Request For Information Form.pdf
PDF 51 KB Posted
- Attached to
- B1710 Office Refurbish
- Solicitation number
- FA667526Q0002
About this file
This is a Request for Information/Clarification Form template used for federal contracting purposes, specifically designated for Air Force use (301 CONF/PK contracting office).
The form serves as a two-page template for contractors to submit requests for information or clarifications regarding contract requirements, drawings, or specifications. Page 1 is designated for contractor use and includes fields for contract number, RFI number, date, subject matter, drawing references, response deadline, the specific request, and any proposed solution if applicable. The contractor must identify the contracting officer, provide their own organizational information, and obtain required signatures. Page 2 is designated for government use only and provides sections for the contracting officer to evaluate the request, issue an RFI response or clarification, and route the form through the Air Force Contracting Office. The form includes a contractor review section requiring the contractor to assess whether the government's response will necessitate a change order or result in project cost increases. The template emphasizes that contractors must return the reviewed form to the contracting officer, and if either change order or cost increase questions are answered affirmatively, the contracting office will notify the contractor of any required further actions such as change proposal submissions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO: RFI NUMBER: DATE (MM/DD/YY)
SUBJECT: DRAWING REFERENCE / DETAIL:
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:
REQUEST:
PROPOSED SOLUTION (If applicable):
TO(Contracting Officer): 301 CONF/PK FROM (Contractor):
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR GOVERNMENT USE ONLY
FROM CONTRACTING
TO:
For Evaluation and Action
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
TO:(AF Contracting Office)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
TO:(Contractor)
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.
| TOContractor: |
| Reviewer: |
| Text1: |
| Text2: 001 |
| Date3_af_date: |
| Text4: |
| Text5: |
| Check Box6: Off |
| Date7_af_date: |
| Text9: |
| Text10: |
| Text11: |
| Text12: |
| Date13_af_date: |
| Text14: |
| Text16: |
| Date17_af_date: |
| Text18: |
| Text20: |
| Date21_af_date: |
| Text22: |
| Date24_af_date: |
| Text25: |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Date31_af_date: |
| Text32: |
File details come from the government source that posted it. Updated .