Request_for_Solicitation_or_Contract_(Project_Info).docx

DOCX document 262 KB Posted

Attached to
Intersection Automated Enforcement Safety System
Solicitation number
Y24-1099
Issued by
Orange County, Orlando City, Florida

About this file

This is a Request for Solicitation or Contract document from Orange County, Florida, specifically for the Public Works / Traffic Engineering Department seeking an Intersection Automated Enforcement Safety System. The county is soliciting proposals for a cutting-edge automated enforcement system to assist in changing driver behavior, with a service start date of March 1, 2025. The procurement requires one hundred (100) red light cameras to be delivered within 90 days of contract execution, with potential vendors including NovoaGlobal, Sensys Gatso, and Verra Mobility. Responses are due by 4:00 pm EST on January 28, 2025, via the OpenGov e-Procurement Platform, with potential vendors required to submit qualification information including similar project references, available equipment and software, and internal quality control measures. The contract is structured as a core four-year term with potential for three additional two-year extensions, totaling a possible ten-year contract period.

The estimated budget for this project is $29,491,152, with funding allocated through accounting line 1002-072-2718-3197. The procurement will follow a Request for Proposals (RFP) process, with award made to the highest-ranking proposer based on evaluation factors. While not specifically designated as a grant-funded project, the county has noted the potential for future disaster recovery use. The procurement allows for a firm fixed fee structure and requires vendors to process potential traffic violations within five days. Potential vendors must demonstrate substantial experience in similar scope projects, and the county will evaluate submissions based on technical capabilities, performance history, and cost considerations.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Solicitation or Contract Date Submitted:

05/15/2024

Procurement Project Information Sheet

This Document shall be submitted to Procurement in MS Word – Do Not PDF or Submit Hardcopies

GENERAL

Solicitation Title
Intersection Automated Enforcement Safety System

Current Contract Number (if this is a rebid) Y12-1099

Service Start Date OR Commodity Need Date 03/01/2025

Project Brief Summary
To obtain a cutting-edge automated enforcement system to assist in changing driver behavior
Department / Division
Public Works / Traffic Engineering

PROJECT SPONSORS

Project Representative Name & Title
Jerald Marks Jr – Project Manager
Email Address
Jerald.marksjr@ocfl.net
Phone Number
407-836-7892

Authorized By Name (Mgr. or Dir.)

Humberto Castillero – Traffic Engineering Manager

FUNDING

Estimated Budget
$29,491,152
Accounting Line
1002-072-2718-3197

Commodity Code (Click for List)

Declaration of Emergency
☐ This contract MAY be used to respond to disaster recovery. (COMPLETE PART 2)
☒ This contract WILL NOT be used to respond to disaster recovery.
Federal Compliance
☐Federal Funding IS a consideration of this procurement. (COMPLETE PART 2)
☒Federal Funding is not a consideration of this Procurement
Grant Funding
☐ Grant Funding IS a consideration of this procurement. (COMPLETE PART 2)

☒ Grant Funding is not a consideration of this Procurement

COMPETITION STANDARDS

☐ RFQ - REQUEST FOR QUOTATIONS (UNDER THE BID LIMIT); INFORMAL PROCESS

Award shall be made to the lowest responsive and responsible quoter meeting all qualification requirements.

☐IFB - INVITATION FOR BIDS; FORMAL SEALED SOLICITATION

Award shall be made to the lowest responsive and responsible bidder meeting all qualification requirements.

☒ RFP – REQUEST FOR PROPOSALS; FORMAL SEALED SOLICITATION

Award shall be made to the high ranking proposer based on a series of evaluation factors.

☐ RFP3 – THREE-PHASE REQUEST FOR PROPOSALS; FORMAL SEALED SOLICITATION

Award shall be made to the high ranking proposer based on a series of escalating evaluation factors (Phase 1- Technical standards, Phase 2- on-site demonstrations & Phase 3 – Cost & Socioeconomic factors) ☐ RFQu - REQUEST FOR QUALIFICATIONS; FORMAL SEALED SOLICITATION Solicitation will result in a shortlist of firms pre-qualified for future solicitation opportunities (disallowed for Federal Grants).

