RFB927940-04 - Addendum #1.pdf

PDF 6 MB Posted

Attached to
HHS WRC Campus Utility Decentralization Phase 4/Fire Alarm Phase 3/Linden Fire Suppression
Solicitation number
RFB927940-04
Issued by
Dallas County, Iowa

About this file

This Addendum #1 to Request for Bids (RFB) 927940-04, issued by the Iowa Department of Administrative Services on May 21, 2026, modifies the bidding documents dated March 27, 2026, for the WRC Decentralization Phase 4 & Fire Alarm Phase 3 project at Woodward Resource Center (DAS Project Numbers 9279.40 & 9279.41). The project encompasses utility decentralization and fire alarm replacement across Linden Court Buildings A/B and C/D, with revised bid due date of June 9, 2026, at 2:00 p.m. A pre-bid meeting was held on May 15, 2026, with minutes and attendee list provided as attachment. The addendum addresses eighteen questions raised during the pre-bid meeting, clarifying critical scope items including abatement contractor responsibilities (four mobilizations required with priority on Linden Court buildings first), electrical penetration procedures (each contractor responsible for their own with code-compliant sealing), equipment specifications (Panel MDP-1 existing; all other panels and transformers new; lighting dual voltage rated at both 120V and 277V), conduit routing flexibility through existing tunnels, reuse of existing conduit and back boxes where ceilings remain un-abated, fire alarm device protection procedures (taping and bagging to prevent accidental activation), PREA training requirements (virtual session under 20 minutes), temporary power coordination between electrical and abatement contractors with floor-by-floor lockout capability, inclusion of hallway devices, use of existing uni-strut racks, air clearance requirements for Oak Hall following abatement, limited power availability at Oak Hall with future addendum forthcoming, floor tile removal specifications (5-foot width on each side of centerline for 10-foot work area), and furniture removal prior to abatement commencement. The addendum supersedes conflicting portions of original documents and requires acknowledgment of receipt in the IMPACS electronic procurement system; failure to acknowledge may result in bidder disqualification.

The addendum includes comprehensive revisions to seventeen mechanical drawing sheets (09-MD200 through 09-M501 and 13-MD200 through 13-M600) addressing basement, first floor, and second floor mechanical ductwork demolition plans and new installations, thermostat plans, and mechanical controls sequences with additions of existing return transfer ducts, return ductwork and fire dampers, ERV and heat pump control sequences, keynote revisions, and expanded mechanical schedules. A substitution request for Potter IPA-4000V Addressable voice notification panel was not approved, with requirement that fire alarm system be Siemens to communicate with existing panels. The contract documents contain mandatory certifications, bonding requirements, and standard state procurement provisions applicable to all respondents, with potential set-asides for disadvantaged business enterprises as determined by state policy. Bidders acknowledge receipt of the addendum in IMPACS and certify understanding of all project specifications, including the comprehensive Hazardous Building Materials Survey Report identifying fourteen distinct materials containing asbestos and lead-based paint requiring licensed abatement prior to construction, with project documentation prepared by licensed professionals including Architect Cameron L. Manley and Professional Engineers Kyle A. Lawson, John D. Baumhover, and Kevin J. Bruxvoort.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1 for RFB927940-04

Project Name: WRC Decentralization Phase 4 & Fire Alarm Phase 3 (9279.40 & 9279.41) Bid Issuance #4

DAS RFB #: 927940-04

DAS Project #: 9279.40 & 9279.41 Date: 5/21/2026

Bids Due: June 9, 2026, at 2:00pm

TO: PROSPECTIVE BIDDERS:

THIS ADDENDUM FORMS A PART OF THE BIDDING AND CONTRACT DOCUMENTS AND MODIFIES THE BIDDING DOCUMENTS DATED 03-27-2026, WITH AMENDMENTS AND ADDITIONS NOTED BELOW. THIS

ADDENDUM SUPERSEDES AND SUPPLEMENTS ALL PORTIONS OF THE ORIGINAL BIDDING AND

CONTRACT DOCUMENTS WITH WHICH IT CONFLICTS. ACKNOWLEDGE RECEIPT OF THIS ADDENDUM

IN THE IMPACS ELECTRONIC PROCUREMENT SYSTEM. FAILURE TO DO SO MAY DISQUALIFY THE

BIDDER.

QUESTIONS AND ANSWERS FROM PRE-BID MEETING

Q1. Should the abatement contractor demo all the black wire/metal associated with the plaster ceiling?

A1. Yes, all this would need to be removed by BP #01-1.

Q2. Does the BP 09 contractor make all the penetrations or does each BP contractor make their own penetrations?

A2. Each contractor will need to make their own penetrations and make sure it is sealed up around devices to meet code requirements.

Q3. On 00-E012, are all panels and transformers shown to be provided as new?

A3. Panel MDP-1 is existing. All other panels and transformers on 00-E012 are new.

Q4. Do the lights need to be 120 or 277v? The specs and drawings conflict.

A4. Based on existing panel schedules, lighting appears to be both 120V and 277V. All light fixtures to be dual voltage rated. Field verify lighting voltage prior to installation.

Q5. How should the contractor pipe the new electric through the tunnel with the existing items?

A5. Conduits do not need to be installed adjacent to each other on a rack. Route individual conduits as required throughout the tunnel.

Q6. How will penetrations be handled for existing ceilings in Linden Court A/B/C/D and hallways that will not be abated? Is the intent to reuse existing conduit and back boxes?

A6. Yes, the intent is to reuse existing conduit and back boxes.

Q7. How many mobilizations will be needed for abatement? Will there be downtime between buildings?

A7. There will need to be at least four mobilizations for abatement.

Q8. When does the work in Oak Hall and other non-Linden Court buildings need to occur?

A8. This work can occur at any time before the substantial completion date, but the priority will be Linden Court buildings.

Q9. Will the fire alarm system be disabled during abatement?

A9. No, the devices will need to be taped and bagged so they are not set off during construction.

Q10. How long is the PREA training? Is it in person or virtual?

A10. This will be a virtual training session that should be less than 20 minutes.

Q11. How will the power be turned off for the abatement contractor? Can it be locked out per floor and the abatement contractor provide and install a temporary power panel?

A11. Electrical contractor to turn off power for the abatement contractor. Electrical contractor to coordinate temporary power with abatement contractor. Panels can be locked out per floor.

Q12. Are hallway devices included in this project?

A12. Hallway devices are to be included in the project.

Q13. Can the electrician build a rack off existing racks?

A13. Electricians can use existing uni-strut rack.

Q14. Will air clearances be required for Oak Hall?

A14. Yes, as other trades will be accessing the areas following abatement, it is required.

Q15. Is power and water available at Oak Hall?

A15. There is limited power and no water available. Another addendum will be issued to clarify the power availability.

Q16. For Oak Hall, is the floor pathway that needs to be abated 5’-0” wide or 1’-0” wide?

A16. The floor tile is spec’d to be removed 5’ each side of a “center line” down the corridor or open areas for a

10’ wide work area for installation of the heat tape on the ceilings.

Q17. Will fire watch be needed when the fire alarm system is bypassed for construction?

A17. Fire alarm devices will need to be taped and bagged so they are not set off during construction.

Q18. Please clarify what furniture will be removed before the abatement contractor begins work.

A18. All furniture will be removed that is not attached to the structure.

CHANGES TO DRAWINGS

DRAWINGS:

• 09-MD200 – BASEMENT MECHANICAL DUCTWORK DEMOLITION PLAN:

o REVISE extent of ductwork demolition.

• 09-MD201 – FIRST FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN:

o ADD existing return transfer ducts and associated demolition.

o REVISE keynote 09-MD17 o ADD keynote 09-MD20

• 09-MD202 – SECOND FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN:

o ADD existing return transfer ducts and associated demolition.

o ADD tags to ducts.

o REVISE Keynote 09-MD17.

o ADD Keynote 09-MD20.

• 09-M200– BASEMENT MECHANICAL PLAN:

o REVISE supply ductwork in area B.

• 09-M201 – FIRST FLOOR MECHANICAL PLAN:

o REMOVE fire dampers between corridor and individual dorm walls.

o ADD return ductwork and fire dampers.

o ADD Keynote 09-M28.

• 09-M202 – SECOND FLOOR MECHANICAL PLAN:

o REMOVE fire dampers between corridor and individual dorm walls.

o ADD return ductwork and fire dampers.

o ADD Keynote 09-M28

• 09-M300 – THERMOSTAT PLAN:

o REVISE thermostats in Area B Basement.

• 09-M501 –MECHANICAL CONTOLS:

o ADD ERV control sequence.

o ADD heat pump control sequence.

• 13-MD200 – BASEMENT MECHANICAL DUCTWORK DEMOLITION PLAN:

o REVISE extent of ductwork demolition.

• 13-MD201 – FIRST FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN:

o ADD existing return transfer ducts and associated demolition.

o REVISE keynote 13-MD16 o ADD keynote 13-MD20

• 13-MD202 – SECOND FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN:

o ADD existing return transfer ducts and associated demolition.

o REVISE Keynote 13-MD16 o ADD Keynote 13-MD20

• 13-M200– BASEMENT MECHANICAL PLAN:

o REVISE ERV Ductwork Area D.

• 13-M201 – FIRST FLOOR MECHANICAL PLAN:

o REMOVE fire dampers between corridor and individual dorm walls.

o ADD return ductwork and fire dampers.

o ADD Keynote13-M32

• 13-M202 – SECOND FLOOR MECHANICAL PLAN:

o REMOVE fire dampers between corridor and individual dorm walls.

o ADD return ductwork and fire dampers.

o ADD Keynote 13-M32

• 13-M300 – THERMOSTAT PLAN:

o REVISE thermostats in Area D Basement.

