yes. Contractors may use existing spaces as onsite offices, provided they do not interfere with work taking place in those areas.

Q5. May contractors bid on all three bid packages?

A5. Bid Package #4 has been added. See Exhibit C for the updated Section 01 12 00, Contract Summary, and

Section 00 41 16, Bid Form.

Q6. Is furniture included in the project scope?

A6. No. Furniture is not included in the project scope and is being handled by the State of Iowa Management and

Leasing Bureau.

Q7. Is there any casework on the interior side of the transaction window?

A7. No. The transaction window should have an integral shelf.

Q8. Which bid package is responsible for the below-slab plumbing demolition and patch back? It is shown on

Architectural Demolition Plan D101, but Section 01 12 00, Contract Summary, lists it under Bid Package #2 –

9481.00 5JD DOC 150 DSM ST Renovation Addendum 2 Page 2 of 3

Mechanical.

A8. The below-slab plumbing demolition and patch back is the responsibility of Bid Package #2 – Mechanical.

Q9. The Door and Frame Schedule identifies the following openings as having Door Panel “F.” Based on the discussion at the Pre-Bid Meeting, these are to be cased openings. Please confirm.

DM113A

DM114A

DM115A

DM116A

DM117A

DM118A

DM119A

DM120A

DM121A

DM122A

A9. Confirmed. These locations are to be framed openings without doors.

Q10. The framing at the following openings is to be adjusted from one side of the wall while minimizing damage to the opposite side. Please confirm whether knock-down frames can be utilized. If welded frames are required, please quantify the extent of drywall removal and replacement needed on the opposite side.

DM113A

DM114A

DM115A

DM116A

DM117A

DM118A

DM119A

DM120A

DM121A

DM122A

A10. Knock down frames are acceptable.

Q11. Who is responsible for providing dumpsters?

A11. Dumpsters should be provided and maintained by Bid Package #1 – General Construction.

Q12. Is there a need for job site perimeter fencing?

A12. No. Perimeter fencing is not required.

Q13. The facility restrooms will be available for use by onsite construction personnel. Who is responsible for cleaning and maintaining these restrooms during construction, and how frequently must they be cleaned?

A13. Cleaning and maintenance of the onsite restrooms is the responsibility of Bid Package #1 – General

Construction. These restrooms should be cleaned once per week.

Q14. The tile wainscot in the ADA restroom does not extend high enough to accommodate the upper mounting location of the vertical grab bar. Should the tile wainscot be extended, or will a detail be provided for mounting the upper portion of the grab bar?

A14. The escutcheon plate should provide sufficient flexibility to accommodate the elevation difference; no modifications are required.

Q15. What is the countertop material for the casework shown in Elevation 2-A on A401?

A15. The countertop material at this elevation is plastic laminate. See Section 06 41 00, Architectural Wood

Casework, Subsection 2.10, which specifies high-pressure decorative laminate (HPDL) bonded to a substrate for all areas except bathrooms. The specification further requires:

9481.00 5JD DOC 150 DSM ST Renovation Addendum 2 Page 3 of 3

1. Laminate sheet: ISO 4586-2, Grade HGS, 0.031-inch (0.8 mm) nominal thickness.

2. Exposed edge treatment: Square, with the substrate built up to a minimum thickness of 1-1/4 inches (32

mm) and covered with matching laminate.

Q16. Who is responsible for the final construction cleaning?

A16. Bid Package #1 – General Construction is responsible for the final construction cleaning.

Q17. The floor has noticeable dips in several areas, and its condition beneath the high-density storage system is unknown. Should an allowance for floor patching be included?

A17. No allowance is included. Floor preparation that is visible or reasonably inferable prior to bidding shall be included in the Base Bid, as required by the Specifications. Unforeseen existing floor preparation encountered anywhere within the Project after demolition or removal of existing finishes, raised-floor components, equipment, or other concealed conditions will be addressed using Unit Price #01, as authorized by the Owner through Change

Order. Unit Price #01 has been added to Section 01 12 00, Contract Summary, and Section 00 41 16, Bid Form.

Please see Exhibit C below.

Q18. Section 10 28 00, Toilet, Bath, and Laundry Accessories lists under-lavatory pipe and supply covers, which are typically included in the mechanical bid package. Which bid package is responsible for providing and installing these covers?

A18. Bid Package #2 – Mechanical is responsible for furnishing and installing the under-lavatory pipe covers listed in Section 10 28 00, Toilet, Bath, and Laundry Accessories.

Q19. Will the addendum clarify whether the project scope should include replacing all existing fire alarm field devices, including the zone-style initiating devices and the non-synchronized horns and strobes, with current devices that provide point identification and synchronized notification; having the engineer determine whether the existing fire alarm wiring is code-compliant and suitable for reuse; and adding a power supply and NAC card to the existing

4100ES panel, with new homerun circuits for the additional horn/strobes? The existing panel’s IDNet loop has 250 available addresses for the initiating devices.

A19. Project scope is to replace only notification/initiation devices shown on the drawings. The existing 4100ES panel is expandable. Contractor and fire alarm vendor to determine requirements for expansion including but not limited to; power supplies, expansion cards, extender panels, and circuits.

Q20. Can the probable construction cost or engineer’s estimate be provided at this time?

A20. The Architect/Engineer’s probable construction cost is $1,006,196.73. The $128,053 SEI allowance is additional, for a combined total estimate of $1,134,249.73.

Q21. For the LVT Flooring, none of the products/styles listed in Part 2.01 meet the requirements listed. The basis of design is 12x24, 2.5mm, glue down. Is that what you’re looking for?