☐ SOLE SOURCE (FORM REQUIRED)

☐ EMERGENCY (FORM REQUIRED)

CONTRACT TYPE

☐ One-Time
☒ Term Contract (Multi-Year Requirement) – Specify Term / Renewals below:

Core four (4) year term with three (3) additional two (2) year extensions totaling ten (10) years

PERFORMANCE / DELIVERY REQUIREMENTS

Invoice Location / Contact
Fiscal & Operations Support Division

4200 South John Young Parkway, Orlando, Florida 32839

Performance Requirements
Provide processing of potential traffic violations within five (5) days
Delivery Requirements
One Hundred (100) red light cameras within 90 days of executing contract
☒ Non-Construction
☐ Construction per Federal Definition; Click Here to View Subpart 2.1

“Construction” means construction, alteration, or repair (including dredging, excavating, and painting) of buildings, structures, or other real property. For purposes of this definition, the terms “buildings, structures, or other real property” include, but are not limited to, improvements of all types, such as bridges, dams, plants, highways, parkways, streets, subways, tunnels, sewers, mains, power lines, cemeteries, pumping stations, railways, airport facilities, terminals, docks, piers, wharves, ways, lighthouses, buoys, jetties, breakwaters, levees, canals, and channels. Construction does not include the manufacture, production, furnishing, construction, alteration, repair, processing, or assembling of vessels, aircraft, or other kinds of personal property.

Fee Schedule
☒ Firm Fixed Fee
☐ Revenue Sharing
☐Cost Plus

(Disallowed for Federal Grants)

POTENTIAL VENDORS

Provide Firm Name and Email Address for each Firm
NovoaGlobal – info@novoaglobal.com

Sensys Gatso – info@sensysgatso.com Verra Mobility – info@verramobility.com Conduent/Elovate Altumint RedSpeed Jenoptik

Pre-Bid/Pre-Proposal/ Pre-Quote Conference
☐ N/A
☒ Non-Mandatory

☐ Mandatory (Justification required; subject to Procurement approval) Justification:

VENDOR QUALIFICATIONS (Applicable to IFB/RFQ) Edit the base language (right) as required:

Consider:

Do you need a specific License Validation?

Do you require resumes to validate experience?

What factors distinguish a qualified firm from an unqualified firm?

Do you require sample goods?

Will the County make site visits before award?

The respondent shall submit the following information with the bid:
A.List and brief description of work substantially similar in scope and magnitude satisfactorily completed with location, dates of contract, names, addresses, email addresses and telephone numbers of owners by completing the attached reference sheets.
B.List of equipment and software available to perform the work
C.List or describe internal quality control measures in regards to equipment and product

RESPONDENT QUALIFICATIONS (Applicable to RFP) ☒ Attached Hereto This document provides the weighted criteria and the corresponding submittals for evaluation purposes.

SPECIFICATIONS / SCOPE OF SERVICES

☒ Attached Hereto

This document defines the performance requirements, deliverables and deadlines associated with your procurement. A scope of services is the foundation of a services contract. A scope of services provides clear direction to the service provider before the work begins.

Guideline:

SUSTAINABILITY/ENVIRONMENTAL ELEMENTS

☐ Applicable ☒ Not Applicable Detail any elements of this procurement that contribute to the County’s sustainability/environmental goals:

BID FORM/ FEE PROPOSAL FORM

☒ Attached Hereto This document provides the basis for a competitive fee comparison. Line items and descriptions shall indicate unit rates and estimated quantities to arrive at a total contract value which shall be used to determine (1) the lowest responsive and responsible bidder (2) the proposer with the lowest fee proposal subject to evaluation.

The bid form/fee proposals form shall be inclusive of all items, services and incidentals required to fulfill the scope of services.

PART 2

ADDITIONAL REQUIREMENTS FOR GRANT FUNDED PROCUREMENTS (MANDATORY)

Grant (if applicable)

☐ Not Applicable

This contact is anticipated to be used for Disaster Response and Recovery (FEMA Reimbursable)

☐ Direct Federal Grant
☐Federal Pass-through
☐ State Grant

☐ Other Grant (Specify):

Grant Start/Expiration
Click Here THROUGH Click Here

☐ Attach first page of Notice of Grants Award ☐ County Funded at Risk of Non-Appropriation of Grant funds. Written approval from the Office of Management and Budget is attached.

☐ Provide any specific information the Grant requires to be included in the solicitation
List below (examples: grant number, amount, agency specific clauses, retention requirements, specific competition requirements or checklists):

Solicitation Type Click Here to view Regulation §200.330 ☐ Contractor Solicitation The County is solely responsible for reporting on grant required outcomes.

☐ Sub-recipient Solicitation The awardee is responsible for program decisions and reporting on grant required outcomes.

Independent Estimate (Cost/Price Analysis) Click Here to view Regulation §200.323

1. Complete the document (MS Word )

2. Revise and save the document and it will attach to this form.

[Applicable to Formal Solicitations Only]

Procurement of Recovered Materials Click Here to view Regulation §200.322 If applicable, identify specific recovered materials to be used for project execution List Below:

Procurement Division Page 2 of 5 [Rev.10/19] image2.emf

1-26 Sample Scope of Service-Scope of Work Formats.pdf image3.emf

Independent Estimate Final [Rev 09-18].docx Solicitation, Contract and Change Order

Independent Estimate

Grant Funded Procurements (Mandatory) Click Here to view Regulation §200.323

Solicitation/Contract Title

ANALYSIS TYPE

☐ Price Analysis (Preferred)

☐ Cost Analysis

PRICE ANALYSIS will be the usual procedure followed in a competitive situation and in situations where items are being procured which are sold in the commercial marketplace to the general public. A “price analysis” is an evaluation of the budgeted price relative to the prices being offered by other vendors and being paid by the general public for the same or similar items. The essential factors, which must be present in order to make a “price analysis,” are as follows:

The product must be a “commercial product” (i.e., one for which there is a basis of comparison in the commercial marketplace). Price analysis would not be suitable, for example, for research and development items, or for one-of-a-kind items for which there was no basis of comparison.

It is not necessary that competing products be exactly identical to the product being offered, but you must be able to compare the products’ capabilities and their respective price differences in light of those varying capabilities. By such comparisons one is able to make value judgments that a particular product’s performance capabilities warrant a higher or lower price than a competing product.

COST ANALYSIS will be required whenever a price analysis cannot be performed. A cost analysis entails the review and evaluation of the separate cost elements and the proposed profit of an offeror’s cost proposal. A cost analysis is conducted to perform an opinion on the degree to which the acceptable cost, including profit, represents what the performance of the contract ‘should cost’, assuming reasonable economy and efficiency. A cost analysis will be appropriate in the following situations:

The product or service being offered is not susceptible to being evaluated against other commercially available items of similar products or services. Examples would include a procurement for professional services where no competing price proposals are submitted or a sole-source procurement for other types of services.

When change orders are issued to contracts requiring the contractor to do work whose cost can only be evaluated by examining the various cost elements, such as labor, materials, travel, etc.

NOTE: The non-Federal entity must negotiate profit as a separate element of the price for each contract in which there is no price competition and in all cases where cost analysis is performed. To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the contractor, the contractor's investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.

PRICE ANALYSIS

NOTE: The independent estimate cannot be based on the budget. However, budgets shall be sufficiently funded to support the amount of the Independent Estimate.

Where appropriate, an analysis will be made of lease versus purchase alternatives, and any other appropriate analysis to determine the most economical approach.

Procurement Division Page 1 [Rev.09/18]

COST ANALYSIS WORKSHEET [Independent Estimate Supplement]

DESCRIPTION

MATERIALS/ EQUIPMENT

LABOR

OVERHEAD

PROFIT

SUB-TOTAL

QTY.

UNIT OF MEAS.

UNIT COST

QTY.

UNIT OF MEAS.

UNIT COST

COST ANALYSIS GRAND TOTAL ESTIMATE

Procurement Division [Rev.09/18] image1.png image1.png