• 13-M501 –MECHANICAL CONTOLS:

o ADD ERV control sequence.

o ADD heat pump control sequence.

• 13-M600 –MECHANICAL SCHEDULES:

o REVISE ERV schedule.

SUBSTITUTION REQUESTS

• 28 3111 Digital, Addressable Fire Alarm System – Manufacturer: Potter IPA-4000V Addressable voice notification panel – Not Approved o The fire alarm needs to be Siemens to communicate with other panels.

ATTACHMENTS

1. Pre-Bid Meeting Minutes and Sign in Sheet held on 05/15/2026.

2. Sheets 09-MD200, 09-MD201, 09-MD202, 09-M200, 09-M201, 09-M202, 09-M300, 09-M501, 13-MD200, 13-MD201, 13-MD202, 13-M200, 13-M201, 13-M202, 13-M300,13-M501, 13-M600

END OF ADDENDUM

09-MD5

A-B-1 B-B-1

A-B-2

09-MD4

09-MD5

30x12 RA

30x12 RA

09-MD5

B C F G

EDA H

09-MD9

09-MD9

09-MD9

40x10 SA

24x12 SA

20x10 SA

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

STAIRS

STAIRS

STAIRS

UNEXCAVATED UNEXCAVATED

RAMP RAMP

ELEVATOR

STAIRS

STAIRS

CORRIDOR

ELECTRICAL

B16

MECHANICAL

B04

RR

B03

STORAGE

B11

STORAGE

B13

ELEVATOR

EQUIPMENT

B19

STORAGE

B19B

ELECTRICAL

B32

STORAGE

B28

STORAGE

B22

JANITOR

B24

RESTROOM

B26

RESTROOM

B25

KITCHEN

B05

KITCHEN

B01B

STORAGE

B14A

STORAGE

B14B

CORRIDOR

B17

MECHANICAL

B18

WORK

AREA

B34

MECHANICAL

B12

RR

B09

RR

B02

MECHANICAL

B21

STORAGE

B01

WORKSHOP

B23

OFFICE

B29

STORAGE

B30

STORAGE

B27

FILE

STORAGE

B31

CORRIDOR

B33

WORK

AREA

B06

WORK

B07

LAUNDRY

B10

STORAGE

B20

JANITOR

B08

ROOM

B09A

STORAGE

B00B

STORAGE

B00A

28x10 SA

10x6

24x10 10x4

10x4

26x10

10x4

30x8

36x18

24x36

09-MD5

40x10

40x10 SA

36x24

16x6 SA12x6 SA

30x8 SA

24x36

10x6

10x8 SA

10x6 SA

24x12 SA 24x12

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:4

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

BA

SE

M

EN

T M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-MD200

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

09-MD4 REMOVE EXISTING DUCTWORK BACK TO WALL AND CAP

DUCT WITH INSULATED DUCT CAP. EXISTING LOUVER

TO REMAIN.

09-MD5 REMOVE EXISTING DUCTWORK TO EXTENT SHOWN.

EXISTING LOUVER AND PLENUM TO REMAIN. PREPARE

PLENUM FOR NEW CONNECTION.

09-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

NORTH

1/8" = 1'-0"X-76BASEMENT MECHANICAL DUCTWORK DEMOLITION PLAN

12'

AD

D xx

/x x/

AD

D -0

M

M M

M

FF

F

09-MD2 09-MD2

09-MD4 09-MD4A-1-1 B-1-1

64x16 RA64x16 RA

B C F G

EDA H

09-MD909-MD9

22x12

26x18 22x12

26x18

10ø

10ø

10ø

10ø

26x18

24x12

12x12 12x12

24x24

26x18

10ø

10ø

10ø

10ø

22x12

26x12

26x18

24x12

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

09-MD15

STAIRS

STAIRS

RAMP CORRIDOR

STAIRS

RAMP

COURTYARDCOURTYARD

ELEVATOR

STAIRS

RESTROOM

JANITOR

MECHANICAL

OFFICE

OFFICE

OFFICE

MECHANICAL

OFFICE

RESTROOM

OFFICE

RESTROOM

OFFICE

DORM

141E

DORM

141F

DORM

141D

DORM

141C

DORM

101E

DORM

101F

DORM

101G

DORM

101D

DORM

101C

DORM

101B

STORAGE

102A

RESTROOM

RESTROOM

Space

Space

LAUNDRY

LAUNDRY

ENTRY

VESTIBULE

CORRIDOR

CORRIDOR

Space

SHOWERS

LIVING

ROOM

DORM

141G

DORM

141B

OFFICE

RECEPTION

STORAGE

RESTROOM

JANITOR

RESTROOM

CORRIDOR

DORM

101H

DORM

101A

DORM

141H

DORM

141A

STORAGE

STORAGE

CORRIDOR

STORAGE

STORAGE

140A

CORRIDOR

SHOWERS

KITCHEN

LIVING

ROOM

KITCHEN

09-MD16 09-MD16

10ø

16x8

18x12 20x12

10ø

10ø

10x6

8ø

14x12

10ø

10ø10ø

10ø

10ø 10ø

10ø10ø

18x12 26x18

22x12

18x12 26x18

22x12

10ø 10ø

10ø 10ø

16x8

18x12

20x12

10x6 8ø

12x12

10ø

8ø

10ø 10ø

8ø

10ø

8ø 12x1212x12

26x18

12x12

12x12

12x12 12x12

ADD

26x26 26x26 x2

R

A26 x2

R

A

26x26

26x26

26x26 26x26 x2

R

A x2

R

A

09-MD17

09-MD17

09-MD20 09-MD20

09-MD2009-MD20

ADD

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:4

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

FI

R

ST

F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-MD201

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

09-MD2 DEMOLISH EXISTING DUCT HEATING COIL AND

DUCTWORK INSIDE THE MECHANICAL ROOM.

09-MD4 REMOVE EXISTING DUCTWORK BACK TO WALL AND CAP

DUCT WITH INSULATED DUCT CAP. EXISTING LOUVER

TO REMAIN.

09-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

09-MD15 REMOVE SECTION OF DUCTWORK FOR INSTALLATION

OF NEW FIRE DAMPER. SEE NEW WORK PLANS.

09-MD16 REMOVE EXISTING KITCHEN TRANSFER DUCT AND

GRILLE. INFILL AND PAINT WALL TO MATCH ADJACENT

WALL COLOR.

09-MD17 DEMOLISH EXISTING RETURN DUCT TO APPROXIMATE

EXTENT INDICATED. DESIGN INTENT IS TO DEMOLISH

RETURN DUCTWORK WHERE CEILING REPLACEMENT

AND ABATEMENT IS OCCURRING. EXISTING RETURN

DUCT SIZING IS SHOWN AS AN APPROXIMATION BASED

ON EXISTING DRAWINGS. CONTRACTOR SHALL VERIFY

EXISTING DUCTWORK SIZING PRIOR TO FABRICATING

NEW CONNECTED DUCTWORK.

09-MD20 DEMOLISH PORTION OF EXISTING RETURN DUCT AS

INDICATED BACK TO WALL AND PREPARE DUCT FOR

NEW CONNECTION. VERIFY TERMINATION POINT AND

NOTIFY ENGINEER IF TERMINATION POINT DIFFERS

FROM ANTICIPATED LOCATION.

NORTH

1/8" = 1'-0"A6 FIRST FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN

12'

AD

D xx

/x x/

AD

D -0

ADD

ADD

ADD

09-MD209-MD2

09-MD4

09-MD4 B-2-1

A-2-1

60x20 RA 60x20 RA

B C F G

EDA H

09-MD9

09-MD9

22x12

26x18 22x12

26x18

09-MD11

09-MD11

10ø

10ø

10ø

10ø

24x24

26x18

26x18 24x12

12x13

26x18 24x12

12x12

10ø

10ø

10ø

8ø

24x24

26x18

22x12

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

12x12

12x13

09-MD1509-MD15

OPEN TO BELOW

OPEN TO BELOW

STAIRS STAIRS

STAIRSSTAIRS

ELEVATOR

STORAGE

MECHANICAL

OFFICE

OFFICE

OFFICE

RR

MEDICAL

SUPPLIES

RR

OFFICE

DORM

239D

DORM

209E

DORM

209D

DORM

209H

DORM

209C

DORM

209B

DORM

209F

DORM

209G DORM

239B

DORM

239C

DORM

239E

DORM

239F

DORM

239G

LAUNDRY

RR

MECHANICAL

OFFICE

STORAGE

STORAGE

208A

LAUNDRY

CORRIDOR

STORAGE

RR

RECEPTION

RESTROOM

JANITOR

SHOWERS

RESTROOM

CORRIDOR

KITCHEN

DORM

209A

RECEPTION

STORAGE

OFFICE

JANITOR

RESTROOM

SHOWERS

KITCHEN

229A

KITCHEN

STORAGE

STORAGE

LIVING

ROOM

DORM

239A

LIVING

ROOM

DORM

239H

CORRIDOR

09-MD16

09-MD16

26x18 18x12

22x12

10ø

26x18

14x12

20x12

10ø10ø

16x810x6

8ø

18x12

8ø

8ø

12x12 12x12

8ø8ø

10ø 10ø

8ø

10ø

18x12

ADD 01

ADD

ADD

09-MD17

09-MD20 09-MD20

x2

R

A 26x26

26x26 x2

R

A x2

R

A x2

09-MD17

x2

R

A

26x26 26x26

09-MD20

09-MD20

x2

12x12 12x12

8ø

10ø

10ø

8ø8ø

10ø

8ø

10ø

ADD

ADD

ADD

ADD

ADD

ADD

ADD

ADD

ADD

ADD

ADD

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:5

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

SE

C

O N

D F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-MD202

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

09-MD2 DEMOLISH EXISTING DUCT HEATING COIL AND

DUCTWORK INSIDE THE MECHANICAL ROOM.

09-MD4 REMOVE EXISTING DUCTWORK BACK TO WALL AND CAP

DUCT WITH INSULATED DUCT CAP. EXISTING LOUVER

TO REMAIN.

09-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

09-MD11 DEMOLISH EXISTING DUCTWORK AND ACCESSORIES IN

THIS LOCATION. PREPARE DUCTWORK FOR NEW VAV

AND DUCTWORK INSTALLATION.

09-MD15 REMOVE SECTION OF DUCTWORK FOR INSTALLATION

OF NEW FIRE DAMPER. SEE NEW WORK PLANS.

09-MD16 REMOVE EXISTING KITCHEN TRANSFER DUCT AND

GRILLE. INFILL AND PAINT WALL TO MATCH ADJACENT

WALL COLOR.

09-MD17 DEMOLISH EXISTING RETURN DUCT TO APPROXIMATE

EXTENT INDICATED. DESIGN INTENT IS TO DEMOLISH

RETURN DUCTWORK WHERE CEILING REPLACEMENT

AND ABATEMENT IS OCCURRING. EXISTING RETURN

DUCT SIZING IS SHOWN AS AN APPROXIMATION BASED

ON EXISTING DRAWINGS. CONTRACTOR SHALL VERIFY

EXISTING DUCTWORK SIZING PRIOR TO FABRICATING

NEW CONNECTED DUCTWORK.

09-MD20 DEMOLISH PORTION OF EXISTING RETURN DUCT AS

INDICATED BACK TO WALL AND PREPARE DUCT FOR

NEW CONNECTION. VERIFY TERMINATION POINT AND

NOTIFY ENGINEER IF TERMINATION POINT DIFFERS

FROM ANTICIPATED LOCATION.

NORTH

1/8" = 1'-0"A6 SECOND FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN

12'

AD

D xx

/x x/

AD

D -0

B

B

C

C

F

F

G

G

E

E

D

D

A

A

H

H

F-A-2

EUH-A-B-1 EUH-B-B-1

F-A-1

F-B-1

40x10 SA

40x10 SA

24x12 SA

20x20 SA

20x18 SA

20x10 SA 20x18 SA

09-M02 09-M0218x12 SA

09-M03

09-M03

09-M03 EUH-A-B-3

4ø FEA 4ø CA

4ø CA

200 CFM

200 CFM

200 CFM

200 CFM

85 CFM

0 CFM

85 CFM

115 CFM

150 CFM

150 CFM

35 CFM

130 CFM

95 CFM

95 CFM

95 CFM

80 CFM

10x8 SA 10x8 SA

10x8 SA

14x10 SA

10x8 SA

12x8 SA

10x6 SA

12x10 SA

14x10 SA

14x12 SA

16x12 SA

12x6 SA 16x6 SA

28x10 SA

105 CFM

105 CFM

105 CFM

105 CFM

200 CFM

200 CFM

200 CFM

200 CFM

100 CFM

100 CFM

100 CFM

100 CFM

100 CFM

120 CFM

120 CFM

120 CFM

310 CFM310 CFM

36x18

DUCT ROUTING IS BASED ON RECORD DRAWINGS AND DIFFUSER

LOCATIONS ON SITE. FIELD VERIFY LOCATION OF DUCTWORK PRIOR TO

PERFORMING WORK.

AIRFLOWS SHOWN ON PLANS ARE ASSUMED AIRFLOWS BASED ON

EXISTING RECORD DRAWINGS.

4ø FEA 4ø CA NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

EUH-AB-ST1 EUH-AB-ST209-M03 09-M03

3/4" RS UP

3/8" RL UP

3/4" RS UP

3/8" RL UP

3/4" RS UP

3/8" RL UP

3/4" COND

3/4" COND DN

3/4" COND DN

3/4" COND DN

09-M12

4ø CA 4ø FEA

4ø FEA

09-M17

09-M15

3/4" COND

3/4" COND

3/4" COND DN

09-M12

3/4" COND

3/4" COND DN

09-M16

09-M16

09-M17

09-M17

FLUE AND COMBUSTION TERMINATION DUCTWORK TO BE TERMINATED AT

LEAST 4'-0" ABOVE GRADE (TYP.).

200 CFM

09-M20

09-M20

09-M20

09-M20

09-M2009-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20 09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M2009-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20

09-M20 09-M20

C.O.

C.O.

C.O.

18x20 RA

SG-D

6x6

SG-D

6x6

8x6 SA

6x6 SA 6x6 SA

Space

ELECTRICAL

B16

MECHANICAL

B04

RR

B03

STORAGE

B11

STORAGE

B13

ELEVATOR

EQUIPMENT

B19

STORAGE

B19B

ELECTRICAL

B32

STORAGE

B28

STORAGE

B22

JANITOR

B24

RESTROOM

B26

RESTROOM

B25

KITCHEN

B05

KITCHEN

B01B

STORAGE

B14A

STORAGE

B14B

CORRIDOR

B17

MECHANICAL

B18

WORK

AREA

B34

MECHANICAL

B12

RR

B09

RR

B02

MECHANICAL

B21

MECH.

B01A

Space

STORAGE

B01

WORKSHOP

B23

OFFICE

B29

STORAGE

B30

STORAGE

B27

FILE

STORAGE

B31

CORRIDOR

B33

WORK

AREA

B06

WORK

B07

LAUNDRY

B10

STORAGE

B20

Space

JANITOR

B08

ROOM

B09A

STORAGE

B00B

STORAGE

B00A

STAIRS

STAIRS

STAIRS

UNEXCAVATED

RAMP RAMP

UNEXCAVATED

ELEVATOR

STAIRS

STAIRS

CORRIDOR

HP-B-1

H P-

B-

46x8 OA

ERV-B-1

8x10 SA

10x8 OA

10x6 RA

10x8 RA

8x6 RA

8x8 OA

RG-E

12x6

RG-E

8x8

09-M22

09-M24

09-M23

RG-E

14x8

09-M22

8ø OA

8ø OA

8x6 RA

10ø RA

RG-E

12x8

105 CFM

65 CFM

65 CFM

10x6 RA

18x12 RA

8x8 RA

16x8 RA

16x8 RA

18x18 RA

RG-E

16x8

560 RG-E

16x8

09-M20

RG-E

24x8

12x6 TA

RG-E

8x6

CD-A

10ø

CD-A

10ø

10ø SA

16x10 SA

350 CFM

350 CFM

10x6 RA

RG-E

10x6

CD-B

14x6

CD-B

14x6

RG-E

18x8

8x6 SA

46x8 OA 30x8 SA

18x6 SA

22x10 SA

RG-E

10x6

22x10 RA

RG-E

10x6

RG-E

10x4

RG-E

10x4

RG-E

10x6

RG-B

22x22

TYP.4

09-M25

09-M26

09-M27

09-M27

10x8 EA

09-M26

RG-B

22x22

16x12 RA

3/8" RL

3/4" RS 09-M02

10x6 RA

RG-E

10x6

RG-E

10x6

09-M20

09-M20

09-M20

12x8 RA

09-M02

09-M02

3/8" RL UP

3/4" RS UP

09-M02

09-M02

ADD

ADD

RG-E

16x16

18x18 RA

ADD

ADD

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:3

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

BA

SE

M

EN

T M

EC

H

AN

IC

AL

D

U C

TW

O

R K

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-M200

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

NORTH

1/8" = 1'-0"A6 BASEMENT MECHANICAL DUCTWORK PLAN

12'

KEYNOTES

KEY NOTE

09-M02 REFRIGERANT PIPING SIZE AND ROUTING SHOWN IS AN

APPROXIMATION. EXACT SIZING AND ROUTING SHALL

BE IN ACCORDANCE WITH MANUFACTURER'S WRITTEN

INSTRUCTIONS.

09-M03 NEW ELECTRIC UNIT HEATER TO BE SURFACE

MOUNTED ON WALL PER MANUFACTURER'S

INSTRUCTIONS. MOUNT UNIT HEATERS BOTTOM TO BE

APPROX 0'-6" AFF.

09-M12 ROUTE CONDENSATE PIPING FROM CONDENSATE

PUMP TO JANITOR'S CLOSET. TERMINATE PIPING AT

THE NEAREST FIXTURE IN JANITOR CLOSET.

09-M15 DESIGN INTENT IS TO USE EXISTING WINDOW OR

PREVIOUSLY INFILLED WINDOW FOR THE WALL

PENETRATION. FIELD VERIFY EXACT PENETRATION

LOCATION PRIOR TO INSTALLATION.

09-M16 PIPE ROUTING SHOWN IS THE INTENDED CONDENSATE

PIPE ROUTING. FIELD VERIFY EXACT PIPE ROUTING

PRIOR TO INSTALLATION.

09-M17 EXTEND FLUE AND COMBUSTION AIR THROUGH WALL

TO EXTERIOR. SLEEVE PENETRATIONS AND SEAL

WEATHERTIGHT. REFER TO FURNACE

MANUFACTURER'S WRITTEN INSTRUCTIONS FOR FLUE

AND COMBUSTION VENTING REQUIREMENTS AND

TERMINATION DETAILS.

09-M20 REBALANCE EXISTING DIFFUSER/GRILLE TO CFM

SHOWN.

09-M22 CONNECT NEW OA INTAKE DUCT TO EXISTING LOUVER

PLENUM. BALANCE OA INTAKE TO 200 CFM.

09-M23 ROUTE RETURN DUCT UP THROUGH SPACE IN

STRUCTURE. OFFSET DUCT AROUND EXISTING PIPING

AS REQUIRED.

09-M24 EXISTING DUCT IS CAPPED.

09-M25 BALANCE OA BRANCH TO 100 CFM.

09-M26 BALANCE OA BRANCH TO 150 CFM.