A21. Basis of design was selected by the Owner. Provide basis of design or equal.

END OF ADDENDUM 02

State of Iowa - Department of Administrative Services 109 SE 13th St.

Des Moines, Iowa 50319 P: (515) 281-7260

Project: 9481.00 DOC 5JD 150 DSM ST Renovation 150 Des Moines St

Des Moines, Iowa 50309

RFB Pre-Bid Meeting Minutes: Meeting #1

Meeting Date Oct 8, 2026 Meeting Time 10:30 am - 12:00 pm Central Time (US & Canada)

Meeting Location 150 Des Moines Street, Des Moines, IA 50309 Video Conferencing Link

Join Meeting

Overview Meeting to allow prospective bidders to visit the site when possible, review project requirements and bid packages, and learn more about the project.

Notes

Attachments

Scheduled Attendees

Name Company Phone Number Email Attendance

Lance Wignall Fifth Judicial District - Department of Correctional Services

P: (515) 250-4864 lance.wignall@iowa.gov Present

Michael Nolan Horizon Architecture michael@horizon-architecture.com Conference

Rawya Osman Horizon Architecture rawya@horizon-architecture.com Present

Parker Polaschek IMEG Consultants Corp P: (515) 334-9906 parker.j.polaschek@imegcorp.com Present

Parker Badding McGough Construction parker.badding@mcgough.com Present

Brandon Adams State of Iowa - Department of Administrative Services brandon.adams@das.iowa.gov Present

Introduction

No. Mtg Origin Title Assignment Due Date Priority Status

1.1 1 Introductions Open

Description

• Attendees o DAS, Owner's Rep

▪ Brandon Adams o 5th District, Facility Coordinator

▪ Lance Wignall o Horizon, Architect of Record

▪ Michael Nolan

▪ Rawya Osman

State of Iowa - Department of Administrative Services Page 1 of 7 Printed On: Oct 8, 2026 03:53 PM CDT

EXHIBIT A

https://teams.microsoft.com/meet/282683621076225?p=APg7D4mlqpefQ1PyNp o IMEG

▪ Parker Polaschek - Plumbing & HVAC Engineer

▪ Senko Dizdarevic - Electrical Engineer

▪ Steve Engler - Technology Engineer o McGough, Construction Manager

▪ Parker Badding - Asst. Project Manager

▪ Adam Douglas - Project Executive

▪ Barry Voelker - Site Superintendent

Official Documented Meeting Minutes

• Contractor meeting attendance can be found in Addendum 02.

Project Overview

2.1 1 Project Description Open

Description

• Bid Package #01 – General Construction: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

o Includes Specifications:

▪ Division 00 – Procurement and Contracting Requirements

▪ Division 01 – General Requirements

▪ Division 02 – Existing Conditions

▪ 02 4100 Demolition

▪ Division 06 – Woods, Plastics, and Composites

▪ 06 1053 Miscellaneous Rough Carpentry

▪ 06 4100 Architectural Wood Casework

▪ Division 08 – Openings

▪ 08 1213 Hollow Metal Frames

▪ 08 1416 Flush Wood Doors

▪ 08 5659 Service Teller Window Units

▪ 08 7100 Door Hardware

▪ Division 09 – Finishes

▪ 09 2116 Gypsum Board Assemblies

▪ 09 3000 Tiling

▪ 09 5100 Acoustical Ceilings

▪ 09 6500 Resilient Flooring

▪ 09 6813 Tile Carpeting

▪ 09 9123 Interior Painting

▪ Division 10 – Specialties

▪ 10 2800 Toilet, Bath, and Laundry Accessories

Meeting #1 - RFB Pre-Bid Meeting Project: 9481.00 DOC 5JD 150 DSM ST Renovation

State of Iowa - Department of Administrative Services Page 2 of 7 Printed On: Oct 8, 2026 03:53 PM CDT

• Bid Package #02 – Mechanical: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

o Includes Specifications:

▪ Division 00 – Procurement and Contracting Requirements

▪ Division 01 – General Requirements

▪ Division 22 – Plumbing

▪ 22 0500 Basic Plumbing Requirements

▪ 22 0505 Plumbing Demolition for Remodeling

▪ 22 0529 Plumbing Supports and Anchors

▪ 22 0719 Plumbing Piping Insulation

▪ 22 1000 Plumbing Piping

▪ 22 1030 Plumbing Specialties

▪ 22 4000 Plumbing Fixtures

▪ Division 23 – Heating, Ventilating, and Air-Conditioning (HVAC)

▪ 23 0500 Basic HVAC Requirements

▪ 23 0505 HVAC Demolition for Remodeling

▪ 23 0593 Testing, Adjusting, and Balancing

▪ 23 0713 Ductwork Insulation

▪ 23 3100 Ductwork

▪ 23 3300 Ductwork Accessories

▪ 23 3700 Air Inlets and Outlets

• Bid Package #03 – Electrical: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

o Includes Specifications:

▪ Division 00 – Procurement and Contracting Requirements

▪ Division 01 – General Requirements

▪ Division 26 – Electrical

▪ 26 0500 Basic Electrical Requirements

▪ 26 0505 Electrical Demolition for Remodeling

▪ 26 0513 Wire and Cable

▪ 26 0526 Grounding and Bonding

▪ 26 0527 Supporting Devices

▪ 26 0533 Conduit and Boxes

▪ 26 0535 Surface Raceways

▪ 26 0553 Electrical Identifications

▪ 26 0933 Lighting Control Systems

▪ 26 2723 Indoor Service Poles

▪ 26 2726 Wiring Devices

▪ 26 5119 LED Lighting

▪ Division 27 – Communications

▪ 27 0500 Basic Communications Systems Requirements

▪ 27 0528 Interior Communication Pathways

▪ 27 5119 Sound Masking System

▪ Division 28 – Electronic Safety and Security

▪ 28 3100 Fire Alarm and Detection Systems

• Add Alternate #01 – Replacement of Existing HVAC Diffusers & Flex Ductwork: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

State of Iowa - Department of Administrative Services Page 3 of 7 Printed On: Oct 8, 2026 03:53 PM CDT o Bid Package #2 – Mechanical shall provide the additive cost to remove and replace the existing air diffusers and associated flex ductwork identified as Alternate Bid Work on Drawings M111 and M211.

o Include removal and lawful disposal of existing diffusers and flex ductwork; preparation of existing ductwork for new connections; new diffusers, flex ductwork, fittings, supports, insulation, accessories, connections, and all incidental work required for a complete installation.

o Include testing, adjusting, and balancing of affected air devices and systems to achieve the airflow values indicated on the Drawings.

o Work identified as Base Bid on Drawings M111 and M211, including removal, storage, reuse, reinstallation, and rebalancing of existing diffusers where indicated, remains in the Base Bid and shall not be included in this Alternate.

o Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

o Execute accepted alternates under the same conditions as other work of the Contract.

• Add Alternate #02 – Sound Masking System: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

o Bid Package #3 – Electrical shall provide the additive cost to furnish, install, test, commission, program, and place into operation a complete sound masking system in accordance with Section 27 51 19 and Drawings T200, T201, T300, and T400.

o Include all speakers, head-end equipment, controls, racks or backboards, power supplies, cabling, pathways, outlet boxes, conduit, supports, grounding and bonding, line-voltage power, required fire alarm interface/shunt, programming, testing, training, closeout documentation, and incidental materials and labor required for a complete, operational system.

o Coordinate locations and installation with ceiling, mechanical, electrical, fire alarm, and architectural work.

o Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

o Execute accepted alternates under the same conditions as other work of the Contract.

• Owner-Furnished & Owner-Installed Work: The 5th District Department of Corrections alongside the State of Iowa Department of Administrative Services (DAS) will perform the following work items:

o Except for the State-selected SEI scope carried as a Bid Package #3 allowance under Paragraph 1.09.C.5.d, the Owner will furnish and install all horizontal communications cabling, data outlets and terminations, network switches, wireless access points, monitors, security systems, access-control equipment, credential readers, cameras, electric strikes, and associated low-voltage cabling.

o The SEI access-control and video-surveillance scope described in Paragraph 1.09.C.5.d shall be included in Bid Package #3 as a stipulated allowance and is not otherwise excluded from the Bid Package #3 Base Bid. All other Owner-furnished and Owner-installed work remains excluded from Bid Package #3 except for electrical work specifically indicated or assigned in the Contract Documents.

o Bid Package #3 shall coordinate locations, installation sequencing, access requirements, and final connections affecting Owner-installed work and the State-selected SEI work. Do not include costs for furnishing, installing, programming, testing, or warranting Owner-installed low voltage, security, access-control, camera, data, or network equipment, except for the stipulated SEI allowance identified in Paragraph 1.09.C.5.d.

o Owner-furnished and Owner-installed work does not include the sound masking system included under Add Alternate 02.

• Unit Prices o There are no unit prices for this project.

For additional information regarding bid packages, alternates, and OFOI work, please reference Specification Section 01 12 00 - Contract Summary.

• Questions regarding scope will be answered via Addendum.

State of Iowa - Department of Administrative Services Page 4 of 7 Printed On: Oct 8, 2026 03:53 PM CDT

2.2 1 Project Schedule Open

Description

• Key Project Dates:

o Bids Due: October 28, 2026 o Contract(s) Issued: November 2, 2026 to November 13, 2026 o Submittals: November 16, 2026 to December 8, 2026 o Construction: November 23, 2026 to April 6, 2027 o Substantial Completion: April 15, 2027 o Closeout: February 15, 2027 to May 20, 2027

A pull-plan session will be held with the successful bid package contractors to finalize the construction schedule.

State Holidays: New Year's Day, Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day, Thanksgiving and day after Thanksgiving, Christmas Day

• N/A

2.3 1 Site Rules Open

Description

• On site supervision by Prime Contractor is required at all times when work by that contractor or their subcontractors/suppliers is taking place.

• Contractors shall provide daily logs for each day they are on site.

o Daily logs to be submitted into Procore.

• Construction progress meeting will be established once construction starts.

• Clean all debris, materials, and bring all finishes back to existing conditions in the area they were working in prior to moving to the next area.

• Smoking policies

Site Specific Rules

• Work hours are from 7:00 AM to 5:00 PM, Monday through Friday unless arrangements are made in advance.

• Hot Work Permit Processes and Fire Watch, when necessary, will be adhered to for this project.

• No drugs, alcohol, or firearms are allowed on the work site.

• Do not leave money, drugs, alcohol, or firearms in your personal vehicle.

• Company and personal vehicles are to be parked and locked in designated or authorized area of the work.

• Secure all tools at the end of the day.

• Maintain control of all tools, supplies, and debris at all times during work.

• All delivery vehicles must go directly to the job site. Extra time should be anticipated for all deliveries.

• View Specification 01 12 00 - Contract Summary for more information.

Official Documented Meeting Minutes

• This building is unoccupied.

o Storage & staging is acceptable on site.

State of Iowa - Department of Administrative Services Page 5 of 7 Printed On: Oct 8, 2026 03:53 PM CDT

• Further information regarding temporary sanitary facilities will be released via Addendum.

RFB Overview

3.1 1 Bid Submission Open

Description

• Bids are due October 28, 2026 @ 2:00 PM

• The Bid shall be submitted to the Issuing Officer through the IMPACS Electronic Procurement System.

o Link and information is in the project manual o Contractors will need to register prior to bidding o Bidders will need to register regardless of whether it has already done business with the State of Iowa.

o Bidders should complete the registration process and ensure the ability to log in as soon as possible to ensure Bids can be submitted on the due date.

o Please make sure the electronic documents submitted contain any required signatures. Digital signatures will be accepted.

• Bid Opening will be held via conference call on October 28, 2026 @ 3:00 PM

• Contractor shall reference Section 00 01 16 for the Bid Submittal Checklist o Bid Proposal Information o Non Discrimination Clause Information o Contractor Targeted Small Business Enterprise Pre-Bid Contract Information o Bid Security – 5% of total Bid amount

• Apparent low bidder will be required to submit subcontractor/supplier list 48hrs after the bid opening

• Contracts can not be finalized until the State has received each awarded contractors' COI and P&P Bonds.

3.2 1 Bid Schedule Open

Description

• Questions/Substitutions due in writing to Construction.Procurement@das.iowa.gov: October 21, 2026

• Addendum Issued: On or before October 23, 2026

• Bids Due: October 28, 2026 @ 2:00 PM

• Tentative NOI Issued: October 29-30

State of Iowa - Department of Administrative Services Page 6 of 7 Printed On: Oct 8, 2026 03:53 PM CDT mailto:Construction.Procurement@das.iowa.gov:

3.3 1 Administrative Details Open

Description

• Contractors will sign a modified ConsensusDocs 802. Example in the project manual.

• Project-specific Certificate of Insurance must be provided prior to contract execution. Follow example in the project manual and limits in the 802.

• Project-specific P&P bonds must be provided prior to contract execution.

• Successful contractor must turn in their list of subcontractors and suppliers within 48 hours of the bid.

• DAS will provide tax exempt certificates upon request.

• Procore will be used for all project management, at no cost to the trade contractor.

o Submittals, Invoicing, RFIs, ASIs, PRs, RFQs o Contracts, Change Orders and Certificates of Substantial and Final Completion will also use DocuSign

• Contractor Schedule of Values shall be broken out as specified in the project manual.

o SOV must contain a closeout line item for at least 1% of the total contract value.

o This line item can only be invoiced once the certificate of final completion has been signed by all parties.

• Once all contractors have been awarded, further conversations regarding daily logs will take place.

3.4 1 Pre-Bid Site Visits Open

Description

• If you would like to schedule an additional site visit after today's meeting, please contact Lance Wignall at (515) 250-4864.

Questions

4.1 1 Questions Open

Description

• Submit all questions in writing to construction.procurement@das.iowa.gov.

Official Documented Meeting Minutes

These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.

Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.

State of Iowa - Department of Administrative Services Page 7 of 7 Printed On: Oct 8, 2026 03:53 PM CDT

EXHIBIT A

UP

A

4'- 1"

5 1 /2"

'-2

3 1

/2"

90'-11 5/8"90'-11 5/8" 3 1/2"

4'-3 1/8"

8'-10 1/8" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2" 8'-10" 3 1/2"

A301

B C D

137 SF

COMPUTER

376 SF

STORAGE

6,820 SF

OPEN

OFFICE

215 SF

OFFICE

197 SF

OFFICE

422 SF

RECEPTION

116 SF

HALLWAY

75 SF

MEN'S

1005 94 SF

WOMEN'S

73 SF

ADA

RESTROOM

232 SF

PRINTERS

1,065 SF

CLASSROOM 01

157 SF

STORAGE

1030 195 SF

MEN'S

RR

255 SF

WOMEN'S

RR

1027328 SF

STORAGE

807 SF

BREAKROOM

548 SF

HALLWAY

186 SF

NEW

MEETING

ROOM

7'-

3 1

/2" 8'-

0" 3 1

/2" 7'-

503 SF

HALLWAY

84 SF

INTERVIEW

R10

88 SF

INTERVIEW

R09

86 SF

INTERVIEW

R08

88 SF

INTERVIEW

R07

88 SF

INTERVIEW

R06

88 SF

INTERVIEW

R05

101586 SF

INTERVIEW

R04

88 SF

INTERVIEW

R03

88 SF

INTERVIEW

R02

88 SF

INTERVIEW

R01

294 SF

ENTRY

LOBBY

137 SF

INTERVIEW

R11

133 SF

INTERVIEW

R12

163 SF

INTERVIEW

R13

13'-9"

D135

D134

D133A

D104

D102

D111 D112 D113 D114 D115 D116 D117 D118 D119 D120

D110

D109

D126A

D126B

D132

D133B

8'- 0"

3 1 /2"

9'- 6 1

/2" 3 1

/2"

'-7 1/

2"

D136

W01

P02

P0

P02

P01 P01 P01 P01 P01 P01 P01 P01 P01

P01

P0

P01

P0

P0

P02

P02

P0

P0

P02

P0

P02

P0

A301

A301

A401

A401

3 1/2" 9'-7" 3 1/2"

103 SF

OFFICE

Zone 1Zone 2

EXHIBIT B

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 1

SECTION 01 1200

CONTRACT SUMMARY

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Project Information B. Project Summary C. Bid Scope Summary D. Work Hour Restrictions E. Access to Site F. Coordination with Occupants G. Rules for Construction Workers H. Bid Package Instructions I. Bid Alternates

1.02 PROJECT INFORMATION

A. Facility Name/Location: 5th District Department of Corrections, 1000 Washington Ave, Des Moines, Iowa, 50314

B. DAS Project #: 9481.00 C. Owner: State of Iowa, Department of Administrative Services, Hoover State Office Building, Level 3, 1305 East Walnut Street, Des Moines, IA 50319 D. Owner’s Representative: Brandon Adams, Iowa Department of Administrative Services, 109 SE

13th Street, Des Moines, IA 50319 E. Construction Manager: Parker Badding, McGough Construction, 217 E 2nd Street, Suite 120, Des Moines, Iowa 50309

1.03 PROJECT SUMMARY

A. The project includes interior renovations & upgrades to the building located at 150 Des Moines Street, Des Moines, Iowa.

B. Target date to provide substantial completion is April 15, 2027.

1.04 BID SCOPE SUMMARY

A. Scope Applicable to All Bid Packages:

1. The Contractor’s Work includes all labor, supervision, materials, equipment, services, supplies, tools, facilities, transportation, hoisting, storage, receiving, licenses, inspections, certifications, overhead, profit, or other items required or reasonably inferable to properly and timely perform and complete all work and services to be performed by the Contractor pursuant to this Agreement. Unless specifically stated otherwise, incidental work required to accomplish the work of this Bid Package shall be included the bid. This would include, but not be limited to, temporary facilities, protection of the work, security of equipment, materials, and work in progress, etc. Contractor’s Work shall be performed in accordance with the Drawings, Specification Divisions 00 and 01, and Specification sections applicable to each Contractor’s scope.

2. Contractor is responsible for all labor and equipment to unload, account for all material delivered, stock, and delivery for this scope of work. Storage and delivery of materials and equipment at the Site shall be permitted only to the extent approved in advance by the Construction Manager, and if anything so stored obstructs the progress of any portion of the work, it shall be promptly removed or relocated by the Contractor without reimbursement.

EXHIBIT C

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 2

3. On site supervision by Prime Contractor at all times work by that contractor or their subcontractors/suppliers is taking place.

4. Provide all temporary facilities required for this scope of work including trailer, trailer power, telephone, secured storage, temporary power for work, temporary and task lighting for work, etc. as determined necessary by Contractor. Coordinate location of trailers, material storage and utility lines with Construction Manager. Limited space is available, and permission to bring any such facility or excess materials on to the site shall be approved by the Construction Manager.

5. Contractor shall provide all equipment and tools for Contractor’s own cleanup. Clean up shall be done at end of every shift or more frequently if required for the Contractor to perform their work, for other Contractors to perform their work, as required by the Owner’s operations, and at the discretion of the Construction Manager.

6. All turf, landscaping, and subgrade disturbances caused by equipment traffic or other activities related to the Contractor’s scope shall be repaired or restored to proper conditions by the Contractor.

7. Protect adjacent existing building elements from damage from Scope of work. Repair existing building elements damaged during Contractor’s Scope of work.

1.05 WORK HOUR RESTRICTIONS

A. Work hours are from 7:00 AM to 5:00 PM, Monday through Friday unless arrangements are made in advance.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

B. Provide access to and from site as required by law and Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permission of Owner and permit if required.

1.07 OWNER OCCUPANCY

A. Owner intends to occupy the building upon Substantial Completion.

B. Cooperate with Owner to minimize conflict and to facilitate Owner’s operations.

C. Schedule the work to accommodate Owner occupancy.

1.08 RULES FOR CONSTRUCTION WORKERS

A. The staff of the State of Iowa has a responsibility to protect the public by providing a secure environment. All work site rules must be followed to the letter, at all times.

B. Hot Work Permit Processes and Fire Watch, when necessary, will be adhered to for this project.

C. All State properties are tobacco free. No smoking will be permitted or tolerated on campus unless in designated areas.

D. You are permitted access only to the work site and no other area of the institution.

E. No drugs, alcohol, or firearms are allowed on the work site.

F. Do not leave money, drugs, alcohol, or firearms in your personal vehicle.

G. Company and personal vehicles are to be parked and locked in designated or authorized area of the work.

H. Secure all tools at the end of the day.

I. Maintain control of all tools, supplies, and debris at all times during work.

J. All delivery vehicles must go directly to the job site. Extra time should be anticipated for all deliveries.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 3

1.09 BID PACKAGE INSTRUCTIONS

A. Bid Package #01 – General Construction: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Includes Specifications:

a. Division 00 – Procurement and Contracting Requirements

b. Division 01 – General Requirements

c. Division 02 – Existing Conditions

1) 02 4100 Demolition

d. Division 06 – Woods, Plastics, and Composites

1) 06 1053 Miscellaneous Rough Carpentry

2) 06 4100 Architectural Wood Casework

e. Division 08 – Openings

1) 08 1213 Hollow Metal Frames

2) 08 1416 Flush Wood Doors

3) 08 5659 Service Teller Window Units

4) 08 7100 Door Hardware

f. Division 09 – Finishes

1) 09 2116 Gypsum Board Assemblies

2) 09 3000 Tiling

3) 09 5100 Acoustical Ceilings

4) 09 6500 Resilient Flooring

5) 09 6813 Tile Carpeting

6) 09 9123 Interior Painting

g. Division 10 – Specialties

1) 10 2800 Toilet, Bath, and Laundry Accessories

2. 02 4100 – Demolition

a. Bid Package #1 shall perform all architectural selective demolition indicated on

Architectural Drawings D101 and D102 and specified in Section 02 41 00.

b. Include removal, protection, salvage or reuse where indicated, containment, debris removal, and lawful disposal of architectural items, including partitions, drywall, ceilings, ceiling grid and tile, floor finishes, raised-floor components, casework, countertops, doors, frames, and other architectural items indicated for removal.

c. Include demolition and modification of existing architectural work reasonably required to accommodate the new work shown. Field verify existing conditions before beginning work.

d. Provide protection of adjacent construction to remain and patch architectural substrates and finishes affected by Bid Package #1 to match adjacent existing or scheduled new finishes.

e. Mechanical, plumbing, electrical, communications, security, and fire alarm demolition are excluded from this Bid Package and are assigned to the applicable MEP Bid Package. Coordinate architectural demolition with those trades.

3. 06 1053 – Miscellaneous Rough Carpentry

a. Furnish and install fire-retardant-treated wood blocking, backing, nailers, and supplemental framing where required by the Drawings and Section 06 10 53.

b. Include blocking and backing for wall-mounted equipment, shelving, cabinets, plumbing fixtures, toilet accessories, wall-mounted door hardware, and similar items.

c. Provide 3/4-inch plywood blocking at TV locations on stud walls, extending 24 inches in each direction from the centerline of the TV, as indicated on Sheet A104.

d. Coordinate blocking and backing locations, elevations, and required dimensions with the Drawings and affected trades before installation.

4. 06 4100 – Architectural Wood Casework

a. This bid package shall furnish and install all millwork, solid surface, and plastic laminate complete per contract documents.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 4

b. This bid package shall clean millwork surfaces, drawers, and shelves after installation is complete.

c. This bid package shall cut out any mechanical or electrical penetrations in the millwork as required by those bid packages.

1) Coordinate the exact size and location with the appropriate trade.

d. This bid package shall install all cabinet locks per contract documents.

e. This bid package shall furnish and install all countertops per the Contract

Documents.

1) Include field verification before fabrication; coordinated openings and cutouts for plumbing, electrical, and other work; casework hardware; plastic-laminate countertops; solid-surface restroom countertops; backsplashes;

and protection of installed casework through completion.

5. 08 1213 – Hollow Metal Frames

a. This bid package is to furnish and install all hollow metal doors and frames and associated door hardware complete as indicated in the contract documents.

1) Include anchoring of door frames to studs.

2) Include anchoring of door frames to concrete slab.

b. Scope to be coordinated and prepped to receive access control, power, automatic entry devices, alarms, and other control systems.

c. Power, electric strikes, and other low voltage wiring to be installed and connected by others.

d. All doors are to be clearly marked and delivered to location agreed upon by Construction Manager.

e. No wood doors will be staged in direct sunlight or unconditioned space.

f. Furnish and install Bondo at exposed fasteners.

1) Repairs are to be sanded flush to follow metal frame prior to painting.

g. Furnish and install doors, hollow-metal frames, door hardware, and accessories identified in the Door and Frame Schedule and Specifications. Include frame preparation for electric strikes and other electrified hardware where indicated.

Electrical connection, access control equipment, and access-control modifications are by others unless specifically assigned to this Bid Package.

6. 08 1416 – Flush Wood Doors

a. This bid package shall furnish and install wood doors and associated hardware complete per the Contract Documents.

b. Furnish and install 20-minute fire-rated wood doors as indicated on the Door and

Frame Schedule on Sheet A601.

c. Provide complete listed and labeled fire-rated door assemblies, including doors, compatible frames, hardware preparations, labels, and accessories required for installation in the new 1-hour fire partition. Coordinate electrified hardware preparation with the Owner-installed access-control work.

7. 08 5659 – Service Teller Window Units

a. This bid package shall furnish and install the service teller window complete per the Contract Documents.

b. This bid package shall include all trim, anchorage, glazing, interfaces, and coordination with adjacent casework and wall construction.

8. 08 7100 – Door Hardware

a. This bid package is responsible for accepting and organizing materials to the designated material staging area which will be coordinated with the Construction Manager.

1) All hardware materials must be inventoried and signed off by this bid package. Materials missing will be the responsibility of this bid package to replace.

b. This bid package shall attend (2) meetings to review door hardware and keying requirements with the Owner, Architect, and Construction Manager prior to fabrication of door frames release of door hardware.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 5

c. This bid package shall check and test each door that has a locking mechanism to ensure that it operates correctly prior to Construction Manager’s punch list.

9. 09 2116 – Gypsum Board Assemblies

a. This bid package shall furnish and install complete per Contract Documents:

1) Drywall Installation

2) Taping & Finish

3) Fire Rated Assemblies

b. Verifying all walls in new areas are scheduled either smooth or textured.

1) Verify existing wall condition and match finish accordingly.

c. This bid package shall furnish and install all control and expansion joints on exposed interior surfaces of exterior walls and/or ceilings.

d. Provide metal-stud partitions, gypsum board, joint treatment, insulation, acoustical sealants, sound partitions, tile backing board, patching, and repairs indicated on the Drawings and specified in Section 09 21 16. Include sound-attenuation blankets at partitions designated “S,” full-stud-thickness insulation where indicated, and backing/blocking required by Sheet A104.

e. Include substrate preparation, repairs, transitions, edge strips, base, and incidental materials required for complete finished installations. Coordinate floor elevation changes and provide ADA-compliant transition profiles as detailed on Sheet A105.

f. This bid package shall furnish and install all acoustic sealants at top and bottom of walls.

1) Exclude penetrations, to be picked up by others.

2) Include structural building components.

g. Interior Drywall shall be held 3/8” off the floor. Gap to be filled with acoustic sealant per Contract Documents.

h. Furnish and install Mold and Moisture drywall for wet areas.

i. Furnish and install Tile Backer Board or Cementous Board for locations scheduled to receive ceramic tile.

j. Scope includes the repair of drywall at existing walls scheduled to remain where backing is required for wall hung items, outlets, conduits, thermostats, etc. are required in existing walls.

1) Including patching back channels in wall created for new electrical rough-ins, blocking, or other channels for other contractors to install their scope of work.

2) For other existing walls to remain provide patching where wall hung items such as shelving, wire mold, etc. have been removed.

3) In rooms and areas that call for no base finish, wall completely to floor.

Include minor patch and repair after flooring is installed.

k. This bid package shall furnish and install all batt, sound, mineral wool insulation within metal framing scope of work per Contract Documents.

1) Furnish and install materials to conform with wall assembly requirements per Contract Documents.

a) This includes thickness of insulation within wall cavities listed in the

Contract Documents.

l. Provide the P01 wall assembly at all locations indicated on the Drawings, including the new north wall of the interview rooms. Construct the P01 wall as a 1-hour fire-rated, STC-49 partition in accordance with Sheet A104 and the Contract Documents.

m. Include all framing, gypsum board, Type X gypsum board where required, insulation, sealants, tracks, attachments, and incidental materials required for a complete 1-hour fire partition. Extend and terminate the rated partition as required by the Drawings and applicable listing.

10. 09 3000 – Tiling

a. This bid package shall furnish and install tiling complete per Contract Documents.

b. Furnish and install all ceramic tile, stone veneer, grout, layout, metal transitions, and anything else included to complete scope.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 6

c. This bid package shall verify and coordinate tile patterns with Construction Manager prior to commencement of work.

11. 09 5100 – Acoustical Ceilings

a. This bid package shall furnish and install Acoustical Ceilings system complete per

Contract Documents.

b. This bid package will install ACT grid first & border tiles then allow utilities to be installed.

1) Ceiling Tile installation to occur after utility finishes are installed and inspected. Construction Manager to coordinate.

12. 09 6500 – Resilient Flooring

a. This bid package shall furnish and install Resilient Flooring complete per the Contract Documents.

b. Include floor prep as required per the manufacturer's requirements.

c. This bid package shall provide temporary floor protection after the installation is completed.

13. 09 6813 – Tile Carpeting

a. This bid package shall furnish and install Tile Carpeting complete per the Contract Documents

1) Furnish and install:

a) Base

b) Tile Carpeting

b. Include floor prep as required per the manufacturer's requirements.

14. 09 9123 – Interior Painting

a. This bid package shall furnish and install Interior Painting complete per Contract Documents.

b. Drywall surfaces will be required to be completed and ready for painting at the time prime paint is applied.

1) This bid package acknowledges that repairs or imperfections are normal and customary and will be required after the prime paint has been applied prior to the application of the first coat of finish paint.

c. Furnish and install all caulking where painted surfaces abut one another or dissimilar materials abut painted or wall covered surfaces including all painted wood trim, prefinished wood trim, cabinets, door frames, countertops, control joints, joints around mechanical-electrical-plumbing trim where necessary, ceramic tile, or other hard surface materials.

d. Fill all nail & screw holes and caulk all woodwork to itself and adjacent surfaces as required to obtain desired finish.

e. Sand all surfaces between prime and finish coat applications for all paint applications.

1) Sand finish coats, when necessary, between coats to remove trapped materials or other inconsistencies in the paint finish.

f. Protect all UL labels of all doors or frames to receive painted finish.

15. 10 2800 – Toilet, Bath, and Laundry Accessories

a. This bid package shall furnish and install all toilet, bath, and laundry accessories complete per the Contract Documents.

b. Include all accessories indicated on the restroom accessory key and ADA mounting-height detail on A401, including required anchors, backing coordination, and tamper-resistant fasteners.

B. Bid Package #02 – Mechanical: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Includes Specifications:

a. Division 00 – Procurement and Contracting Requirements

b. Division 01 – General Requirements

c. Division 22 – Plumbing

1) 22 0500 Basic Plumbing Requirements

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 7

2) 22 0505 Plumbing Demolition for Remodeling

3) 22 0529 Plumbing Supports and Anchors

4) 22 0719 Plumbing Piping Insulation

5) 22 1000 Plumbing Piping

6) 22 1030 Plumbing Specialties

7) 22 4000 Plumbing Fixtures

d. Division 23 – Heating, Ventilating, and Air-Conditioning (HVAC)

1) 23 0500 Basic HVAC Requirements

2) 23 0505 HVAC Demolition for Remodeling

3) 23 0593 Testing, Adjusting, and Balancing

4) 23 0713 Ductwork Insulation

5) 23 3100 Ductwork

6) 23 3300 Ductwork Accessories

7) 23 3700 Air Inlets and Outlets

2. DIVISION 22 & DIVISION 23 DEMOLITION

a. Bid Package #2 is responsible for all plumbing and HVAC demolition shown on the

Contract Documents and specified in Sections 22 05 05 and 23 05 05.

b. Include disconnection, removal, relocation, storage for reuse, extension, capping, temporary services, supports, hangers, and disposal of plumbing and HVAC work required to complete the Work.

c. Coordinate demolition sequence and required shutdowns with the Construction Manager and Owner. Maintain systems serving occupied areas until approved shutdown and changeover are complete.

d. Bid Package #2 is responsible for cutting and patching back penetrations to original finish as a result from its Work, as required by the electrical specifications.

1) This Bid Package shall include the removal and replacement of concrete required for pipe demolition.

2) This Bid Package shall include floor scans prior to any concrete cutting.

3. ALL DIVISION 22

a. Furnish and install all plumbing work indicated in the Contract Documents, including domestic water, sanitary waste and vent, storm piping, plumbing fixtures, plumbing specialties, valves, supports, insulation, testing, and connections required for complete and operational systems.

b. Coordinate plumbing rough-in locations, fixture locations, elevations, and final connections with architectural work, casework, toilet accessories, floor finishes, and other trades.

c. Maintain active plumbing systems serving occupied areas until approved shutdowns and changeovers are complete. Coordinate all shutdowns with the Owner and Construction Manager.

d. Include removal of water connections at fire-extinguisher cabinet locations identified for repurposing on the Architectural Demolition Drawings. Coordinate non-destructive removal with Bid Package #1, which will perform the cabinet modification and relabeling work.

e. Include all required cutting, scanning, coring, patching, supports, sleeves, and incidental work necessary for complete plumbing installation, as specified.

4. ALL DIVISION 23

a. Furnish and install all HVAC work indicated in the Contract Documents, including ductwork, ductwork accessories, air devices, insulation, supports, connections, testing, adjusting, balancing, and all work required for complete and operational systems.

b. Include demolition, disconnection, removal, relocation, extension, capping, temporary services, and disposal of existing HVAC work required for the new construction.

c. Maintain active HVAC systems serving occupied areas until approved shutdowns and changeovers are complete. Coordinate all shutdowns, sequencing, and temporary-service requirements with the Owner and Construction Manage.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 8

d. Coordinate ductwork, air devices, thermostats, access requirements, and final installation with ceilings, lighting, fire alarm, sound masking, architectural partitions, and other trades.

e. Furnish and install FD-1 fire dampers at all duct penetrations through the new 1-hour fire partitions, as indicated on Sheet M211 and the Life Safety Damper Schedule on Sheet M400.

f. Include fire dampers, sleeves, breakaway connections, access doors, labels, supports, duct modifications, coordination, and all incidental work required for a complete code-compliant installation in accordance with Section 23 33 00.

g. Field verify final damper sizes based on completed installation drawings and coordinate damper locations with the new P01 fire partitions and other trades.

h. Include testing, adjusting, and balancing of affected systems and air devices after completion of the Work, including the Base Bid diffuser reuse work and any accepted Add Alternate 01 work.

C. Bid Package #03 – Electrical: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Includes Specifications:

a. Division 00 – Procurement and Contracting Requirements

b. Division 01 – General Requirements

c. Division 26 – Electrical

1) 26 0500 Basic Electrical Requirements

2) 26 0505 Electrical Demolition for Remodeling

3) 26 0513 Wire and Cable

4) 26 0526 Grounding and Bonding

5) 26 0527 Supporting Devices

6) 26 0533 Conduit and Boxes

7) 26 0535 Surface Raceways

8) 26 0553 Electrical Identifications

9) 26 0933 Lighting Control Systems

10) 26 2723 Indoor Service Poles

11) 26 2726 Wiring Devices

12) 26 5119 LED Lighting

d. Division 27 – Communications

1) 27 0500 Basic Communications Systems Requirements

2) 27 0528 Interior Communication Pathways

3) 27 5119 Sound Masking System

e. Division 28 – Electronic Safety and Security

1) 28 3100 Fire Alarm and Detection Systems

2. DIVISION 26, 27, & 28 DEMOLITION

a. Bid Package #3 is responsible for all electrical and fire alarm demolition shown on the Contract Documents, including associated raceways, wiring, devices, equipment, supports, and disposal.

b. Existing communications cabling, data outlets, security systems, access-control equipment, cameras, credential readers, electric strikes, and associated low-voltage work are excluded from this Bid Package and shall be performed by the Owner, unless specifically indicated otherwise.

c. Coordinate electrical and fire alarm demolition sequencing, required shutdowns, and protection of Owner-installed systems with the Construction Manager and Owner.

d. Bid Package #3 is responsible for cutting and patching back penetrations to original finish as a result from its Work, as required by the electrical specifications.

3. ALL DIVISION 26 – ELECTRICAL

a. Furnish and install branch circuitry, feeders, conduit, wiring, boxes, devices, and connections required for a complete and operational electrical system.

PROJECT 9481.00 CONTRACT SUMMARY 01 1200 - 9

b. Furnish and install new luminaires, lamps or LED components, emergency lighting, exit signage, lighting controls, occupancy sensors, dimming controls, and associated wiring and programming as indicated.

c. Provide electrical rough-in and final power connections for mechanical, plumbing, technology, communications, and other equipment where indicated or required by the Contract Documents.

d. Include all sleeves and penetrations required by Division 26 work, supports, seismic bracing where required, access panels, coordination, testing, labeling, and closeout documentation necessary for complete installation.

e. Coordinate shutdowns, removal, reconnection, and sequencing with the Owner, Construction Manager, and other Bid Package Contractors. Maintain active systems serving occupied areas until approved shutdown and changeover are complete.

4. ALL DIVISION 27 – COMMUNICATIONS

a. Provide Division 27 pathways and rough-in expressly indicated for Bid Package

#3, including conduits, sleeves, outlet boxes, plaster rings, pull strings, & cable supports.

b. Except for the State-selected SEI scope described in Paragraph 1.09.C.5.d, horizontal cabling, outlets, terminations, network equipment, wireless access points, monitors, security cabling, and associated low-voltage equipment are Owner-furnished and Owner-installed and are excluded from this Bid Package.

c. Provide line-voltage electrical power and other Division 26 work required to support Owner-installed communications and technology systems where indicated on the Contract Documents.

d. Coordinate all rough-in and support work with the Owner before installation.

e. The Owner-installed communications and low-voltage…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .