This document contains the revised work package details for the Cottage Innovations Center for Culinary Entrepreneurship project located in Fitzgerald, Georgia. The project is being managed by the Fitzgerald & Ben Hill County Development Authority. The work packages cover various trades including general requirements, sitework, concrete, gypsum assemblies, LVP flooring, painting, fiberglass reinforced panels, specialties, kitchen equipment, plumbing, mechanical, and electrical. Each work package provides a detailed scope of work and references the applicable drawings and specifications. The project is scheduled for completion on August 20, 2024.

The document also includes information about the related state and local contract opportunity. The project is located in the state of Georgia. The contract opportunity covers the construction of the Cottage Innovations Center, with the detailed requirements provided in the attached work package information. Pricing, funding sources, and any set-asides or incumbent information is not provided in the document.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cottage Innovations Center for Culinary Entrepreneurship Fitzgerald & Ben Hill County Development Authority

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

Work Packages List

1a – General Requirements (CM/GC Only – Fee Proposal)

1b – General Work

2 – Sitework

3 – Concrete

9a – Gypsum Assemblies & Acoustical Ceilings

9b – LVP

9c – Painting

9d – Fiberglass Reinforced Panels

10 – Specialties

11 – Kitchen Equipment

15a – Plumbing

15b – Mechanical

16 – Electrical

Please carefully review the following work package descriptions.

***LRA SD Drawings take precedence over Architectural Drawings***

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

Work Package: 1a – General Requirements (CM/GC Only – Fee Proposal)

Work Package: 1b – General Work

Provide all supervision, labor, material and equipment necessary and incidental to complete all General

Work as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Final Civil Drawings dated 01/23/2024

Furnish & Erect pre-engineered metal building

Provide metal building insulation (Basis of Design: Therm-All Proliner System).

Provide alternate for wire suspended batt insulation system at roof line.

Furnish and install blocking in walls as required.

On-going and final clean-up.

Work Package: 2 – Sitework

Provide all supervision, labor, material and equipment necessary and incidental to complete all Site

Work as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Civil Drawings dated 01/23/2024

Clearing/Grading, underground utilities, GAB parking area (including wheel stops)

Curb cut, driveway and sidewalk

Site concrete: handicapped parking (including signs and pavement marking), sidewalk

Installation and maintenance of required BMPs per GSWCC requirements. Disturbed area is less than 1 acre, so a General Permit will not be required.

Temporary & Permanent Seeding included.

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

Work Package: 3 – Concrete

Provide all supervision, labor, material and equipment necessary and incidental to complete all Building

Concrete Work as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Final Civil Drawings dated 01/23/2024

Form, place and finish the following concrete: Building Foundations, SOG, Porches (front & back), HVAC condenser pads

Includes all needed materials (forms, rebar, sand fill, 6mm poly, concrete, curing compound/sealer)

Includes saw-cutting SOG

Includes setting anchor bolts. CM will provide anchor bolts and template. CM will verify anchor bolt placement prior to concrete being placed.

ADD CONCRETE DUMPSTER PAD AT LOCATION SHOWN ON CIVIL DRAWINGS. PAD TO BE

10’X12’X6” THICK WITH 12” TURNDOWN FOOTING. 3000 PSI CONCRETE WITH FIBER. 2 - #4

REBARS CONINTUOUS IN BOTTOM OF FOOTING. INCLUDE 5 – 6” STEEL PIPE BOLLARDS (7’

LONG) FILLED WITH CONCRETE.

Work Package: 9a – Gypsum Assemblies & Acoustical Ceilings

Provide all supervision, layout, labor, material and equipment necessary and incidental to complete all

Gypsum Assemblies & Acoustical Ceilings as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Includes metal stud framing of all exterior and interior walls.

Includes 5/8” Type X mold resistant drywall at all walls

Includes 2’x4’ acoustical ceiling panels. Provide vinyl coated drywall panels around both commercial hoods as required.

Provide alternate pricing for 2’x2’ system.

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

On-going and final clean-up.

Work Package: 9b – LVP Flooring

Provide all supervision, labor, material and equipment necessary and incidental to complete all LVP &

Rubber base as per the Bid Documents, including but not limited to, the following:

LVP (20mil wear layer) to be provided in ADA Unisex Restroom, Office and Front Entryway.

4” rubber base and transition strips to be provided in these locations also

On-going and final clean-up.

DISREGARD FINISH SCHEDULE SHOWN IN LRA SD DRAWINGS. INFORMATION CONTAINED IN

THIS WORK PACKAGE REPRESENTS REQUIRED FINISHES.

Work Package: 9c – Painting

Provide all supervision, labor, material and equipment necessary and incidental to complete all Painting as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Painting will be limited to Office and Front Entryway. All doors and jambs will also require paint.

All other walls will require FRP (see Section 9d).

On-going and final clean-up.

Work Package: 9d – Fiberglass Reinforced Panels

Provide all supervision, labor, material and equipment necessary and incidental to complete all

Fiberglass Reinforced Panels as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

Fiberglass Reinforced Panels are required at all walls within the Kitchen Area, ADA Unisex

Restroom and Janitorial Closet

All required trim and adhesive should be included for complete installation.

On-going and final clean-up.

Work Package: 10a – Specialties

Provide all supervision, labor, material and equipment necessary and incidental to complete all

Specialties as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

Toilet and bath accessories.

On-going and final clean-up.

Work Package: 11 – Kitchen Equipment

Provide all supervision, labor, material and equipment necessary and incidental to complete all Kitchen

Equipment as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Contract for Kitchen Equipment Package will be administered directly thru Fitzgerald & Ben Hill

County Development Authority. Selected vendor will be responsible for coordinating all equipment and equipment requirements with CM. Vendor will also be responsible for coordinating with other trades as it relates to their work. Vendor will be responsible for delivery, uncrating/unboxing, assembly and final placement of their equipment. Dumpster will be provided onsite for disposal of packaging materials.

On-going and final clean-up.

SEE ADDED FOOD SERVICE SPECIFICATION AND EQUIPMENT CUTSHEETS. ALTERNATE

MANUFACTURER’S ITEMS OF EQUAL QUAILTY WILL BE ACCEPTABLE.

Work Package: 15a – Plumbing

Provide all supervision, labor, material and equipment necessary and incidental to complete all

Plumbing as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

Final Food Service Drawings dated 07/31/2024

Final Civil Drawings dated 01/23/2024

Includes all required plumbing (including final connections) for commercial kitchen equipment.

On-going and final clean-up.

INCLUDE 2 TANKLESS GAS WATER HEATERS (RINNAI RX199iN OR EQUAL) LOCATED ON THE

EXTERIOR OF THE BUILDING. INCLUDE PROTECTIVE SHROUD FOR PIPING.

INCLUDE 1,000 GALLON GREASE TANK ON EXTERIOR OF BUILDING. SEE REVISED SHEET P-1.

DWV PIPING TO BE PVC

WATER PIPING TO BE PVC/PEX

PLUMBING FIXTURES AS FOLLOWS: PORCELAIN TANK TYPE TOILET (ADA HEIGHT), PORCELAIN

WALL HUNG SINK WITH LEVER FAUCET AND ADA INSULATION KIT, HIGH DENSITY COMPOSITE

MOPSINK WITH STANDARD FAUCET

GAS PIPING SHOULD BE SIZED FOR BOTH WATER HEATERS, 2 – 5 TON PACKAGED HVAC UNITS

(GAS HEAT), AND KITCHEN EQUIPMENT (APPROXIMATE TOTAL BTUs: 650,000)

INCLUDE STANDARD EXTERIOR WATER FAUCETS AT FRONT AND REAR OF BUILDING. INCLUDE

BACKFLOW DEVICE ON FAUCETS.

LOCATE WATER RISER IN JANITOR’S CLOSET.

COOLER DRAIN LOCATION TO BE LOCATED TO KITCHEN HOOD SIDE OF COOLER, NOT IN FOYER.

NO CURRENT PLANS FOR ICE MACHINES OR TRENCH DRAINS.

Work Package: 15b – Mechanical

Provide all supervision, labor, material and equipment necessary and incidental to complete all

Mechanical as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated 07/31/2024

Final Civil Drawings dated 01/23/2024

Includes Final Testing, Adjusting and Balancing

Includes all required mechanical (including final connections) for commercial kitchen equipment.

Kitchen Hoods (including hood, exhaust fans, fresh air fans, fire suppression system and all associated duct) will be responsibility of Owner’s Kitchen Equipment Subcontractor.

On-going and final clean-up.

Fitzgerald, GA

AUGUST 20, 2024

All Trades

GMP Work Packages

LRA Constructors, Inc.

HVAC UNITS WILL BE 5 TON PACKAGED UNITS WITH GAS HEAT, MINIMUM SEER RATING OF 15.

UNITS WILL BE MOUNTED ON PADS AT REAR OF BUILDING. DUCTWORK WILL ENTER BUILDING

ABOVE INTERIOR CEILING HEIGHT. PROVIDE PADS FOR UNITS. PROVIDE PAINT-GRIP METAL

SHROUD AROUND EXTERIOR PORTION OF DUCTWORK.

Work Package: 16a – Electrical

Provide all supervision, labor, material and equipment necessary and incidental to complete all Electrical as per the Bid Documents, including but not limited to, the following:

Final Architectural Drawings dated November 13, 2023

LRA SD Drawings dated 07/12/24

Final Food Service Drawings dated August 31, 2022

Final Civil Drawings dated 01/23/2024

Coordinate with Mechanical for Commercial Kitchen Hoods requirements as well as all other

HVAC equipment.

Includes all required electrical (including final connections) for commercial kitchen equipment.

Includes fire/smoke alarm requirements.

On-going and final clean-up.

ELECTRICAL SERVICE TO BE 600A 3 PHASE. METER AND EXTERIOR DISCONNECT TO BE LOCATED

AT REAR OF BUILDING.

ADD LED WALL MOUNTED LIGHT PACKS ON FRONT AND REAR OF BUILDING (4 TOTAL FIXTURES)

INCLUDE ALLOWANCE OF $3,500 FOR ELECTRICAL CORD REELS ($700 PER REEL)