09-M27 EXTEND LOUVER PLENUM AS REQUIRED FOR

CONNECTION TO NEW VENTILATION DUCT.

AD

D xx

/x x/

AD

D

FFF FF F F F

C3 09-M400

VAV-A-1W VAV-B-1E

AHU-B

AHU-A

F3 09-M400

C6 09-M400

E6 09-M400

A3 09-M400

A6 09-M400

ACCU-A-2

EUH-A-1-2 EUH-B-1-2

EUH-A-1-1 EUH-B-1-1

EUH-A-1-3 EUH-B-1-3

B C F G

EDA H

ACCU-A-1

ACCU-B-2

ACCU-B-1

09-M04

09-M04

09-M04

EUH-B-1-4

09-M03

09-M03 09-M03

09-M03

09-M03

09-M03 09-M03

EUH-A-1-5

EUH-A-1-4

09-M03

09-M03

09-M0809-M08

12x4 SA

12x4 SA

24x6 SA

16ø SA

100 CFM

340 CFM

100 CFM

285 CFM

100 CFM

DUCT ROUTING IS BASED ON RECORD DRAWINGS AND DIFFUSER

LOCATIONS ON SITE. FIELD VERIFY LOCATION OF DUCTWORK PRIOR TO

PERFORMING WORK.

AIRFLOWS SHOWN ON PLANS ARE ASSUMED AIRFLOWS BASED ON

EXISTING RECORD DRAWINGS.

VAV-A-101

VAV-A-116

VAV-A-112

VAV-B-131

VAV-B-141

VAV-B-126

26x26 SA

CD-A

10ø

TYP.4

26x26 SA

20x14 SA

18x14 SA

14x14 SA

10ø SA

CD-A

10ø

TYP.4

20x14 SA

18x12 SA

14x12 SA

10ø SA

48x32 SA

09-M10

09-M11

09-M10

09-M11

18x18 SA

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

EUH-AB-3

09-M03

EUH-AB-2

EUH-AB-1

3/8" RL

3/4" RS

3/8" RL

3/4" RS

3/4" RS

3/8" RL

09-M03 09-M03

09-M19 09-M19

16ø SA

RESTROOM

JANITOR

MECHANICAL

OFFICE

OFFICE

OFFICE

MECHANICAL

OFFICE

RESTROOM

OFFICE

RESTROOM

OFFICE

DORM

141E

DORM

141F

DORM

141D

DORM

141C

DORM

101G

DORM

101C

DORM

101B

RESTROOM

RESTROOM

LAUNDRY

LAUNDRY

ENTRY

VESTIBULE

CORRIDOR

CORRIDOR

SHOWERS

LIVING

ROOM

DORM

141G

DORM

141B

OFFICE

RECEPTION

STORAGE

RESTROOM

JANITOR

RESTROOM

CORRIDOR

DORM

101H

DORM

101A

DORM

141H

DORM

141A

STORAGE

STORAGE

CORRIDOR

STORAGE

STORAGE

140A

SHOWERS

KITCHEN

LIVING

ROOM

KITCHEN

STAIRS

STAIRS

COURTYARD COURTYARD

ELEVATOR

STAIRS

STAIRS

RAMP RAMP CORRIDOR

DORM

101E

DORM

101F

DORM

101D

CORRIDOR

CORRIDOR

09-M06 09-M06

CD-A

8ø

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

LD-F

48x2.75

CD-A

8ø

140 LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

CD-A

12ø

CD-A

10ø

CD-A

10ø

CD-A

10ø

TYP.4

18x16 SA 16x14 SA

12x12 SA

10ø SA

10ø SA 10ø SA10ø SA

12ø SA

10ø SA

09-M20

09-M20

09-M20

100 CFM

26x18 SA

18x14 SA

12ø SA 16x12 SA

14x14 SA 14x14 SA

12x12 SA 12x12 SA

10ø SA10ø SA6ø SA 6ø SA

10ø SA 6ø SA10ø SA6ø SA

10ø SA

6ø SA

10ø SA6ø SA

10ø SA

10ø SA 6ø SA

6ø SA

26x18 SA 20x18 SA

26x26 SA 20x18 SA

09-M20

09-M20

09-M20

CD-A

10ø

CD-A

10ø

CD-A

10ø

CD-A

12ø

CD-A

12ø

12ø SA 14x10 SA

10ø SA

14x12 SA

16x14 SA

16x12 SA 12ø SA

14x14 SA 14x14 SA

12x12 SA 12x12 SA

18x14 SA 26x18 SA

20x18 SA 26x18 SA

RG-B

22x22

RG-B

22x22

RG-B

22x22

RG-B

22x22

CD-A

8ø

170 CD-A

8ø

CD-A

12ø

CD-A

12ø

CD-A

8ø

180LD-F

48x2.75

LD-F

48x2.75

70 CD-A

8ø

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

180 LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

ACCU-B-3

09-M04

09-M04

ADD

ADD

ADD

ADD

ADD

ADD

ADD

ADD

x2

R

A x2

R

A

26x26 RA 26x26 RA x2

R

A x2

R

A x2

R

A x2

R

A

09-M28

09-M28

09-M28 09-M28

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:3

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

FI

R

ST

F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-M201

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

NORTH

1/8" = 1'-0"A6 FIRST FLOOR MECHANICAL DUCTWORK PLAN

12'

KEYNOTES

KEY NOTE

09-M03 NEW ELECTRIC UNIT HEATER TO BE SURFACE

MOUNTED ON WALL PER MANUFACTURER'S

INSTRUCTIONS. MOUNT UNIT HEATERS BOTTOM TO BE

APPROX 0'-6" AFF.

09-M04 ACCU TO BE WALL MOUNTED PER MANUFACTURER'S

INSTRUCTIONS WITH MANUFACTURER PROVIDED

MOUNTING BRACKETS.

09-M06 REFER TO DETAIL G5 ON SHEET M500 FOR FIRE

DAMPER DETAIL.

09-M08 INSTALL SUPPLY AND RETURN DUCTS THROUGH

EXISTING OPENING FROM DEMOLISHED LOUVER. SEE

ARCHITECTURAL DRAWINGS FOR FLASHING AND

SEALING REQUIREMENTS.

09-M10 NEW AHU TO BE GROUND MOUNTED ON NEW

EQUIPMENT PAD.

09-M11 NEW ELECTRIC REHEAT VAV TO BE INSTALLED IN THE

EXISTING MECHANICAL ROOMS. EXISTING OA LOUVER

PENETRATION TO BE RE-USED TO ROUTE DUCTWORK

OUTSIDE.

09-M19 NEW RETURN DUCTWORK TO DRAW AIR FROM

EXISTING PLENUM RETURN DUCTWORK AND

MECHANICAL ROOM. TERMINATE RA OPENING IN ROOM

WITH 3/4" HARDWARE CLOTH.

09-M20 REBALANCE EXISTING DIFFUSER/GRILLE TO CFM

SHOWN.

09-M28 EXTEND EXISTING DUCT PAST NEW FIREWALL AND

INSTALL FIRE DAMPER. TERMINATE ABOVE CEILING

AFTER FIRE DAMPER.

AD

D xx

/x x/

AD

D -0

F FF F

F FFF

C3 09-M400

VAV-A-2W

VAV-B-2E

F3 09-M400

C6 09-M400

E6 09-M400

A6 09-M400

A3 09-M400

EUH-A-2-2

EUH-B-2-2

EUH-A-2-3 EUH-B-2-3

EUH-B-2-1EUH-A-2-1

B C F G

EDA H

32x30 SA

30x32 SA DN 30x32 SA DN

09-M03

09-M03 09-M03

09-M0309-M03

09-M03

EUH-B-2-4

09-M03

09-M08 09-M08

12x4 SA

100 CFM

100 CFM

455 CFM

100 CFM

100 CFM

12x4 SA

290 CFM

DUCT ROUTING IS BASED ON RECORD DRAWINGS AND DIFFUSER

LOCATIONS ON SITE. FIELD VERIFY LOCATION OF DUCTWORK PRIOR TO

PERFORMING WORK.

AIRFLOWS SHOWN ON PLANS ARE ASSUMED AIRFLOWS BASED ON

EXISTING RECORD DRAWINGS.

16ø SA

VAV-A-209

VAV-A-214

VAV-A-216

VAV-B-229

VAV-B-239

VAV-B-228

20x14 SA

CD-A

10ø

TYP.4

18x12 SA

14x12 SA

10ø SA

16x14 SA 16x14 SA

20x18 SA

18x16 SA

16x12 SA

12ø SA

CD-A

12ø

TYP.4

32x30 SA

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

09-M06 09-M06

09-M1909-M19

OPEN TO BELOWOPEN TO BELOW

STORAGE

MECHANICAL

OFFICE

OFFICE

OFFICE

RR

MEDICAL

SUPPLIES

RR

OFFICE

DORM

239D

DORM

209E

DORM

209D

DORM

209H

DORM

209C

DORM

209B

DORM

209F

DORM

209G

DORM

239B

DORM

239C

DORM

239E

DORM

239F

DORM

239G

Space

Space

LAUNDRY

RR

MECHANICAL

OFFICE

STORAGE

LAUNDRY

CORRIDOR

STORAGE

RR

RECEPTION

ELEVATOR

217RESTROOM

JANITOR

SHOWERS

RESTROOM

CORRIDOR

KITCHEN

DORM

209A

RECEPTION

STORAGE

OFFICE

JANITOR

RESTROOM

SHOWERS

KITCHEN

229A

KITCHEN

STORAGE

LIVING

ROOM

DORM

239A

LIVING

ROOM

DORM

239H

CORRIDOR

STAIRS

STAIRS STAIRS

STAIRS

RAMP RAMP

12ø SA

16ø SA

RG-B

22x22

RG-B

22x22 RG-B

22x22

RG-B

22x22

12ø SA

18x14 SA 26x18 SA

CD-A

10ø

CD-A

10ø

TYP.4

CD-A

10ø

10ø SA

26x18 SA26x26 SA

CD-A

12ø

CD-A

10ø

26x18 SA 26x26 SA

CD-A

12ø

12ø SA

10ø SA

18x12 SA 26x18 SA

14ø SA

14x12 SA 16x14 SA

CD-A

12ø

CD-A

12ø

10ø SA

22x12 SA 26x18 SA

CD-A

8ø

LD-F

48x2.75

CD-A

10ø

CD-A

10ø

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

100CD-A

8ø

CD-A

8ø

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

CD-A

8ø

CD-A

8ø

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

LD-F

48x2.75

CD-A

8ø

CD-A

8ø

CD-A

8ø

CD-A

8ø

CD-A

8ø

10ø SA

10ø SA6ø SA

6ø SA

6ø SA 10ø SA

10ø SA

6ø SA

12x12 SA 12x12 SA

12x12 SA

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

16x12 SA

14ø SA

18x16 SA 16x14 SA 12x12 SA

10ø SA

12x12 SA

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

RG-C

22x10

CD-A

12ø

CD-A

12ø

ADD 01

ADD

ADD

ADD

ADD

ADD

ADD

ADD

26x26 RA x2

R

A x2

R

A

09-M28 09-M28

09-M28 x2

R

A x2

R

A x2

R

A x2

R

A

09-M28

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

4:

:3

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

SE

C

O N

D F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-M202

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

NORTH

1/8" = 1'-0"A6 SECOND FLOOR MECHANICAL DUCTWORK PLAN

12'

KEYNOTES

KEY NOTE

09-M03 NEW ELECTRIC UNIT HEATER TO BE SURFACE

MOUNTED ON WALL PER MANUFACTURER'S

INSTRUCTIONS. MOUNT UNIT HEATERS BOTTOM TO BE

APPROX 0'-6" AFF.

09-M06 REFER TO DETAIL G5 ON SHEET M500 FOR FIRE

DAMPER DETAIL.

09-M08 INSTALL SUPPLY AND RETURN DUCTS THROUGH

EXISTING OPENING FROM DEMOLISHED LOUVER. SEE

ARCHITECTURAL DRAWINGS FOR FLASHING AND

SEALING REQUIREMENTS.

09-M19 NEW RETURN DUCTWORK TO DRAW AIR FROM

EXISTING PLENUM RETURN DUCTWORK AND

MECHANICAL ROOM. TERMINATE RA OPENING IN ROOM

WITH 3/4" HARDWARE CLOTH.

09-M28 EXTEND EXISTING DUCT PAST NEW FIREWALL AND

INSTALL FIRE DAMPER. TERMINATE ABOVE CEILING

AFTER FIRE DAMPER.

AD

D xx

/x x/

AD

D -0

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

B C F G

EDA H

EUH-A-1-3

VAV-A-112

VAV-A-1W

ACCU-A-1

AHU-A

VAV-A-116

VAV-A-101

ACCU-A-2

EUH-A-1-1

EUH-A-1-4

EUH-A-1-5

EUH-B-1-2EUH-A-1-2

EUH-AB-1

EUH-B-1-4

EUH-AB-2

EUH-AB-3

VAV-B-126

VAV-B-141

EUH-B-1-1

ACCU-B-2

AHU-BACCU-B-1

VAV-B-1EEUH-B-1-3

VAV-B-131

ELECTRIC CABINET UNIT HEATER TO BE

INSTALLED WITH FACTORY MOUNTED

INTEGRAL THERMOSTAT. TYPICAL OF ALL

CABINET UNIT HEATERS ON PLAN. REFER

TO SCHEDULES FOR MORE DETAIL.

B

B

C

C

F

F

G

G

E

E

D

D

A

A

H

H

F-A-2

EUH-A-B-1 EUH-B-B-1

F-A-1 F-B-1

EUH-A-B-3

EUH-AB-ST1 EUH-AB-ST2

ACCU-A-1

EUH-AB-2

EUH-AB-3

ELECTRIC CABINET UNIT

HEATER TO BE

INSTALLED WITH

FACTORY MOUNTED

INTEGRAL THERMOSTAT.

TYPICAL OF ALL CABINET

UNIT HEATERS ON PLAN.

REFER TO SCHEDULES

FOR MORE DETAIL.

HP-B-1

HP-B-2

ADD

ADD

ADD

B C F G

EDA H

VAV-A-2W

VAV-B-2E

EUH-A-2-2 EUH-B-2-2

EUH-A-2-3 EUH-B-2-3

EUH-B-2-1EUH-A-2-1

EUH-B-2-4

VAV-A-209

VAV-A-214

VAV-A-216

VAV-B-229

VAV-B-239

VAV-B-228

ELECTRIC CABINET UNIT HEATER TO BE

INSTALLED WITH FACTORY MOUNTED

INTEGRAL THERMOSTAT. TYPICAL OF ALL

CABINET UNIT HEATERS ON PLAN. REFER

TO SCHEDULES FOR MORE DETAIL.

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

9-

LI

N D

EN

A

/B

5/

/2

3:

:3

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

TH

ER

M O

ST

AT

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

09-M300

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

NORTH

1/16" = 1'-0"D4 FIRST FLOOR THERMOSTAT PLAN

24'

NORTH

1/16" = 1'-0"D6 BASEMENT THERMOSTAT PLAN

24'0

NORTH

1/16" = 1'-0"A6 SECOND FLOOR THERMOSTAT PLAN

24'

AD

D xx

/x x/

AD

D

1. ELECTRIC UNIT HEATER

RUN CONDITIONS - SCHEDULED:

THE UNIT SHALL RUN ACCORDING TO A USER DEFINABLE TIME SCHEDULE IN THE FOLLOWING

MODES:

• OCCUPIED MODE: THE UNIT SHALL MAINTAIN A HEATING SETPOINT OF 70°F (ADJ.).

• UNOCCUPIED MODE (NIGHT SETBACK): THE UNIT SHALL MAINTAIN A HEATING SETPOINT

OF 65°F (ADJ.).

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• LOW ZONE TEMP: IF THE ZONE TEMPERATURE IS LESS THAN THE HEATING SETPOINT BY

A USER DEFINABLE AMOUNT (ADJ.).

FAN:

THE FAN SHALL RUN ANYTIME THE ZONE TEMPERATURE IS BELOW HEATING SETPOINT, UNLESS

SHUTDOWN ON SAFETIES. THE FAN SPEEDS SHALL BE INDEXED AS FOLLOWS:

• LOW SPEED SHALL RUN ANYTIME THE ZONE TEMPERATURE DROPS BELOW SETPOINT.

• HIGH SPEED SHALL RUN ANYTIME THE ZONE TEMPERATURE DROPS EVEN FURTHER

BELOW SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).

THE FAN SHALL RUN FOR A USER DEFINED PERIOD OF TIME AFTER THE HEATING ELEMENT IS

INDEXED OFF TO DISSPATE HEAT OFF THE HEATING ELEMENT.

ELECTRIC HEATING STAGES:

THE CONTROLLER SHALL MEASURE THE ZONE TEMPERATURE AND STAGE THE HEATING TO

MAINTAIN ITS HEATING SETPOINT. TO PREVENT SHORT CYCLING, THERE SHALL BE A USER

DEFINABLE (ADJ.) DELAY BETWEEN STAGES, AND EACH STAGE SHALL HAVE A USER DEFINABLE

(ADJ.) MINIMUM RUNTIME.

DISCHARGE AIR TEMPERATURE:

THE CONTROLLER SHALL MONITOR THE DISCHARGE AIR TEMPERATURE.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• HIGH DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE IS GREATER THAN

120°F (ADJ.).

• LOW DISCHARGE AIR TEMP: IF THE DISCHARGE AIR TEMPERATURE IS LESS THAN 45°F

(ADJ.).

FAN STATUS:

THE CONTROLLER SHALL MONITOR THE FAN STATUS.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• FAN FAILURE: COMMANDED ON, BUT THE STATUS IS OFF.

• FAN IN HAND: COMMANDED OFF, BUT THE STATUS IS ON.

ELEC

BO - HEATING ELEMENT STAGE 1

BO - FAN LOW SPEED

BO - FAN HIGH SPEED

BI - FAN STATUS

AI - ZONE TEMP

CT

M

T

BO - HEATING ELEMENT STAGE 2

1.

SEQUENCE OF OPERATIONS: GAS FURNACE, DX COOLING SYSTEM

THERMOSTAT CONTROLLED OPERATIONS

RUN CONDITIONS - SCHEDULED:

THE UNIT SHALL RUN ACCORDING TO A USER DEFINABLE TIME SCHEDULE IN THE FOLLOWING MODES:

OCCUPIED MODE: THE UNIT SHALL MAINTAIN

A 75°F (ADJ.) COOLING SETPOINT

A 70°F (ADJ.) HEATING SETPOINT.

UNOCCUPIED MODE (NIGHT SETBACK): THE UNIT SHALL MAINTAIN

A 78°F (ADJ.) COOLING SETPOINT.

A 65°F (ADJ.) HEATING SETPOINT.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

HIGH ZONE TEMP: IF THE ZONE TEMPERATURE IS GREATER THAN THE COOLING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).

LOW ZONE TEMP: IF THE ZONE TEMPERATURE IS LESS THAN THE HEATING SETPOINT BY A USER DEFINABLE AMOUNT (ADJ.).

ZONE SETPOINT ADJUST:

THE OCCUPANT SHALL BE ABLE TO ADJUST THE ZONE TEMPERATURE HEATING AND COOLING SETPOINTS AT THE ZONE SENSOR. THE SETPOINT ADJUSTMENT RANGE SHALL BE LIMITED BETWEEN THE EFFECTIVE TEMPERATURE RANGE OF 68F-76F. ZONE SETPOINT ADJUSTMENT SHALL OVERRIDE TEMPERATURE FOR 2 HOURS (ADJ.). AFTER TIME

EXPIRES ZONE SETPOINT RETURNS TO SCHEDULED SETPOINT.

ZONE UNOCCUPIED OVERRIDE:

A TIMED LOCAL OVERRIDE CONTROL SHALL ALLOW AN OCCUPANT TO OVERRIDE THE SCHEDULE AND PLACE THE UNIT INTO AN OCCUPIED MODE FOR 2 HOURS (ADJ.). AT THE EXPIRATION OF THIS TIME, CONTROL OF THE UNIT SHALL AUTOMATICALLY RETURN TO THE SCHEDULED SETPOINT.

SUPPLY FAN: ON - OFF

THE SUPPLY FAN SHALL RUN ANYTIME THE UNIT IS IN OCCUPIED MODE. THE SPEED OF THE SUPPLY FAN SHALL BE CONTROLLED BY THE FURNACE CONTROLLER. THE

OUTDOOR AIR DAMPER SHALL BE OPEN ANYTIME THE SUPPLY FAN IS IN OPERATION.

COOLING OPERATION:

THE CONTROLLER SHALL MEASURE THE ZONE TEMPERATURE AND STAGE THE COOLING TO MAINTAIN ITS COOLING SETPOINT. TO PREVENT SHORT CYCLING, THERE SHALL BE A TIME DELAY BETWEEN STARTUP OF THE ACCU AND SHUTDOWN OF THE ACCU. INTENTION IS FOR THIS TO BE DONE VIA THE CONTROL BOARD. THIS CAN BE DONE VIA

THE THERMOSTAT AS WELL.

ZONE HUMIDITY:

THE CONTROLLER SHALL MONITOR THE ZONE HUMIDITY.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

HIGH ZONE HUMIDITY: IF THE ZONE HUMIDITY IS GREATER THAN 70% (ADJ.).

LOW ZONE HUMIDITY: IF THE ZONE HUMIDITY IS LESS THAN 35% (ADJ.).

DEHUMIDIFICATION:

THE CONTROLLER SHALL MEASURE THE ROOM AIR HUMIDITY AND OVERRIDE THE COOLING SEQUENCE TO MAINTAIN THE ROOM AIR HUMIDITY AT OR BELOW 60% RH (ADJ.).

DEHUMIDIFICATION SHALL BE ENABLED WHENEVER THE UNIT IS IN OCCUPIED MODE. COOLING SYSTEM IS TO BE ALLOWED TO COOL 3°F BELOW SETPOINT TO MAINTAIN

ROOM HUMIDITY SETPOINT.

HARD WIRED SAFETIES

FREEZE PROTECTION:

THE UNIT SHALL SHUT DOWN AND GENERATE AN ALARM UPON RECEIVING A FREEZESTAT STATUS. OA DAMPER SHALL CLOSE.

FURNCACE CONTROL BOARD OPERATIONS

GAS HEATING STAGES:

THE INTERNAL FURNACE CONTROLLER SHALL CONTROL THE BURNER STAGING OPERATIONS.

GAS

BO - HEATING STAGE 1

BO - HEATING STAGE 2

DX

BO - COOLING STAGE 1

BO - COOLING STAGE 2

SARA

AI - ZONE HUMIDITY

BI - ZONE OVERRIDE

AI - ZONE SETPOINT ADJUST

AI - ZONE TEMP

H

T

ECM

BI - SUPPLY FAN STATUS

M

CT

AO - DISCHARGE AIR TEMPERATURE

T

BO - SUPPLY FAN START/STOP

OA BALANCING DAMPER

OA

RA BALANCING DAMPER

EA

EF

AI - DISCHARGE AIR TEMP

AI - OUTSIDE AIR TEMP

RA

EA

AO - OUTSIDE AIR DAMPER

AI - OUTSIDE AIR DAMPER STATUS

N.C.

OA

BI - SUPPLY FAN START/STOP

BI - SUPPLY FAN STATUS

SF

BO - EXHAUST FAN START/STOP

BI - EXHAUST FAN STATUS

SA

M

CT

T

S

M

CT

TOTAL ENERGY RECOVERY CORE

AO - EXHAUST AIR DAMPER

AI - EXHAUST AIR DAMPER STATUS

N.C.

S

ENERGY RECOVERY VENTILATOR:

Run Conditions - Scheduled:

The unit shall run according to a user definable time schedule in the following modes:

Occupied Mode: The OUTDOOR AIR DAMPER SHALL OPEN AND THE UNIT SHALL RUN CONSTANTLY DURING SCHEDULED OCCUPIED HOURS. THE OCCUPIED HOURS SCHEDULE SHALL MATCH THAT OF THE ASSOCIATED FAN COIL UNITS AND FURNACES.

Unoccupied Mode: THE OUTDOOR AIR DAMPER SHALL CLOSE AND THE UNIT SHALL TURN OFF DURING UNOCCUPIED HOURS.

Fan:

The fan shall run anytime the unit is commanded to run, unless shutdown on safeties.

Filter Differential Pressure Monitor:

The controller shall monitor the differential pressure across the filter.

Alarms shall be provided as follows:

Filter Change Required: Filter differential pressure exceeds a user definable limit (adj.).

Fan Status:

The controller shall monitor the fan status.

Alarms shall be provided as follows:

Fan Failure: Commanded on, but the status is off.

Fan in Hand: Commanded off, but the status is on.

Fan Runtime Exceeded: Fan status runtime exceeds a user definable limit (adj.).

HL

AI - FILTER DIFFERENTIAL PRESSURE

H L

AI - FILTER DIFFERENTIAL PRESSURE

H L

AI - FILTER DIFFERENTIAL PRESSURE

BI - FAN STATUS

BO - FAN START/STOP

AI - DISCHARGE AIR TEMP

AI - ZONE SETPOINT ADJUST

RA

AI - ZONE TEMP

DA

BO - COOLING

CHW

T

T

CT

M

SPLIT-SYSTEM HEAT PUMP FAN COIL UNIT:

Run Conditions - Scheduled:

The unit shall run according to a user definable time schedule in the following modes:

Occupied Mode: The unit shall maintain A 75°F (adj.) cooling setpoint A 70°F (adj.) heating setpoint.

DURING OCCUPIED MODE THE SUPPLY BLOWER ON THE FAN COIL UNIT SHALL OPERATE CONTINUOUSLY AT THE LOWEST FAN SETTING.

THE HEAT PUMP SHALL BE ENERGIZED AND SHALL PROVIDE THE NECESSARY HEATING OR COOLING CAPACITY AS REQUIRED TO MAINTAIN SPACE CONDITIONS. THE FAN SHALL ADJUST SPEED BASED ON INTERAL LOGIC TO SATISFY HEATING OR COOLING REQUIREMENTS.

Unoccupied Mode (night setback): The unit shall maintain A 85°F (adj.) cooling setpoint.

A 55°F (adj.) heating setpoint.

Alarms shall be provided as follows:

High Zone Temp: If the zone temperature is greater than the cooling setpoint by a user definable amount (adj.).

Low Zone Temp: If the zone temperature is less than the heating setpoint by a user definable amount (adj.).

Zone Optimal Start:

The unit shall use an optimal start algorithm for morning start-up. This algorithm shall minimize the unoccupied warm-up or cool-down period while still achieving comfort conditions by the start of scheduled occupied period.

Emergency Shutdown:

The unit shall shut down and generate an alarm upon receiving an emergency shutdown signal.

Fan:

The fan shall run anytime the unit is commanded to run, unless shutdown on safeties.

Filter Differential Pressure Monitor:

The controller shall monitor the differential pressure across the filter.

Alarms shall be provided as follows:

Filter Change Required: Filter differential pressure exceeds a user definable limit (adj.).

Discharge Air Temperature:

The controller shall monitor the discharge air temperature.

Alarms shall be provided as follows:

High Discharge Air Temp: If the discharge air temperature is greater than 120°F (adj.).

Low Discharge Air Temp: If the discharge air temperature is less than 40°F (adj.).

Fan Status:

The controller shall monitor the fan status.

Alarms shall be provided as follows:

Fan Failure: Commanded on, but the status is off.

Fan in Hand: Commanded off, but the status is on.

Fan Runtime Exceeded: Fan status runtime exceeds a user definable limit (adj.).

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

5/

/2

4:

:4

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

M

EC

H

AN

IC

AL

C O

N

TR

O L

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

JD

B

-2

7-

09-M501

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

TOTAL HARDWARE (3) TOTAL SOFTWARE (11)

TOTALS 2 0 1 0 1 2 0 1 5 2 4

LOW ZONE TEMP x HIGH ZONE TEMP x SCHEDULE x HEATING STAGE 2 x x HEATING STAGE 1 x x HEATING SETPOINT x x x ZONE OVERRIDE x x x ZONE TEMP x x x

ZONE SETPOINT ADJUST x x

AI AO BI BO AV BV LOOP SCHED TREND ALARM

POINT NAME

HARDWARE POINTS SOFTWARE POINTS SHOW ON

GRAPHIC

POINTS MATRIX - UH - ELECTRIC

NOT TO SCALEG2 SEQUENCE - UH - ELECTRIC

NOT TO SCALEG3aCONTROLS SCHEMATIC - UH - ELECTRIC

NOT TO SCALEB6 GAS FURNACE CONTROLS SCHEMATIC

TOTAL HARDWARE (12) TOTAL SOFTWARE (28)

TOTALS 4 0 1 3 2 2 10 5 13

SCHEDULE x

HEATING MODE x x x

HEATING SETPOINT x x x COOLING MODE x x x COOLING SETPOINT x x x SUPPLY FAN COMMAND x x x SUPPLY FAN STATUS x x x x ECONOMIZER DAMPER x x x MIXED AIR DAMPER x x x DISCHARGE AIR TEMPERATURE x x x x ZONE SETPOINT ADJUST x x ZONE HUMIDITY x x x x ZONE TEMPERATURE x x x x

POINT NAME AI AO BI BO AV BV TREND ALARM SHOW ON

GRAPHIC

POINTS LIST - GAS FURNACE

AD

D xx

/x x/

AD

D -0

NOT TO SCALEC4 ERV CONTROL SEQUENCE

NOT TO SCALEA4 HEAT PUMP CONTROL SEQUENCE

J K N O

MLI P

D-B-1 C-B-1

30x12 RA

13-MD5

30x12 RA

13-MD9

13-MD9

32x12 SA

28x12

16x8 SA

13-MD10

13-MD10

13-MD1016x10 SA

24x36

24x36

36x24 RA

24x36

36x24

48x24

STAIRS

RAMP

R A

M P

STAIRS

UNEXCAVATED

RAMP RAMP CORRIDOR

UNEXCAVATED

ELEVATOR

STAIRS

STAIRS

ELECTRICAL

B11

ELEVATOR

EQUP.

B14

STORAGE

B15

QA OFFICE

B36

JANITOR/MECH

B31

MEN

RESTROOM

B27

MECHANICAL

B13

JANITOR

B07A

STORAGE

B08

STORAGE

B09

RESTROOM

B05

STORAGE

B16

STORAGE

B25

STORAGE

B24

CONFERENCE

ROOM

B18

ACCTG

OFFICE

B19

EXEC. DIR.

OFFICE

B30

HR ASST

OFFICE

B34

GROUP

LIVING DIR.

OFFICE

B29

RESTROOM

B33

CORRIDOR

B12

MECHANICAL

B10

EXAM

B06

STORAGE

B04

RESTROOM

B03

MECHANICAL

B21

ADMISSIONS

OFFICE

B26

GYM

B07

WAITING

AREA /

RECEPTION

B35

WOMEN

RESTROOM

B26

IT/OFFICE

B21A

STORAGE

B22

HR OFFICE

B20

OFFICE

B20-A

CORRIDOR

B23

CONF RM

#2

MEETING

RM

NURSING

B01

MECH

B01A

GYM

B10B

GYM

B10

CORRIDOR

B17

20x10 SA

22x10 SA

18x8

18x8

12x6

26x10

26x10 SA

26x10 SA

28x12 SA

16x10

14x10 SA

13-MD18

20x10 SA

20x10

13-MD19

12x4

14x10

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

-L

IN

D

EN

C

/D

5/

/2

4:

:1

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

BA

SE

M

EN

T M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

13-MD200

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

13-MD5 REMOVE EXISTING DUCTWORK TO EXTENT SHOWN.

EXISTING LOUVER AND PLENUM TO REMAIN. PREPARE

PLENUM FOR NEW CONNECTION.

13-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

13-MD10 PREPARE EXISTING SUPPLY DUCTWORK FOR

CONNECTION TO NEW FURNACE RETURNS.

13-MD18 REMOVE EXISTING GRILLE AND DUCT BACK TO WALL.

PREPARE WALL FOR INSTALLATION OF NEW LOUVER

AND PLENUM IN EXISTING OPENING.

13-MD19 REMOVE EXISTING DUCTWORK TO EXTENT SHOWN.

EXISTING LOUVER AND PLENUM TO REMAIN. CAP

PLENUM WITH INSULATED DUCT CAP.

NORTH

1/8" = 1'-0"A6 BASEMENT MECHANICAL DUCTWORK DEMOLITION PLAN

12'

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

AD

D xx

/x x/

AD

D

MLI P

D-1-1

13-MD4 13-MD2

64x16 RA

C-1-1

64x16 RA

13-MD413-MD2

13-MD9

13-MD9

8ø

8ø

8ø

24x12

8ø

8ø

8ø

12x13

12x12

24x12

12x13

12x12

13-MD11

13-MD11

13-MD1313-MD13

STAIRS

STAIRS

COURTYARD COURTYARD

ELEVATOR

STAIRS

STAIRS

RAMP RAMP CORRIDOR

ENTRY VESTIBULE

JANITOR

RESTROOM

RESTROOM

RESTROOM

102 RESTROOM

STORAGE

102A

OFFICE

OFFICE

OFFICE

MECHANICAL

OFFICE

STORAGE

RESTROOM

OFFICE

142C

OFFICE

OFFICE

142F

DORM

101E

DORM

101D OFFICE

142E

OFFICE

142D

STORAGE

STORAGE

141A

OFFICE

RECEPTION

LIVING

ROOM

CORRIDOR

DORM

101F

DORM

101C

KITCHEN

LAUNDRY

OFFICE

OFFICE

MECHANICAL

WOMEN

RESTROOM

DORM

101G

DORM

101B

KITCHEN

RESTROOM

CORRIDOR

JANITOR

RESTROOM

OFFICE

142G

OFFICE

142H

OFFICE

142A

OFFICE

142B

CORRIDOR

SHOWERS

SHOWERS

DORM

101H

CORRIDOR

DORM

101A

CORRIDOR

RECEPTION

STORAGE

115 STORAGE

LIVING

ROOM

13-MD1513-MD15

13-MD16

ADD

ADD

ADD

ADD

13-MD20

x2

R

A

26x26

13-MD20

x2 x2

R

A x2

R

A x2

R

A

26x26 26x26

13-MD20 13-MD20

13-MD16

x2

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

-L

IN

D

EN

C

/D

5/

/2

4:

:1

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

FI

R

ST

F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

13-MD201

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

13-MD2 DEMOLISH EXISTING DUCT HEATING COIL AND

DUCTWORK INSIDE THE MECHANICAL ROOM.

13-MD4 DEMOLISH OA DUCTWORK BACK TO AHU. WALL

PENETRATION TO BE REUSED FOR NEW OA

DUCTWORK.

13-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

13-MD11 DEMOLISH EXISTING DUCTWORK AND ACCESSORIES IN

THIS LOCATION. PREPARE DUCTWORK FOR NEW VAV

AND DUCTWORK INSTALLATION.

13-MD13 REMOVE SECTION OF DUCTWORK FOR INSTALLATION

OF NEW FIRE DAMPER. SEE NEW WORK PLANS

13-MD15 REMOVE EXISTING KITCHEN TRANSFER DUCT AND

GRILLE. INFILL AND PAINT WALL TO MATCH ADJACENT

WALL COLOR.

13-MD16 DEMOLISH EXISTING RETURN DUCT TO APPROXIMATE

EXTENT INDICATED. DESIGN INTENT IS TO DEMOLISH

RETURN DUCTWORK WHERE CEILING REPLACEMENT

AND ABATEMENT IS OCCURRING.

13-MD20 DEMOLISH PORTION OF EXISTING RETURN DUCT AS

INDICATED BACK TO WALL AND PREPARE DUCT FOR

NEW CONNECTION. VERIFY TERMINATION POINT AND

NOTIFY ENGINEER IF TERMINATION POINT DIFFERS

FROM ANTICIPATED LOCATION.

NORTH

1/8" = 1'-0"A6 FIRST FLOOR MECHANICAL DUCTWORK PLAN

12'

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

AD

D xx

/x x/

AD

D -0

MLI P

60x20 RA

13-MD4 09-MD2

C-2-1

60x20 RA

13-MD413-MD2

8ø

8ø

8ø

26x18

12x12

24x12

8ø

8ø

8ø

8ø

12x12

24x12

26x18

12x12

D-2-1

13-MD9

13-MD9

13-MD11 13-MD11

12x12

13-MD1313-MD13

13-MD16

13-MD16

OPEN TO BELOWOPEN TO BELOW

STAIRS

STAIRS

ELEVATOR

STAIRS

STAIRS

OFFICE

MECHANICAL

OFFICE

OFFICE

OFFICE

RESTROOM

MEDS

RESTROOM

OFFICE

DORM

241D

DORM

241C

DORM

241E

DORM

241F

Space

Space

STORAGE

RESTROOM

MECHANICAL

OFFICE

OFFICE

LAUNDRY

STORAGE

RESTROOM

STORAGE

208A RECEPTION

CORRIDOR

DORM

241G

DORM

241B

RESTROOM

SHOWERS

JANITOR

RESTROOM

LIVING

ROOM

KITCHEN

RESTROOM

JANITOR

DORM

209G

DORM

209D

DORM

209E

DORM

209F

SHOWERS

DORM

209C

DORM

209B

DORM

209A

STORAGE

STORAGE

DORM

241A

RESTROOM

STORAGE

KITCHEN

KITCHEN

228A

LIVING

ROOM

DORM

241H

CORRIDOR

DORM

209H

CORRIDOR

Space

13-MD15

13-MD1526x18

18x12

22x12

8ø

8ø

26x18

26x18

20x12

16x8

8ø 8ø 10x6 8ø

12x12

12x12 10ø

8ø 8ø

10ø

8ø8ø

10ø 10ø

22x12 26x18

18x12

26x18

14x12

20x12

8ø8ø

8ø

18x12

8ø

16x8

10x6

8ø 8ø

10ø10ø

8ø 8ø

10ø 10ø

12x12 12x12

12x12 12x12

8x68x6 SA

ADD

ADD

ADD

ADD

26x26 x2

R

A x2 x2 x2

R

A

26x26 26x26 x2

R

A

26x26 x2

R

A

13-MD20

13-MD20

13-MD2013-MD20

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

-L

IN

D

EN

C

/D

5/

/2

4:

:1

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

SE

C

O N

D F

LO

O

R M

EC

H

AN

IC

AL

D

U C

TW

O

R K

D

EM

O

LI

TI

O

N

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

13-MD202

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

09-MD2 DEMOLISH EXISTING DUCT HEATING COIL AND

DUCTWORK INSIDE THE MECHANICAL ROOM.

13-MD2 DEMOLISH EXISTING DUCT HEATING COIL AND

DUCTWORK INSIDE THE MECHANICAL ROOM.

13-MD4 DEMOLISH OA DUCTWORK BACK TO AHU. WALL

PENETRATION TO BE REUSED FOR NEW OA

DUCTWORK.

13-MD9 REMOVE EXISTING BLOWER COIL UNIT AND

ASSOCIATED PIPING, OUTDOOR AIR DUCTWORK, AND

CONTROLS. SUPPLY DUCTWORK TO REMAIN FOR

RECONNECTION.

13-MD11 DEMOLISH EXISTING DUCTWORK AND ACCESSORIES IN

THIS LOCATION. PREPARE DUCTWORK FOR NEW VAV

AND DUCTWORK INSTALLATION.

13-MD13 REMOVE SECTION OF DUCTWORK FOR INSTALLATION

OF NEW FIRE DAMPER. SEE NEW WORK PLANS

13-MD15 REMOVE EXISTING KITCHEN TRANSFER DUCT AND

GRILLE. INFILL AND PAINT WALL TO MATCH ADJACENT

WALL COLOR.

13-MD16 DEMOLISH EXISTING RETURN DUCT TO APPROXIMATE

EXTENT INDICATED. DESIGN INTENT IS TO DEMOLISH

RETURN DUCTWORK WHERE CEILING REPLACEMENT

AND ABATEMENT IS OCCURRING.

13-MD20 DEMOLISH PORTION OF EXISTING RETURN DUCT AS

INDICATED BACK TO WALL AND PREPARE DUCT FOR

NEW CONNECTION. VERIFY TERMINATION POINT AND

NOTIFY ENGINEER IF TERMINATION POINT DIFFERS

FROM ANTICIPATED LOCATION.

NORTH

1/8" = 1'-0"A6 SECOND FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN

12'

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

AD

D xx

/x x/

AD

D -0

MLI P

F-C-1

F-C-2

EUH-C-B-1 EUH-D-B-1

32x12 SA

18x12 SA 18x18 RA

14x10 SA

4ø FEA

4ø CA

20x18 SA

EUH-C-B-2

13-M02

175 CFM

10x8 SA

12x8 SA

16x8 SA

175 CFM

175 CFM

175 CFM

190 CFM

160 CFM

135 CFM

225 CFM

150 CFM

150 CFM

135 CFM

22x6 SA 10x6 SA

28x10 SA

22x10 SA

28x12 SA

28x12 SA

32x12 SA

115 CFM

110 CFM

110 CFM

125 CFM

110 CFM

70 CFM

70 CFM

14x8 SA

12x8 SA

10x6 SA

75 CFM

125 CFM

125 CFM DUCT ROUTING IS BASED ON RECORD DRAWINGS AND DIFFUSER

LOCATIONS ON SITE. FIELD VERIFY LOCATION OF DUCTWORK PRIOR TO

PERFORMING WORK.

AIRFLOWS SHOWN ON PLANS ARE ASSUMED AIRFLOWS BASED ON

RECORD DRAWINGS.

125 CFM

55 CFM

55 CFM

100 CFM

NOTE:

BUILDING CONTAINS HAZARDOUS MATERIAL SUCH AS ASBESTOS AND

LEAD PAINT. SUPPLEMENTAL HAZARDOUS MATERIAL REPORT IS

PROVIDED IN THE BID DOCUMENTS AS A SEPARATE

ATTACHMENT. REFER TO HAZARDOUS MATERIAL REPORT FOR EXTENTS

OF TESTING AND RESULTS.

EUH-CD-ST4 EUH-CD-ST513-M03

13-M03

13-M03

13-M03 13-M03

3/8" RL

3/4" RS

3/8" RL UP

3/4" RS UP

3/8" RL UP

3/4" RS UP

3/8" RL UP

3/4" RS UP

4ø CA

4ø FEA

3/4" COND

3/4" COND DN

13-M12

3/4" COND DN

3/4" COND

3/4" COND DN

13-M123/4" COND DN

13-M12

3/4" COND

13-M17

13-M17

C.O.

50 CFM

50 CFM

175 CFM

175 CFM

C.O.

175 CFM

175 CFM

85 CFM

85 CFM

85 CFM

85 CFM

85 CFM

55 CFM

55 CFM 55 CFM

55 CFM

75 CFM

75 CFM

75 CFM

75 CFM 85 CFM 55 CFM

55 CFM

55 CFM

3/4" COND

13-M16

13-M16

3/4" COND

ELECTRICAL

B11

ELEVATOR

EQUP.

B14

STORAGE

B15

QA OFFICE

B36

JANITOR/MECH

B31 MEN

RESTROOM

B27

MECHANICAL

B13

JANITOR

B07A

STORAGE

B08

STORAGE

B09

RESTROOM

B05

STORAGE

B16

STORAGE

B25

STORAGE

B24

CONFERENCE

ROOM

B18

ACCTG

OFFICE

B19

EXEC. DIR.

OFFICE

B30

HR ASST

OFFICE

B34

GROUP

LIVING DIR.

OFFICE

B29

RESTROOM

B33

CORRIDOR

B12

MECHANICAL

B10

EXAM

B06

STORAGE

B04

RESTROOM

B03

MECHANICAL

B21

ADMISSIONS

OFFICE

B26

GYM

B07

WAITING

AREA /

RECEPTION

B35

WOMEN

RESTROOM

B26

IT/OFFICE

B21A

STORAGE

B22

HR OFFICE

B20

OFFICE

B20-A

CORRIDOR

B23

CONF RM

#2

MEETING

RM

Space

NURSING

B01

MECH

B01A

GYM

B10B

GYM

B10

CORRIDOR

B17

STAIRS

RAMP

R A

M P

STAIRS

GYM

B07

UNEXCAVATED

RAMP RAMP CORRIDOR

UNEXCAVATED

ELEVATOR

STAIRS

STAIRS

14x12 SA

12x6 SA

HP-D-3

HP-D-1

H P-

D -2

ERV-D-1

EUH-D-2

RG-E

12x8

RG-E

6x6

RG-E

6x6

10ø OA

13-M27

13-M26

13-M27

13-M28

110 CFM

12x6 RA

L-D-1

RG-E

12x6

RG-E

8x6

RG-E

8x6

10x6 SA

10x10 SA

13-M30

13-M29

3/4" COND

3/8" RL UP

3/4" RS UP

13-M02

3/8" RL UP

3/4" RS UP

13-M02

RG-E

12x6

RG-E

10x6

18x8 SA

RG-E

10x6

RG-E

10x6

14x8 RA

RG-E

8x6

10x6 SA

13-M30

RG-E

12x6

12x4 RA

RG-E

12x6

RG-E

12x6 12514x10 RA

10x4 RA

14x8 RA

RG-E

18x6

16x8 TA

14x12 EA

RG-E

18x12

13-M31

18x10 SA

14x12 RA

ADD

12ø EA

10x10 RA 10x10 SA

EUH-FS-ST3 13-M03

Space

AP

PR

O

VE

D B

Y

D R

AW

N

B Y

IS

SU

ED

F

O R

IS

SU

E D

AT

E

PR

O

JE

C

T N

U M

BE

R

FI

EL

D B

O O

K

W

ES

TO

W N

P

KW

Y, S

U

IT

E

W

ES

T

D

ES

M O

IN

ES

, I A

5.

3.

S H

IV

E-

H

AT

TE

R

Y.

C

O M

BA D E

FC G

H

BA D E FC G H

Autodesk Revit 2022

-L

IN

D

EN

C

/D

5/

/2

4:

:5

PM

Au to de sk

D oc s:

//I

A D

AS

W R

C Pr oj ec ts /L in de n- M

EP

-R

_M as te r.r vt

BA

SE

M

EN

T M

EC

H

AN

IC

AL

D

U C

TW

O

R K

PL

AN

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

JD

B

LD

F

-2

7-

13-M200

W R

C D ec en tra liz at io n Ph as e

Fi re

A la rm P ha se

(9

9.

Io w a D ep ar tm en t o f A dm in is tra tiv e

Se rv ic es th S t, W oo dw ar d, IA

KEYNOTES

KEY NOTE

13-M02 REFRIGERANT PIPING SIZE AND ROUTING SHOWN IS AN

APPROXIMATION. EXACT SIZING AND ROUTING SHALL

BE IN ACCORDANCE WITH MANUFACTURER'S WRITTEN

INSTRUCTIONS.

13-M03 NEW ELECTRIC UNIT HEATER TO BE SURFACE

MOUNTED ON WALL PER MANUFACTURER'S

INSTRUCTIONS.

13-M12 ROUTE CONDENSATE PIPING FROM CONDENSATE

PUMP TO JANITOR'S CLOSET. TERMINATE PIPING AT

THE NEAREST FIXTURE IN JANITOR CLOSET.

13-M16 PIPE ROUTING SHOWN IS THE ANTICIPATED

CONDENSATE PIPE ROUTING. FIELD VERIFY EXACT PIPE

ROUTING PRIOR TO INSTALLATION.

13-M17 EXTEND FLUE AND COMBUSTION AIR THROUGH WALL

TO EXTERIOR. SLEEVE PENETRATIONS AND SEAL

WEATHERTIGHT. REFER TO FURNACE

MANUFACTURER'S WRITTEN INSTRUCTIONS FOR FLUE

AND COMBUSTION VENTING REQUIREMENTS AND

TERMINATION DETAILS.

13-M26 ROUTE NEW OA INTAKE DUCT THROUGH WALL. SLEEVE

PENETRATION AND SEAL…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .