Replace AHU COVID Wards 6J-6K Bid Set Drawings updated 1-19-22.pdf

PDF 12 MB Posted

Attached to
Y1DA--674-20-019 Replace AHU's COVID Wards 6J - 6K
Solicitation number
36C25722B0029
Issued by

About this file

This document outlines a federal contract opportunity to replace air handling units in two COVID wards at a Veterans Affairs medical center. The solicitation number is 36C25722B0029 and seeks to replace the air handling units in Wards 6J and 6K at the Veterans Affairs medical center in Temple, Texas, under project number 674-20-019. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17. Offerors should provide design and construction services to replace the existing air handling units with new energy efficient units and ensure proper ventilation is maintained in the wards housing COVID-19 patients. The response due date is not specified but the work is expected to be completed by the end of 2022.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

MEP ENGINEER:

HUITT-ZOLLARS, INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102 817-335-3000 POC: Joel Colwell jcolwell@Huitt-Zollars.com

ARCHITECT:

CB DESIGN GROUP

421 KING STREET

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

POC: PAUL W. BRIDGES

PROFESSIONAL SEAL:

Olin E. Teague VA Medical Center 1901 Veterans Memorial Drive Temple, TX 76504

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

12/20/2021

674-20-01

JSAL

A/E DESIGN SERVICES TO

REPLACE AHUs BLDG. 204

(COVID UNIT, WARDS 6J-6K)

100% BID SET SUBMISSION

COVER SHEET

GI100

-2

-0

G I1

.p d f

Department of Veterans Affairs

A/E DESIGN SERVICES TO REPLACE AHUs BLDG 204

(COVID UNIT, WARDS 6J-6K)

OLIN E. TEAGUE VA MEDICAL CENTER

1901 VETERANS MEMORIAL DRIVE

TEMPLE, TX 76504

LOCATION MAP DRAWING LIST

Medical Center Director

Director of Facility Management Service

Medical Director

Project COR

Project CO

Infection Control

Safety Officer

APPROVALS

GENERAL INFORMATION

GI100 COVER SHEET

GI200 SYMBOLS, ABBREVIATIONS & NOTES

GI300 GENERAL NOTES

GENERAL CONTRACT

GC301 ICRA PLAN - AREA J

GC302 ICRA PLAN - AREA K

GC401 LIFE SAFETY PLAN & CODE STUDY

ARCHITECTURAL

AD701 6TH FLOOR REFLECTED CEILING DEMOLITION PLAN - AREA J

AD702 6TH FLOOR REFLECTED CEILING DEMOLITION PLAN - AREA K

AE701 6TH FLOOR REFLECTED CEILING RENOVATION PLAN - AREA J

AE702 6TH FLOOR REFLECTED CEILING RENOVATION PLAN - AREA K

MECHANICAL

M-001 HVAC GENERAL NOTES AND DESIGN DATA

M-002 HVAC ABBREVIATIONS AND SYMBOLS

MD-101 SIXTH FLOOR HVAC PLAN - DEMOLITION PLAN - WING 6J

MD-102 SIXTH FLOOR HVAC PLAN - DEMOLITION PLAN - WING 6K

MD-103 SIXTH FLOOR HVAC PLAN - DEMOLITION PLAN - MECHANICAL ROOM 6K112

MD-104 HVAC PLAN - DEMOLITION PLAN- ROOF

M-101 SIXTH FLOOR HVAC PLAN - WING 6J

M-102 SIXTH FLOOR HVAC PLAN - WING 6K

M-103 SIXTH FLOOR HVAC PLAN - MECHANICAL ROOM 6K112

M-104 HVAC PLAN - ROOF

M-310 HVAC SECTIONS

M-501 HVAC DETAILS

M-502 HVAC DETAILS

M-601 HVAC SCHEDULES

M-602 HVAC SCHEDULES

M-603 HVAC SCHEDULES

M-701 CONTROL DIAGRAMS

ELECTRICAL

E-001 ELECTRICAL LEGEND, ABBREVIATIONS AND GENERAL NOTES

E-101 6TH FLOOR ELECTRICAL PLAN - AREA J

E-102 6TH FLOOR ELECTRICAL PLAN - AREA K

E-200 ENLARGED ELECTRICAL PLANS

PROJECT DIRECTORY

CONTRACTING OFFICER REPRESENTATIVE (COR)

Nelson Gonzalez

Olin E. Teague VAMC 1901 Veterans Memorial Dr.

Temple, TX 76504

PHONE: (254) 743-7971

Nelson.gonzalez3@va.gov

ARCHITECT

CB DESIGN GROUP

421 King Street Suite 301

PHONE: (703) 772-4213

Wes Bridges wbridges@cbdg-ae.com

MEP/FP/STRUCTURAL ENGINEER

HUITT-ZOLLARS INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102

PHONE: (817) 335-3000

Joel Colwell jcolwell@Huitt-Zollars.com

CONTRACTING OFFICER (CO)

Lynn Pettit

Department of Veterans Affairs | Contracting

VISN 17 NCO

2002 Scott Blvd.

Temple, TX 76504

PHONE: (254) 899-6001

Lynn.Pettit@va.gov

N.T.S.

100% BID SET SUBMISSION

ALongeau Text Box

WOOD

ALUMINUM

STEEL

EARTH

CONCRETE MASONRY UNITS

RIGID INSULATION

CONCRETE

EXISTING CONSTRUCTION TO REMAIN

EXISTING CONSTRUCTION TO BE REMOVED

BRICK

WOOD-FINISHED

WOOD ROUGH

PLYWOOD

GYPSUM - PLASTER

ACOUSTIC TILE

CAST STONE

ALL METALS - SMALL SCALE

GLASS - LARGE SCALE

BATT INSULATION

CERAMIC TILE

CARPET

GRAVEL

CENTER LINE

DETAIL INDICATOR

DETAIL INDICATIOR

DETAIL INDICATOR FOR SMALL CONDITIONS

DIMENSION LINE

NEW DOOR OPENING / BORROWED LIGHT

INDENTIFIER

DRAWING BLOCK TITLE, TYPICAL

ELEVATION INDICATOR, EXTERIOR

ELEVATION INDICATOR, INTERIOR, MULTIPLE VIEW

ELEVATION INDICATOR, INTERIOR, SINGLE VIEW

SECTION INDICATOR

TYPICAL DETAIL INDICATOR

FURNITURE, FIXTURE, & EQUIPMENT INDICATOR

COLUMN GRID

KEYNOTE

WALL OR PARTITION TYPE

FIRE EXTINGUISHER CABINET

NORTH ARROW

FEC

A

DETAIL NUMBER

SHEET WHERE

DRAWN

XXxxx

XXxxx

X

DRAWING TITLE

SCALE: 1 1/2" = 1'-0"

1 3/16"

D2

XX-XX

XXxxx

XXxxx

CL

XXxxx x'-x" VERTICAL HEIGHT INDICATOR

REVISION

REVISION CLOUD

NORTH

BREAK LINE

X

DEMOLITION KEYNOTE

NEW ROOM NAME AND NUMBERCORRIDOR

C2

XX

A

XXxxx

D

BC

COLUMN NUMBER

COLUMN LETTER

XXxxx

ELEVATION NUMBER

SHEET WHERE

DRAWN

ELEVATION NUMBER

SHEET WHERE

DRAWN

ELEVATION NUMBER

SHEET WHERE

DRAWN

DETAIL NUMBER

SHEET WHERE DRAWN

DETAIL NUMBER

SHEET WHERE DRAWN

WALL MOUNTED FIRE EXTINGUISHERFE

XX

SHEET WHERE

DRAWN

ELEVATION NUMBER

& AND

@ AT

C CENTERLINE

# NUMBER

AB ANCHOR BOLT

ABV ABOVE

ACT ACOUSTIC CEILING TILE

AD AREA DRAIN

ADA AMERICANS WITH

DISABILITIES ACT

ADJ ADJUSTABLE

AFF ABOVE FINISHED FLOOR

AHU AIR HANDLING UNIT

AIA AMERICAN INSTITUTE OF

ARCHITECTS

ALUM ALUMINUM

ALT ALTERNATE

AP ACCESS PANEL

APPROX APPROXIMATE

ARCH ARCHITECTURAL

AUTO AUTOMATIC

AVG AVERAGE

BD BOARD

BLDG BUILDING

BLK BLOCK

BM BEAM

BOT BOTTOM

BRG BEARING

BEL BELOW

BR BUMPER RAIL

BRK BRICK

CAB CABINET

CB CATCH BASIN

CEM CEMENT

CCT CUBICLE CURTAIN TRACK

CG CORNER GUARD

CI CAST IRON

CIP CAST IN PLACE

CJ CONTROL JOINT

CT CERAMIC TILE

CLG CEILING

CL CLOSET

COL COLUMN

CONC CONCRETE

CONF CONFERENCE

CONT CONTINUOUS

CPT CARPET

CT CERAMIC TILE

CU CUBIC

DBL DOUBLE

DEMO DEMOLITION

DEPT DEPARTMENT

DET DETAIL

DF DRINKING FOUNTAIN

DIA DIAMETER

DIM DIMENSION

DISP DISPENSER

DN DOWN

DO DOOR OPENING

DOZ DOZEN

DP DAMPPROOFING

DR DOOR

DWG DRAWING

DWGS DRAWINGS

DWR DRAWER

E EAST

EA EXHAUST AIR, EACH

EL ELEVATION

ELEV ELEVATION

ELEC ELECTRICAL

EMER EMERGENCY

ENCL ENCLOSURE

ENGR ENGINEER

EP ELECTRICAL PANELBOARD

EQ EQUAL

EQUIP EQUIPMENT

EWC ELECTRIC WATER COOLER

EWS EYE WASH STATION

EXP EXPANSION

EJ EXPANSION JOINT

EXIST EXISTING

EXT EXTERIOR

FA FIRE ALARM

FB FACE BRICK

FD FLOOR DRAIN

FDC FIRE DEPARTMENT

CONNECTION

FDN FOUNDATION

FE FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER

CABINET

FF FINISH FACE

FHC FIRE HOSE CABINET

FIN FINISH

FLR FLOOR

FLUOR FLUORESCENT

FO __ FACE OF __

FOC FACE OF CONCRETE

FOS FACE OF STUD

FOW FACE OF WALL

FPRF FIREPROOF(ING)

FR FIRE RATING, FRAME

FRMG FRAMING

FS FULL SIZE

FT FOOT OR FEET

FTG FOOTING

FUR FURRING

FUT FUTURE

GC GENERAL CONTRACTOR

GA GAUGE

GAL GALLON

GALV GALVANIZED

GALV STL GALVANIZED STEEL

GB GRAB BAR

GC GENERAL CONTRACTOR

GD GUARD

GL GLASS

GND GROUND

GR GRADE

GWB GYPSUM WALLBOARD

GYP BD GYPSUM WALLBOARD

HB HOSE BIBB

HC HOLLOW CORE

HD HEAD

HDWR HARDWARE

HDWD HARDWOOD

HT HEIGHT

HNDRL HANDRAIL

HM HOLLOW METAL

HMD HOLLOW METAL DOOR

HMF HOLLOW METAL FRAME

HR HANDRAIL

HO HOLD OPEN

HORIZ HORIZONTAL

HP HIGH POINT

HR HOUR

HVAC HEATING, VENTILATION, AIR

CONDITIONING

IBC INTERNATIONAL BUILDING CODE

ID IDENTIFICATION, INSIDE

DIAMETER / DIMENSION

IN INCH

INCL INDLUDE(D)

INSUL INSULATION

INT INTERIOR

INV INVERT

JAN JANITOR

JST JOIST

JT JOINT

KP KICK PLATE

KO KNOCKOUT

L LENGTH

LAB LABORATORY

LAM LAMINATE

LAV LAVATORY

LBS POUND

LED LIGHT EMITTING DIODE

LF LINEAR FEET

LH LEFT HAND

LIN LINEAR

LIQ LIQUID

LKR LOCKER

LG LONG

LL LEAD LINED

LLV LONG LEG VERTICAL

LP LOW POINT

LRG LARGE

LT LIGHT

LT WT LIGHTWEIGHT

LVR LOUVER

MATL MATERIAL

MAS MASONRY

MAX MAXIMUM

MECH MECHANICAL

MTL METAL

MFR MANUFACTURER

MH MANHOLE

MIN MINIMUM

MISC MISCELLANEOUS

MO MASONRY OPENING

MP MOP PLATE

MTD MOUNTED

N NORTH

NA NOT APPLICABLE

NEC NATIONAL ELECTRICAL CODE

NEG NEGATIVE

NFC NATIONAL FIRE CODE

NFPA NATIONAL FIRE PROTECTION

ASSOCIATION

NIC NOT IN CONTRACT

NO NUMBER

NOM NOMINAL

NTS NOT TO SCALE

OA OVERALL

OC ON CENTER

OD OUTSIDE DIAMETER / DIMENSION

OFF OFFICE

OH OPPOSITE HAND

OPNG OPENING

OPP OPPOSITE

OH OVERHEAD

OZ OUNCE

PAV PAVING

PC PRECAST CONCRETE

PL PLATE

PLAM PLASTIC LAMINATE

PLAS PLASTER

PLYWD PLYWOOD

PLBG PLUMBING

PMF PREMOLDED FILLER

PR PAIR

PT POINT

PTN PARTITION

QT QUARRY TILE

R RADIUS, RISER

RA RETURN AIR

RAD RADIUS

RB RESILIENT BASE, RUBBER

BASE

RD ROOF DRAIN

RL ROOF LEADER

REF REFERENCE

REFR REFRIGERATOR

REQ'D REQUIRED

REV REVISION

RFI REQUEST FOR

INFORMATION

RFP REQUEST FOR PROPOSAL

RH RIGHT HAND

RM ROOM

RO ROUGH OPENING

S SOUTH

SA SUPPLY AIR

SAN SANITARY

SC SOLID CORE

SCHED SCHEDULE

SECT SECTION

SH SPRINKLER HEAD

SHT SHEET

SIM SIMILAR

SM SMOKE

SPEC SPECIFICATION

SPKR SPEAKER

SQ SQUARE

STA STATION

STD STANDARD

STO STORAGE

STL STEEL

SS STAINLESS STEEL

STOR STORAGE

STRUCT STRUCTURAL

SUSP SUSPENDED

SYM SYMMETRICAL

SYS SYSTEM

T TREAD

TEL TELEPHONE

TEMP TEMPERED

T&G TONGUE AND GROOVE

THK THICK

TOC TOP OF CONCRETE

TOP TOP OF PAVEMENT

TOS TOP OF STEEL

TOW TOP OF WALL

TV TELEVISION

TYP TYPICAL

UNFIN UNFINISHED

UON UNLESS OTHERWISE

NOTED

VB BAPOR BARRIER

VERT VERTICAL

VCT VINYL COMPOSITION TILE

VIF VERIFY IN FIELD

VTR VET THRU ROOF

W WEST

W/ WITH

WD WOOD

W/O WITHOUT

WP WATERPROOF

WT WEIGHT

WWF WELDED WIRE FRAME

NOTE: ALL ABBREVIATIONS SHOWN

MAY NOT BE USED ON THIS PROJECT.

CERTAIN COMMON ABBREVIATIONS

MAY NOT BE SHOWN.

L

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

MEP ENGINEER:

HUITT-ZOLLARS, INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102 817-335-3000 POC: Joel Colwell jcolwell@Huitt-Zollars.com

ARCHITECT:

CB DESIGN GROUP

421 KING STREET

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

POC: PAUL W. BRIDGES

PROFESSIONAL SEAL:

Olin E. Teague VA Medical Center 1901 Veterans Memorial Drive Temple, TX 76504

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

12/20/2021

674-20-01

JSAL

A/E DESIGN SERVICES TO

REPLACE AHUs BLDG. 204

(COVID UNIT, WARDS 6J-6K)

100% BID SET SUBMISSION

SYMBOLS, ABBREVIATIONS & NOTES

GI200

-2

-0

G I2

.p d f

SYMBOLS OF MATERIALS DRAWING KEY ARCHITECTURAL ABBREVIATIONS

ALongeau

G1 ITEMS AND CONDITIONS NOTED, DETAILED, OR OTHERWISE IDENTIFIED ON DRAWINGS ARE APPLICABLE AND BINDING TO SIMILAR CONDITIONS ON ALL DRAWINGS. FOR CONDITIONS NOT NOTED OR NOT DETAILED, PROVIDE MATERIALS OF EQUAL QUALITY AND PERFORMANCE TO OTHER SIMILAR

CONDITIONS ON THE JOB.

G2 SECTIONS SHOWN ARE INTENDED TO SHOW THE SPECIFIC CONSTRUCTION WHERE INDEXED AS WELL AS ESTABLISH THE GENERAL CONSTRUCTION DETAILS FOR SECTIONS THROUGHOUT THE PROJECT WHICH DO NOT HAVE SPECIFIC SECTIONS DRAWN. THE MOST SIMILAR SECTION SHALL BE ADAPTED TO ANY SECTION NOT DETAILED. ANY SPECIFIC QUESTIONS CONCERNING CONSTRUCTION NOT ADEQUATELY COVERED BY THE ABOVE

SHOULD BE DIRECTED TO THE ARCHITECT DURING THE BID PERIOD.

G3 ALL CONSTRUCTION IS TO BE ASSUMED NEW AND FURNISHED AND INSTALLED BY THE CONTRACTOR, UNLESS NOTED OTHERWISE.

G4 REFER TO MECHANICAL AND ELECTRICAL DRAWINGS FOR NOTED PERTAINING TO THEIR PARTICULAR TRAFES. COORDINATE THE WORK OF ALL TRADES AND REPORT TO THE ARCHITECT ANY PERCEIVED DISCREPENCIES. CONTRACTOR SHALL BE RESPONSIBLE FOR ESTABLISHING SEQUENCES OF CONSTRUCTION AND MEANS AND METHODS FOR HOW TO PERFORM THE WORK REQUIRED IN THE CONTRACT DOCUMENTS. ALL CONTRACTORS SHALL CAREFULLY REVIEW ALL EXISTING CONDITIONS AND DETERMINE THE MOST FEASIBLE SEQUENCE FOR PERFORMING THE NEW WORK SO AS TO AVOID

CONFLICTS IN THE FIELD.

G5 ANY AREAS OR SPACES NOT CLEARLY DEFINED OR INDICATED BY NOTED SHALL BE OF SAME MATERIAL AND FINISH AS AREAS OF SIMILAR USE OR

FUNCTION ELSEWHERE IN THE BUILDING.

G6 WALL AND CEILING FINISHES SHALL INCLUDE PROJECTIONS, BEAM ENCLOSURES, RECESSES, BULKHEADS, PILASTERS AND

G7 ALL APPURTENANCES BUILT INTO OR THROUGH WALLS, INCLUDING DOORS, WINDOWS, DUCTS, FRAMES, LOUVRES, GRILLES, MECHANICAL WORK, ETC., SHALL FIT SNUGLY AND BE THOROUGHLY SEALED AROUND PERIMETERS. INSTALL FIRE SEALANT AROUND ALL PENETRATIONS THROUGH FLOORS, FIRE RATED WALLS AND SMOKE PARTITIONS. WORK AT EXTERIOR WALLS SHALL BE FLASHED OR OTHERWISE WATERPROOF SEALED.

G8 FIELD CHECK ROUGH AND/OR FINISHED DIMENSIONS FOR ACCURATE FITTING OF CABINETS, COUNTERS, STOREFRONT, DOORS, FRAMES, FIXTURES, MILLWORK, AND ALL OTHER INSTALLATIONS PRIOR TO SHOP OR FACTORY FABRICATION. PROVIDE AND INSTALL NECESSARY FILLER STRIPS, SCRIBE STRIPS, BASES, CLOSURES, FINISHES AND TRIM TO COMPLETE SUCH INSTALLATIONS. DIMENSIONS OF SUCH INSTALLATIONS SHALL BE CONSIDERED "NOMINAL." CONTRACOTRS SHALL ACCOUNT FOR ALL MANUFACTURER'S REQUIRED TOLERANCES, CLEARANCES AND SHIM SPACE TO ENSURE PROPER

INSTALLATION OF THE NEW WORK.

G9 SEE EQUIPMENT PLANS AND FLOOR PLANS FOR CASEWORK, CABINETS, MILLWORK AND OTHER BUILT-IN ITEMS. COORDINATE WITH MEP DRAWINGS FOR

SINKS, OUTLETS, AND OTHER ITEMS TO BE BUILT INTO SUCH ITEMS.

G10 IF A DISCREPANCY APPEARS TO EXIST BETWEEN DRAWINGS OF DIFFERENT SCALES, CONSULT ARCHITECT FOR CLARIFICATION.

G11 IF A DISCREPANCY APPEARS TO EXIST BETWEEN DRAWINGS AND/OR SPECIFICATIONS, THE MORE STRINGENT (TYPICALLY THE MORE COSTLY) REQUIREMENT SHALL APPLY. ITEMS DESCRIBED ON DRAWINGS, BUT NOT SPECIFIED, SHALL BE PROVIDED. CONTRACTOR SHALL BE RESPONSIBLE TO SUBMIT AN RFI TO SEEK CLARIFICATION OF ANY PERCEIVED DISCREPENCY DURING BID PHASE.

G12 WRITTEN INFORMATION ON DRAWINGS TAKES PRECEDENT OVER DRAWING LINES.

G13 IN THE ABSENCE OF A WRITTEN DIMENSION, OR IN CASE OF DOUBT AS TO THE PROPER MEASUREMENT, CONSULT ARCHITECT. DO NOT SCALE DRAWINGS. ASSUMPTIONS MADE, OR ACTIONS TAKEN, BASED ON SCALED DIMENSIONS SHALL BE AT THE CONTRACTOR'S RISK AND ANY RESULTING CORRECTIONS SHALL BE PERFOMRED BY CONTRACTOR AT NO ADDITIONAL COST TO THE GOVERNMENT.

G14 EACH CONTRACTOR OR SUB-CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WITH THE WORK OF OTHER TRADES SHOWN THROUGHOUT THE COMPLETE SET OF CONTRACT DOCUMENTS. CHANGES RESULTING FROM A CONTRACTOR OR SUB-CONTRACTOR'S FAILURE TO OPTAIN AND REVIEW A COMPLETE SET OF CONTRACT DOCUMENTS SHALL BE CORRECTED AT NO ADDITIONAL COST TO THE GOVERNMENT.

G15 AT ALL CHANGES IN FLOOR FINISHES, PROVIDE AND INSTALL AN APPROPRIATE TRANSITION STRIP AS SHOWN ON THE DRAWINGS.

G16 CONSULT HVAC AND ELECTRICAL DRAWINGS FOR LOCATIONS AND DESCRIPTIONS OF ACCESS PANELS, LOUVER OPENINGS, VENTILATORS, GRILLES, VALVE CABINETS, FIRE DAMPERS OR OTHER APPURTENANCES AFFECTING WALLS, CEILINGS OR FLOORS AND PROVIDE NECESSARY LINTELS, SUPPORT

OR ANCHORING

G17 ELECTRIC SWITCHES, OUTLETS, THERMOSTATS, CONTROLS, CLOCKS, SPEAKERS, OR OTHER WALL-MOUNTED ACCESSORIES SHALL BE INSTALLED IN LOCATIONS WHICH ARE UNOBSTRUCTED BY CABINETS, COUNTERS, RACKS, MARKER AND TACKBOARDS, FIXTURES, SHELVING OR OTHER FURNISHING OR EQUIPMENT DESIGNATED FOR SPACES SHOWN ON DRAWINGS. ITEMS FOR WALL-MOUNTING ARE NOT TO BE INSTALLED ON, THROUGH, OR INTO, ANY

EQUIPMENT OTHER THAN WALLS, UNLESS SPECIFICALLY NOTED OTHERWISE.

G18 ELECTRICAL OUTLETS, CLOCKS, P.A. SPEAKERS, PULL STATIONS, EXIT SIGNS, OR OTHER DEVICES SHOWN DIAGRAMMATICALLY ON THE ARCHITECTURAL DRAWINGS SERVE TO ALERT CONTRACTORS OF THE PRESENCE OF SUCH DEVICES. CONSULT THE ELECTRICAL DRAWINGS FOR FURTHER INFORMATION AND ADVISE ARCHITECT OF ANY PERCEIVED DISCREPENCY BETWEEN ARCHITECTURAL AND ELECTRICAL DRAWINGS REGARDING LOCATION OR TYPE OF

DEVICES SHOWN PRIOR TO PREPARING SUBMITTALS.

G19 ELECTRIC SWITCHES, THERMOSTATS OR OTHER ELECTRONIC CONTROLS IN THE SAME VICINITY SHALL BE MOUNTED AT THE SAME HEIGHT FROM FLOOR

(UNLESS NOTED OTHERWISE) IN A UNIFORM, ORDERLY FASHION.

G20 SUBMITTAL REVIEW - THE CONTRACT DOCUMENTS PROVIDE SIZES, DIMENSIONS, PRODUCT REQUIREMENTS, ETC. CONTRACTOR SHALL VERIFY THAT SUBMITTALS ARE COORDINATED WITH THE REQUIREMENT OF THE CONTRACT DOCUMENTS PRIOR TO SUBMISSION. A/E REVIEW OF SUBMITTALS IS NOT FOR THE PURPOSE OF DETERMINING THAT SIZES, DIMENSIONS, ETC MATCH WHAT HAS ALREADY BEEN PROVIDED IN THE CONTRACT DOCUMENTS. ALL DEVIATIONS FROM WHAT IS SHOWN ON THE CONTRACT DOCUMENTS SHALL BE CLOUDED ON THE SUBMITTAL OR OTHERWISE CLEARLY BROUGHT TO THE ATTENTION OF THE REVIEWER. FAILURE TO CLEARLY BRING ANY DEVIATION(S) TO THE ATTENTION OF THE REVIEWER SHALL BE UNDERSTOOD BY ALL PARTIES THAT WHAT IS SHOWN IN THE SUBMITTAL COMPLIES WITH THE CONTRACT DOCUMENTS REGARDLESS OF WHETHER OR NOT THE REVIEWER DISCOVERS THE DEVIATION. CHANGES RESULTING FROM THE CONTRACTOR'S FAILURE TO CLEARLY IDENTIFY DEVIATIONS IN SUBMITTALS SHALL BE THE CONTRACTOR'S SOLE RESPONSIBILITY AND SHALL BE CORRECTED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE GOVERNMENT.

G21 CONTRACTORS SHALL CAREFULLY REVIEW EXISTING FIELD CONDITIONS AND COORDINATE ALL QUANTITIES, DIMENSIONS, AND TOLERANCES REQUIRED TO PERFORM THE WORK SHOWN ON THE CONTRACT DOCUMENTS. CONTRACTOR IS RESPONSIBLE FOR DETERMINING INFORMATION THAT PERTAINS SOLELY TO FABRICATION PROCESSES, INSTALLATION TECHNIQUES (MEANS AND METHODS), AND SEQUENCING OF THE WORK TO MEET THE REQUIREMENTS OF THE PROJECT SCHEUDLE. EACH SUBCONTRACTOR SHALL COORDINATE WITH OTHER TRADES PRIOR TO BEGINNING THEIR PORTION

OF THE WORK.

G22 PUBLIC EXITS SHALL REMAIN CLEAR AT ALL TIMES WHILE THE BUILDING IS OCCUPIED. NO STORAGE SHALL BE PERMITTED IN THE EXIT ACCESS.

G23 PATCH ALL HOLES IN FLOORS, WALLS, AND CEILINGS WITHIN THE PROJECT LIMITS AFTER DEMOLITION AND NEW WORK IS COMPLETE.

G24 UNLESS SPECIFIC DIMENSIONS ARE PROVIDED, MEP DRAWINGS ARE CONSIDERED "DIAGRAMMATIC." IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR(S) TO FIELD COORDINATE LOCATIONS, SEQUENCES, ETC FOR UNOBSTRUCTURED INSTALLATION OF ITEMS THAT ARE SHOWN ON MEP DRAWINGS IN DIAGRAMMITIC FORM. COORDINATE ABOVE-CEILING WORK OF MEP TRADES TO THAT EACH TRADE LOCATES THEIR WORK AS TIGHT TO THE STRUCTURE/DECK ABOVE AS IS FEASIBLE. EACH SUCCESSIVE TRADE SHALL LOCATE THEIR WORK AS TIGHT TO THE TRADE BEFORE.

G25 THE DRAWINGS AND SPECIFICATIONS ARE COMPLIMENTARY AND NEITHER SHALL TAKE PRECEDENT OVER THE OTHER. WHAT IS REQUIRED BY EITHER THE DRAWINGS OR SPECIFICATIONS SHALL BE INTERPRETED AS BEING REQUIRED AS PART OF THE SCOPE OF WORK FOR THIS PROJECT. ITEMS SPECIFIED, BUT NOT INDICATED ON THE DRAWINGS, SHALL BE PROVIDED. ITEMS SHOWN ON THE DRAWINGS, BUT NOT SPECIFIED, SHALL BE PROVIDED.

IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO SEEK CLARIFICATION OF AN APPARENT DISCREPENCY BETWEEN DRAWINGS AND/OR SPECIFICATIONS DURING THE BIDDING PHASE. OTHERWISE, THE CONTRACTOR SHALL ASSUME THE MOST STRINGENT (TYPICALLY THE MOST

EXPENSIVE) REQUIREMENT SHALL APPLY

1. HOSPITAL STAFF SHALL ENSURE THE REMOVAL OF ANY MEDICAL WASTE, INCLUDING SHARPS CONTAINERS, FROM AREAS TO BE RENOVATED, PRIOR

TO THE START OF THE PROJECT.

2. INFECTION CONTROL SHALL BE NOTIFIED BY FACILITIES MANAGEMENT STAFF IMMEDIATELY IF UNEXPECTED MEDICAL WASTE IS ENCOUNTERED.

IN STRIVING TO PROVIDE A HEALTHY AND SAFE ENVIRONMENT AT VA FACILITIES, VHA IS IMPLEMENTING A SMOKE-FREE POLICY FOR ALL VHA HEALTH CARE FACILITIES AND PROPERTY ASSIGNED TO VHA THAT IS UNDER THE CHARGE AND CONTROL OF VA. THE POLICY APPLIES TO CIGARETTES, CIGARS, PIPES OR ANY OTHER COMBUSTION OF TOBACCO, INCLUDING BUT NOT LIMITED TO ELECTRONIC OR E-CIGARRETES, VAPE PENS OR E-CIGARS.

UNDER VHA DIRECTIVE 1085, ALL VHA HEALTH CARE FACILITIES WILL BE SMOKE-FREE FOR PATIENTS, VISITORS, CONTRACTORS, VOLUNTEERS AND

VENDORS EFFECTIVE OCTOBER 1, 2019.

1. ISOLATE HVAC SYSTEM IN AREA WERE WORK IS TO BE DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM.

2. MAINTAIN NEGATIVE AIR PRESSURE AT ALL TIMES WITH NO DISRUPTION OF THE AIR SYSTEMS OF THE ADJACENT AREAS. INSTALL HEPA (HIGH EFFICIENCY PARTICULATE ACCUMULATOR) FILTER VACUUM SYSTEM RATED AT 95% CAPTURE OF 0.3 MICRONS INCLUDING

EFFECTIVE FOR POLLEN, MOLD SPORES

1. VA DESIGN MANUAL (PG-18-0)

2. VA DESIGN, QUALITY, AND STANDARD ALERTS

3. VA DESIGN GUIDES (PG-18-12)

4. VA DESIGN AND CONSTRUCTION PROCEDURES (PG-18-3)

5. PHYSICAL SECURITY DESIGN MANUAL FOR VA FACILITIES

6. VA FIRE PROTECTION DESIGN MANUAL

7. VA BARRIER FREE DESIGN GUIDE (PG-18-3)

8. VA SIGNAGE DESIGN GUIDE

9. VA MASTER SPECIFICATIONS

10. VA SUSTAINABLE DESIGN MANUAL

1. THESE PLANS DEPICT AREAS WHERE MATERIAL SAMPLES SHOWED THE PRESENCE OF ASBESTOS CONTAINING MATERIALS AND / OR LEAD- BASED PAINT. THESE PLANS ARE ONLY REPRESENTATIVE OF A LIMITED NUMBER OF SAMPLES AND SHALL NOT BE ASSUMED TO BE THE ONLY

LOCATIONS OF THESE MATERIALS.

2. TESTING SHOWS THAT THE FOLLOWING ITEMS / MATERIALS PRESENT THROUGHOUT THIS PROJECT CONTAIN LEAD-BASED PAINT (LBP):

2.1. OFF-WHITE PLASTER WALLS

2.2. WHITE METAL RADIATOR COVERS

2.3. CERAMIC TILE WALLS AND FLOORS

2.4. OFF-WHITE METAL DOOR FRAMES

2.5. BROWN PLASTER BASEBOARD

2.6. RED PLASTER FIRE CABINETS

2.7. OFF-WHITE METAL / PLASTER PIPE COLUMNS

2.8. OFF-WHITE BRICK / DRYWALL / PLASTER WALLS

3. TESTING SHOWS THAT THE FOLLOWING ITEMS / MATERIALS PRESENT THROUGHOUT THIS PROJECT ARE ASBESTOS CONTAINING MATERIALS

(ACM):

3.1. AIRCELL TSI INSULATION - WHITE AND GRAY

3.2. WHITE TSI

3.3. RAISED FLOOR FOOT MASTIC - BLACK

3.4. TAN VINYL FLOOR TILE (VFT)

3.5. BLACK MASTIC ASSOCIATED WITH BEIGE VFT

3.6. OFF-WHITE FIBERGLASS BRIDGING PAINT

3.7. MIXED CARPET MASTIC - BLACK / YELLOW

4. CONTRACTOR SHALL ASSUME THAT ACM'S ARE PRESENT WITHIN CONCEALED SPACES SUCH AS PIPE CHASES AND THE CRAWL SPACE AND

SHALL REMOVE AND DISPOSE OF ALL SUCH MATERIALS ENCOUNTERED.

5. MATERIALS INDICATED ON THIS PLAN SERVE ONLY TO ALERT THE CONTRACTOR TO THEIR PRESENCE ON THIS PROJECT. EPA REGULATIONS STIPULATE THAT IF ONE SAMPLE OF A MATERIAL IS FOUND TO CONTAIN ASBESTOS THEN THE ENTIRE QUANTITY OF THAT MATERIAL CONTAINS ASBESTOS, REGARDLESS OF ADDITIONAL ANALYSIS. CONTRACTOR SHALL REMOVE ALL SIMILAR MATERIALS WITHIN THE ENTIRE PROJECT

SCOPE.

6. THIS PLAN IS BASED ON THE "HAZARDOUS MATERIALS SURVEY REPORT DATED OCTOBER 25, 2019 BY ECS, LTD." AND SERVES ONLY AS A SUMMARY OF SOME INFORMATION FOUND IN THAT DOCUMENT. REFER TO SECTION 02 82 11 TRADITIONAL ASBESTOS ABATEMENT, 02 83 33.13 LEAD-BASED PAINT REMOVAL & DISPOSAL AND THE "HAZARDOUS MATERIALS SURVEY", INCLUDED IN THE PROJECT SPECIFICATION MANUAL, FOR ADDITIONAL INFORMATION AND REQUIREMENTS.

1. CONTRACTOR SHALL PROVIDE EVERYTHING NEEDED FOR INFECTION

CONTAINMENT/CONTROL SYSTEM. SOME ITEMS MAY INCLUDE, BUT ARE NOT LIMITED TO;

CONSTRUCTION ZONE SIGNS, HEPA FILTERS, AIR SCRUBBERS, ETC. CONTACT RESIDENT

ENGINEER, FACILITY INFECTION CONTROL RISKS ASSESSMENT TEAM (ICRA) FOR FULL

PROCEDURE REQUIREMENTS.

2. IT IS RECOMMENDED THAT THE CONTRACTOR UTILIZES MOVEABLE CONTAINMENT SYSTEM,

CONSTRUCTED OF A MINIMUM 6ML POLY OR PREFABRICATED ZIP WALL THAT CAN BE

SEALED TO WORK AREAS. THE INTEGRITY OF THE BARRIER WALLS MUST ASSURE A

COMPLETE SEAL OF THE CONSTRUCTION AREA FROM ADJACENT AREAS. REFER TO THE

TWO ICRA SHEETS - GC301 AND GC302.

3. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL SUBMIT CONTAINMENT/CONTROL

SYSTEM PLAN TO COR FOR APPROVAL, INCLUDING PERIODIC STATUS REPORTS, AND SUBMIT

TO THE VA RESIDENT ENGINEER AND FACILITY ICRA TEAM FOR REVIEW FOR COMPLIANCE

WITH CONTRACT REQUIREMENTS. ALL PERSONNEL INVOLVED IN THE CONSTRUCTION SHALL

BE EDUCATED AND TRAINED IN INFECTION PREVENTION MEASURES ESTABLISHED BY THE

MEDICAL CENTER AND SHALL FOLLOW INFECTION CONTROL PROCEDURES.

4. IN EACH CONSTRUCTION AREA, THE CONTRACTOR SHALL UTILIZE A 120V HEPA FILTER

EQUIPPED AIR SCRUBBER MACHINE.

5. DO NOT REMOVE CONSTRUCTION BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT

IS SIGNED OFF BY COR AND VA'S INFECTION CONTROL DEPARTMENT.

6. PROVIDE DUST “STICKY” MAT AT EACH ENTRANCE/EXIT OF CONSTRUCTION AREA AND

REPLACE OR CLEAN WHEN NO LONGER EFFECTIVE.

7. ALL FURNITURE AND EQUIPMENT (IF APPLICABLE) SHALL BE PROTECTED DURING

DEMOLITION AND CONSTRUCTION.

GENERAL NOTES

1. DEPICTION OF EXISTING CONDITIONS BASED ON ORIGINAL CONSTRUCTION DOCUMENTS AND

LIMTED FIELD OBSERVATIONS. EXISTING ELEMENTS AND CONDITIONS CONCEALED BY IN-

PLACE EQUIPMENT AND FINISHES WERE NOT OBSERVED OR INVESTIGATED. ONCE CUTTING

AND SELECTIVE DEMOLITION WORK IS COMPLETE, REPORT ANY CONFLICTS TO COR/RE.

2. VAMC EQUIPMENT SUPPLIER TO REMOVE EXISTING UNMOUNTED AND MOUNTED EQUIPMENT

PRIOR TO CONSTRUCTION. ONCE OWNER & EQUIPMENT SUPPLIER HAS REMOVED

EQUIPMENT, PHOTOGRAPHICALLY DOCUMENT ENTIRE AREA OF NEW WORK. TAKE NOTE OF

ANY DAMAGED SURFACES OR ELEMENTS. PREPARE WRITTEN AND PHOTOGRAPHIC REPORT

OF SURVEY AND SUBMIT TO OWNER AND DESIGNER.

3. PROTECT ALL EXISTING FINISHES AND ELEMENTS TO REMAIN. REPAIR OR REPLACE

DAMAGED SURFACES TO MATCH ADJACENT FINISHES.

REMOVAL OF IN-PLACE CONSTRUCTION NECESSARY TO PERMIT INSTALLATION OR

PERFORMANCE OF OTHER WORK.

FITTING AND REPAIR WORK REQUIRED TO RESTORE SURFACES TO ORIGINAL

CONDITIONS AFTER INSTALLATION OF OTHER WORK.

DETACH ITEMS FROM EXISTING CONSTRUCTION AND LEGALLY DISPOSE OF THEM OFF-

SITE, UNLESS INDICATED TO BE SALVAGED OR REMOVED AND REINSTALLED.

DETACH ITEMS FROM EXISTING CONSTRUCTION AND DELIVER THEM TO OWNER

READY FOR REUSE.

DETACH ITEMS FROM EXISTING CONSTRUCTION, PREPARE THEM FOR REUSE, AND

REINSTALL THEM WHERE INDICATED.

EXISTING ITEMS OF CONSTRUCTION THAT ARE NOT TO BE REMOVED AND THAT ARE

NOT OTHERWISE INDICATED TO BE REMOVED, REMOVED AND SALVAGED, OR

REMOVED AND REINSTALLED.

DEFINITIONS

CUTTING:

PATCHING:

REMOVE:

SALVAGE:

REMOVE AND

REINSTALL:

EXISTING TO

REMAIN:

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

MEP ENGINEER:

HUITT-ZOLLARS, INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102 817-335-3000 POC: Joel Colwell jcolwell@Huitt-Zollars.com

ARCHITECT:

CB DESIGN GROUP

421 KING STREET

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

POC: PAUL W. BRIDGES

PROFESSIONAL SEAL:

Olin E. Teague VA Medical Center 1901 Veterans Memorial Drive Temple, TX 76504

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

12/20/2021

674-20-01

JSAL

A/E DESIGN SERVICES TO

REPLACE AHUs BLDG. 204

(COVID UNIT, WARDS 6J-6K)

100% BID SET SUBMISSION

GENERAL NOTES

GI300

-2

-0

G I3

.p d f

GENERAL NOTESHAZARDOUS MATERIALS NOTES

REFERENCES

SMOKING POLICY

ENVIRONMENTAL CONTROL NOTES

MEDICAL WASTE NOTES

(THESE NOTES APPLY TO THE COMPLETE SET OF CONSTRUCTION DOCUMENTS)

NOTE: SEE LIFE SAFETY DRAWINGS FOR SPECIFIC EDITIONS OF APPLICABLE CODES

INFECTION CONTROL NOTES

DEMOLITION NOTES

ALongeau

UP

EFGJ.5IKLMNPQ.5RsUVWY

AREA J

AREA K

7' - 0"

IK1

IK2

IK2

IK2

IK1

IK3

IK3

STAIR 10

6S-10

STORAGE

6J07

PATIENT

6J8

TOILET

6J6A

PATIENT

6J9

TOILET

6J8A

PATIENT

6J6

PATIENT

6J10

WAITING

6J5 TOILET

6J09A

PATIENT

6J11

CORRIDOR

C6-3

PATIENT

6J4

PATIENT

6J12

TOILET

6J12A

TOILET

6J1A

PATIENT

6J3

TOILET

6J03A

MED

6J2

WAITING

6J13

COPY

6J1

LOUNGE

6J40

UNIT MANAGER

6J39

OFFICE

6J38

W.C.

6J32

DICT.

6J33

CONFERENCE

6G32

C&P CHECK-IN

C6-4

SOILED UTILITY

6J28

STORAGE

6J27

PATIENT

6J26

TOILET

6J26A

BREAK

6G30

OEF/ OIF OFFICE

6J29

TOILET

6J25A

VEST.

6J25B

PATIENT

6J25

PATIENT

6J24

TOILET

6J24A

VEST.

6J23B

STORAGE

6J22

ELECTRICAL

6K11

STORAGE

6J22A

TOILET

6J23A

TOILET

6K09A

PATIENT

6K10

TOILET

6K13A

PATIENT

6K14

PATIENT

6K13

MECHANICAL ROOM

6K12

PATIENT

6J21

TOILET

6J20A

TOILET

6J18A

TOILET

6J16A

PATIENT

6J16

PATIENT

6J17

PATIENT

6J18

PATIENT

6J19

PATIENT

6J20

CORRIDOR

C6-5

6J

6J

6K

A6

GC301

XC6-4AT

XC6-4BT

4'

6"

A6

GC301

IK3

MIN.

6' - 0"

SECTION EXISTING FLOOR FINISH/ BASE

UNDERSIDE OF STRUCTURE

EXISTING FINISHED CEILING

SYSTEM

METAL "C-H" STUDS (20 GA.) @ 24" O.C. W/

1" GYP. BD. SHAFTLINER (UPPER SIDE) &

5/8" TYPE "X" GYP. BD. OPPOSITE SIDE.

FIRE RATED PARTITION U.L. DES. NO. U415

RUNNER CHANNEL SET IN TWO CONT. BEADS

OF SEALANT AND FASTENED TO STUDS

SOUND ATTENUATION BLANKET INSUL.

METAL STUDS W/ 5/8" TYPE "X" GYP.

BD., EACH SIDE. FIRE RATED PARTITION

UL DES. NO 465

OUTLINE OF EXISTING WALL

RUNNER CHANNEL MECHANICALLY

FASTENED TO FLOOR, APPLY TWO CONT.

BEADS OF FIRE/ ACOUSTICAL SEALANT AT

EACH SIDE

HEAVY WEIGHT RESIN PAPER EXTEND 8"

EACH SIDE MIN. OF TEMPORARY PARTITION.

NOTE: IF NOT PHYSICALLY FEASIBLE TO EXTEND THE TEMPORARY

PARTITION FULL HEIGHT TO UNDERSIDE OF STRUCTURE ABOVE RETURN

PARTITION PERPENDICULAR TO WALL/ SOFFIT TO ENCLOSE WORK AREA

KEY PLAN

NOT TO SCALE

PLAN

NORTH

TRUE

NORTH

AREA J

AREA K

AREA G

ICRA KEY NOTES

IK1 AIRTIGHT ANTEROOM

IK2 TEMPORARY WALK-OFF MAT

IK3 HEPA FILTER EXHAUST FAN SYSTEM VENTED THROUGH OPERABLE WINDOW.

COORDINATE LOCATION OF HEPA FILTER WITHIN CONSTRUCTION ZONE WITH

VA COR.

IK4 DOOR TO BE SEALED OFF FOR DURATION OF CONSTRUCTION

ICRA CONSTRUCTION NOTES

1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT

CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS (I.E. SHEETROCK, PLYWOOD, & PLASTIC) TO SEAL AREA

FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC

COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR

VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR

FILTRATION UNITS. AIR PRESSURE SHALL BE CONTINUOUSLY MONITORED. BALL IN THE

WALL IS NOT ACCEPTABLE FOR MONITORING.

4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES AIRTIGHT AND/OR FIRE SEAL AS

REQUIRED.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM SO

THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE

OR THEY CAN WEAR CLOTH OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY

LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO WEAR SHOE COVERS. SHOE

COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS APPROVED

BY THE COR, INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION

CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL

SEVERIVCES DEPARTMENT.

8. REMOVE CONSTRUCTION WASTE DAILY DURING THE HOURS OUTSIDE OF 0800-1630.

CONSTRUCTION WASTE / RUBBISH MUST BE TRANSPORTED IN TIGHTLY COVERED

CONTAINERS AT ALL TIMES.

9. CONTRACTOR TO USE ROUTE AGREED UPON BY THE ICRA TEAM AND COR FOR

TRANSPORT OF CONTAINERS THROUGH THE FACILITY.

10. PLACE DUST MATS AT ENTRANCE AND EXIT OF WORK AREA.

ICRA REMOVAL NOTES

1. REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS

ASSOCIATED WITH CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED

CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

5. WET MOP AREA WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

ICRA GENERAL NOTES

1. PROVIDE TEMPORARY/ PERMANENT RATED ICRA PARTITIONS AS CONCEPTUALLY

INDICATED ON PLANS. CONTRACTOR SHALL SUBMIT AN ICRA PLAN FOR APPROVAL OF THE

COR PRIOR TO BEGINNING ANY WORK.

2. DOORS IN ICRA PARTITIONS SHALL HAVE CLOSERS, PANIC DEVICES, STOREROOM

FUNCTION LOCKS, AND ALARMS. DOORS SHALL AUTOMATICALLY LOCK UPON CLOSURE.

3. CONTRACTOR SHALL INSTALL "CONSTRUCTION ZONE - AUTHORIZED PERSONNEL ONLY"

SIGN ON THE PUBLIC SIDE OF ALL ICRA DOORS.

4. CONTRACTOR TO COMPLY WITH ALL OSHA REQUIREMENTS PERTAINING TO SILICA AND

DUST CONTAINMENT/ REMEDIATION.

#ICRA MATRIX

UNDER

CONSTRUCTION

NOT IN SCOPE

AREA TO REMAIN

IN USE

ICRA BARRIER

ICRA PLAN KEY

CONSTRUCTION PROJECT

TYPE

A B C D

LOW I II II III/IV

MEDIUM I II III IV

HIGH I II III/IV IV

HIGHEST II III/IV III/IV IV

PATIENT

RISK GROUP

GC ICRA PATH

1. EXECUTE WORK BY METHODS TO MINIMIZE RAISING

DUST FROM CONSTRUCTION OPERATIONS.

2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED

FOR VISUAL INSPECTION.

DURING CONSTRUCTION

PROJECT

UPON COMPLETION OF

PROJECT

1. CLEAN ANY DUST/DEBRIS GENERATED BY PROJECT.

C

LA

S

I

1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST

FROM DISPERSING INTO ATMOSPHERE.

2. WATER MIST WORK SURFACES TO CONTROL DUST

WHILE CUTTING.

3. SEAL UNUSED DOORS WITH DUCT TAPE.

4. BLOCK OFF AND SEAL AIR VENTS.

5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK

AREA.

6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE

WORK IS BEING PERFORMED.

1. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

2. WET MOP AND/OR VACUUM WITH HEPA FILTERED

VACUUM BEFORE LEAVING WORK AREA.

3. REMOVE ISOLATION OF HVAC SYSTEM WHEN JOB IS

COMPLETED.

4. CLEAN TRACKED DUST/DEBRIS IN COMMON AREAS AS

NEEDED; CLEAN AREA AT THE END IF THE WORK DAY.

5. AREA SHOULD BE TERMINALLY CLEANED BY

ENVIRONMENTAL SERVICES PRIOR TO USE.

C

LA

II

1. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE

WORK IS BEING DONE TO PREVENT CONTAMINATION

OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,

PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK

AREA OR IMPLEMENT CONTROL CUBE METHOD (CART

WITH PLASTIC COVERING AND SEALED CONNECTION

TO WORK SITE WITH HEPA VACUUM OR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS).

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE

UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS; OR

HEPA AIR SCRUBBER IF UNABLE TO ACHIEVE NEGATIVE

PRESSURE; FILTER CHANGED AS NEEDED.

4. MAINTAIN STICKY MATS AT ENTRANCE. AVOID

TRACKING DUST/DEBRIS OUTSIDE OF WORK AREA,

CLEAN AREA AS NEEDED.

5. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL

PROJECT IS COMPLETED AND DIRT AND DEBRIS HAS

BEEN REMOVED.

2. WET MOP AND/OR VACUUM WORK AREA WITH HEPA

FILTERED VACUUM.

3. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE

SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

4. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS

WHERE WORK IS BEING PERFORMED.

5. AREA SHOULD BE TERMINALLY CLEANED BY

ENVIRONMENTAL MANAGEMENT SERVICES

DEPARTMENT PRIOR TO USE

C

LA

III

WORK IS BEING DONE TO PREVENT CONTAMINATION

OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,

PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK

AREA OR IMPLEMENT CONTROL CUBE METHOD (CART

WITH PLASTIC COVERING AND SEALED CONNECTION

TO WORK SITE WITH HEPA VACUUM OR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE

UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.

4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES

APPROPRIATELY.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL

PERSONNEL TO PASS THROUGH THIS ROOM SO THEY

CAN BE VACUUMED USING A HEPA VACUUM CLEANER

BEFORE LEAVING WORK SITE OR THEY CAN WEAR

CLOTH OR PAPER COVERALLS THAT ARE REMOVED

EACH TIME THEY LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING WORK SITE AREA

REQUIRED TO WEAR SHOE COVERS. SHOE COVERS

MUST BE CHANGED EACH TIME THE WORKER EXITS

THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL

PROJECT IS COMPLETED PROJECT AND INSPECTED.

8. AREA SHOULD BE TERMINALLY CLEANED BY THE

OWNER’S ENVIRONMENTAL SERVICES DEPARTMENT

PRIOR TO USE.

1. REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE

SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE

COVERING UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

5. WET MOP AREA WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS

WHERE WORK IS BEING PERFORMED.

C

LA

IV

ICRA REFERENCE NOTES

1. BARRIER WALLS:

A. THE CONSTRUCTION AREAS MUST BE KEPT SEPARATED FROM PATIENT CARE AREAS

BY BARRIERS THAT KEEP THE DUST AND DIRT INSIDE THE WORKSITE.

B. THE WALLS MUST PROVIDE A COMPLETE SEAL OF THE CONSTRUCTION AREA FROM

ADJACENT AREAS (WALLS MAY BE RIGID OR 4 OR 6 MIL THICKNESS PLASTIC).

2. ENVIRONMENTAL CONTROL:

A. NEGATIVE AIR PRESSURE MUST BE MAINTAINED WITHIN THE CONSTRUCTION AREA

WHEN POSSIBLE. IF UNABLE TO MAINTAIN NEGATIVE PRESSURE A HEPA AIR-

SCRUBBER MUST BE USED AND LEFT ON FOR THE DURATION OF THE PROJECT (24/7).

B. DEMOLITION DEBRIS IS REMOVED IN TIGHTLY FITTED COVERED CARTS – USE

SPECIFIED TRAFFIC PATTERNS.

C. STICKY OR WALK-OFF MATS ARE PLACED IMMEDIATELY OUTSIDE THE CONSTRUCTION

ZONE AND CHANGED WHENEVER NECESSARY TO CONTROL THE SPREAD OF DUST

AND DIRT.

D. EXTERIOR WINDOW SEALS ARE TO BE USED TO REDUCE THE AMOUNT OF OUTSIDE

EXCAVATION DEBRIS COMING INTO THE BUILDING.

E. IF DEMOLITION CHUTES ARE USED, THEY MUST BE SEALED WHEN NOT IN USE; THE

CHUTE AND DAMPER SHOULD BE SPRAYED WITH WATER, AS NECESSARY TO

MAINTAIN DUST CONTROL

F. CONTROL, COLLECTION AND DISPOSAL MUST BE PROVIDED FOR ANY DRAIN LIQUID OR

SLUDGE FOUND WHEN DEMOLISHING PLUMBING.

3. TRAFFIC CONTROL:

A. USE DESIGNATED ENTRY AND EXIT PROCEDURES.

B. KEEP ALL EGRESS PATHWAYS FREE OF DEBRIS.

C. NO UNAUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER CONSTRUCTION

AREAS.

D. USE DESIGNATED ELEVATORS ONLY.

4. CLEANING:

A. KEEP THE CONSTRUCTION AREA CLEAN ON A DAILY BASIS.

B. DUST AND DIRT MUST BE KEPT TO A MINIMUM.

5. WORKERS:

A. CLOTHING MUST BE FREE OF LOOSE SOIL AND DEBRIS WHEN EXITING THE

CONSTRUCTION AREA.

B. USE PERSONAL PROTECTIVE EQUIPMENT (MASKS, FACE SHIELDS, ETC.) AS INDICATED

FOR THE TASK AT HAND.

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

MEP ENGINEER:

HUITT-ZOLLARS, INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102 817-335-3000 POC: Joel Colwell jcolwell@Huitt-Zollars.com

ARCHITECT:

CB DESIGN GROUP

421 KING STREET

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

POC: PAUL W. BRIDGES

PROFESSIONAL SEAL:

Olin E. Teague VA Medical Center 1901 Veterans Memorial Drive Temple, TX 76504

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

12/20/2021

674-20-01

JSAL

A/E DESIGN SERVICES TO

REPLACE AHUs BLDG. 204

(COVID UNIT, WARDS 6J-6K)

100% BID SET SUBMISSION

ICRA PLAN - AREA J

GC301

-2

-0

G C

/2

/2

.p d f

1/8" = 1'-0"A15

6TH FLOOR ICRA PLAN - AREA J

1 1/2" = 1'-0"A6

ICRA BARRIER ( 1HR FR )

ALongeau

BCDEFGJ.5IKLM

AREA J

AREA K

AREA J

AREA K

IK2

IK1

IK2

IK3

IK3

IK1

IK2

IK4

VEST.

6J23B

STORAGE

6J22

ELECTRICAL

6K11

STORAGE

6J22A

TOILET

6J23A

TOILET

6K09A

PATIENT

6K10

TOILET

6K13A

PATIENT

6K14

PATIENT

6K13

6K

6K

6K

PATIENT

6K15

PATIENT

6K16

PATIENT

6K17

PATIENT

6K18

PATIENT

6K09

PATIENT

6K08

PATIENT

6K07

PATIENT

6K06B

TOILET

6K07A

TOILET

6K08A

TOILET

6K15A

TOILET

6K17A

CLEAN UTILITY

6K19

RESERCH LAB

6K06

OFFICE

6K3

CLASSROOM

6K4

CORRIDOR

C6-2

ICE

6K43

STORAGE

6K42

S. UTILITY

6K44

C. UTILITY

6K45

MED.

6K00A

NURSE STATION

6K00

WOMEN'S HEALTH

CHIEF

6K38

OFFICE

6K41HAC

6K39

IDF

6K40

CORRIDOR

C6-11

STAFF LOUNGE

6K34

W.C.

6K35

OFFICE

6K36

OFFICE

6K37

LINEN

6G04

TRASH

6G05

WAITING

6K23

PATIENT

6K24

PATIENT

6K25

PATIENT

6K26

PATIENT

6K27

STAIR 9

6S-9

TOILET

6K28A

PATIENT

6K28

PATIENT

6K29

PATIENT

6K30

PATIENT

6K31

PATIENT

6K32

TOILET

6K31A

TOILET

6K29A

TOILET

6K26A

TOILET

6K25A

CORRIDOR

C6-10

CORRIDOR

C6-10

PATIENT

6K33

ANTE

6K33A

TOILET

6533B

TOILET

6K32B

ANTE

6K32A

A6

GC301

M

IN

6'

0"

MIN.

6' - 0"

ALIGN

8'

A6

GC301

IK3

6K00AT

6K00BT

KEY PLAN

NOT TO SCALE

PLAN

NORTH

TRUE

NORTH

AREA J

AREA K

AREA G

ICRA MATRIX

UNDER

CONSTRUCTION

NOT IN SCOPE

AREA TO REMAIN

IN USE

ICRA BARRIER

ICRA PLAN KEY

CONSTRUCTION PROJECT

TYPE

A B C D

LOW I II II III/IV

MEDIUM I II III IV

HIGH I II III/IV IV

HIGHEST II III/IV III/IV IV

PATIENT

RISK GROUP

GC ICRA PATH

ICRA KEY NOTES

IK1 AIRTIGHT ANTEROOM

IK2 TEMPORARY WALK-OFF MAT

IK3 HEPA FILTER EXHAUST FAN SYSTEM VENTED THROUGH OPERABLE WINDOW.

COORDINATE LOCATION OF HEPA FILTER WITHIN CONSTRUCTION ZONE WITH

VA COR.

IK4 DOOR TO BE SEALED OFF FOR DURATION OF CONSTRUCTION

ICRA CONSTRUCTION NOTES

1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT

CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS (I.E. SHEETROCK, PLYWOOD, & PLASTIC) TO SEAL AREA

FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC

COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR

VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR

FILTRATION UNITS. AIR PRESSURE SHALL BE CONTINUOUSLY MONITORED. BALL IN THE

WALL IS NOT ACCEPTABLE FOR MONITORING.

4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES AIRTIGHT AND/OR FIRE SEAL AS

REQUIRED.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM SO

THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE

OR THEY CAN WEAR CLOTH OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY

LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO WEAR SHOE COVERS. SHOE

COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS APPROVED

BY THE COR, INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION

CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL

SEVERIVCES DEPARTMENT.

8. REMOVE CONSTRUCTION WASTE DAILY DURING THE HOURS OUTSIDE OF 0800-1630.

CONSTRUCTION WASTE / RUBBISH MUST BE TRANSPORTED IN TIGHTLY COVERED

CONTAINERS AT ALL TIMES.

9. CONTRACTOR TO USE ROUTE AGREED UPON BY THE ICRA TEAM AND COR FOR

TRANSPORT OF CONTAINERS THROUGH THE FACILITY.

10. PLACE DUST MATS AT ENTRANCE AND EXIT OF WORK AREA.

ICRA REMOVAL NOTES

1. REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS

ASSOCIATED WITH CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED

CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

5. WET MOP AREA WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

ICRA GENERAL NOTES

1. PROVIDE TEMPORARY/ PERMANENT RATED ICRA PARTITIONS AS CONCEPTUALLY

INDICATED ON PLANS. CONTRACTOR SHALL SUBMIT AN ICRA PLAN FOR APPROVAL OF THE

COR PRIOR TO BEGINNING ANY WORK.

2. DOORS IN ICRA PARTITIONS SHALL HAVE CLOSERS, PANIC DEVICES, STOREROOM

FUNCTION LOCKS, AND ALARMS. DOORS SHALL AUTOMATICALLY LOCK UPON CLOSURE.

3. CONTRACTOR SHALL INSTALL "CONSTRUCTION ZONE - AUTHORIZED PERSONNEL ONLY"

SIGN ON THE PUBLIC SIDE OF ALL ICRA DOORS.

4. CONTRACTOR TO COMPLY WITH ALL OSHA REQUIREMENTS PERTAINING TO SILICA AND

DUST CONTAINMENT/ REMEDIATION.

1. EXECUTE WORK BY METHODS TO MINIMIZE RAISING

DUST FROM CONSTRUCTION OPERATIONS.

2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED

FOR VISUAL INSPECTION.

DURING CONSTRUCTION

PROJECT

UPON COMPLETION OF

PROJECT

1. CLEAN ANY DUST/DEBRIS GENERATED BY PROJECT.

C

LA

I

1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST

FROM DISPERSING INTO ATMOSPHERE.

2. WATER MIST WORK SURFACES TO CONTROL DUST

WHILE CUTTING.

3. SEAL UNUSED DOORS WITH DUCT TAPE.

4. BLOCK OFF AND SEAL AIR VENTS.

5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK

AREA.

6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE

WORK IS BEING PERFORMED.

1. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

2. WET MOP AND/OR VACUUM WITH HEPA FILTERED

VACUUM BEFORE LEAVING WORK AREA.

3. REMOVE ISOLATION OF HVAC SYSTEM WHEN JOB IS

COMPLETED.

4. CLEAN TRACKED DUST/DEBRIS IN COMMON AREAS AS

NEEDED; CLEAN AREA AT THE END IF THE WORK DAY.

5. AREA SHOULD BE TERMINALLY CLEANED BY

ENVIRONMENTAL SERVICES PRIOR TO USE.

C

LA

II

WORK IS BEING DONE TO PREVENT CONTAMINATION

OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,

PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK

AREA OR IMPLEMENT CONTROL CUBE METHOD (CART

WITH PLASTIC COVERING AND SEALED CONNECTION

TO WORK SITE WITH HEPA VACUUM OR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS).

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE

UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS; OR

HEPA AIR SCRUBBER IF UNABLE TO ACHIEVE NEGATIVE

PRESSURE; FILTER CHANGED AS NEEDED.

4. MAINTAIN STICKY MATS AT ENTRANCE. AVOID

TRACKING DUST/DEBRIS OUTSIDE OF WORK AREA,

CLEAN AREA AS NEEDED.

5. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL

PROJECT IS COMPLETED AND DIRT AND DEBRIS HAS

BEEN REMOVED.

2. WET MOP AND/OR VACUUM WORK AREA WITH HEPA

FILTERED VACUUM.

3. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE

SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

4. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS

WHERE WORK IS BEING PERFORMED.

5. AREA SHOULD BE TERMINALLY CLEANED BY

ENVIRONMENTAL MANAGEMENT SERVICES

DEPARTMENT PRIOR TO USE

C

LA

III

WORK IS BEING DONE TO PREVENT CONTAMINATION

OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,

PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK

AREA OR IMPLEMENT CONTROL CUBE METHOD (CART

WITH PLASTIC COVERING AND SEALED CONNECTION

TO WORK SITE WITH HEPA VACUUM OR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE

UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.

4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES

APPROPRIATELY.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL

PERSONNEL TO PASS THROUGH THIS ROOM SO THEY

CAN BE VACUUMED USING A HEPA VACUUM CLEANER

BEFORE LEAVING WORK SITE OR THEY CAN WEAR

CLOTH OR PAPER COVERALLS THAT ARE REMOVED

EACH TIME THEY LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING WORK SITE AREA

REQUIRED TO WEAR SHOE COVERS. SHOE COVERS

MUST BE CHANGED EACH TIME THE WORKER EXITS

THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL

PROJECT IS COMPLETED PROJECT AND INSPECTED.

8. AREA SHOULD BE TERMINALLY CLEANED BY THE

OWNER’S ENVIRONMENTAL SERVICES DEPARTMENT

PRIOR TO USE.

1. REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE

SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT

IN TIGHTLY COVERED CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE

COVERING UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

5. WET MOP AREA WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS

WHERE WORK IS BEING PERFORMED.

C

LA

IV

ICRA REFERENCE NOTES

1. BARRIER WALLS:

A. THE CONSTRUCTION AREAS MUST BE KEPT SEPARATED FROM PATIENT CARE AREAS

BY BARRIERS THAT KEEP THE DUST AND DIRT INSIDE THE WORKSITE.

B. THE WALLS MUST PROVIDE A COMPLETE SEAL OF THE CONSTRUCTION AREA FROM

ADJACENT AREAS (WALLS MAY BE RIGID OR 4 OR 6 MIL THICKNESS PLASTIC).

2. ENVIRONMENTAL CONTROL:

A. NEGATIVE AIR PRESSURE MUST BE MAINTAINED WITHIN THE CONSTRUCTION AREA

WHEN POSSIBLE. IF UNABLE TO MAINTAIN NEGATIVE PRESSURE A HEPA AIR-

SCRUBBER MUST BE USED AND LEFT ON FOR THE DURATION OF THE PROJECT (24/7).

B. DEMOLITION DEBRIS IS REMOVED IN TIGHTLY FITTED COVERED CARTS – USE

SPECIFIED TRAFFIC PATTERNS.

C. STICKY OR WALK-OFF MATS ARE PLACED IMMEDIATELY OUTSIDE THE CONSTRUCTION

ZONE AND CHANGED WHENEVER NECESSARY TO CONTROL THE SPREAD OF DUST

AND DIRT.

D. EXTERIOR WINDOW SEALS ARE TO BE USED TO REDUCE THE AMOUNT OF OUTSIDE

EXCAVATION DEBRIS COMING INTO THE BUILDING.

E. IF DEMOLITION CHUTES ARE USED, THEY MUST BE SEALED WHEN NOT IN USE; THE

CHUTE AND DAMPER SHOULD BE SPRAYED WITH WATER, AS NECESSARY TO

MAINTAIN DUST CONTROL

F. CONTROL, COLLECTION AND DISPOSAL MUST BE PROVIDED FOR ANY DRAIN LIQUID OR

SLUDGE FOUND WHEN DEMOLISHING PLUMBING.

3. TRAFFIC CONTROL:

A. USE DESIGNATED ENTRY AND EXIT PROCEDURES.

B. KEEP ALL EGRESS PATHWAYS FREE OF DEBRIS.

C. NO UNAUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER CONSTRUCTION

AREAS.

D. USE DESIGNATED ELEVATORS ONLY.

4. CLEANING:

A. KEEP THE CONSTRUCTION AREA CLEAN ON A DAILY BASIS.

B. DUST AND DIRT MUST BE KEPT TO A MINIMUM.

5. WORKERS:

A. CLOTHING MUST BE FREE OF LOOSE SOIL AND DEBRIS WHEN EXITING THE

CONSTRUCTION AREA.

B. USE PERSONAL PROTECTIVE EQUIPMENT (MASKS, FACE SHIELDS, ETC.) AS INDICATED

FOR THE TASK AT HAND.

W A

LL

T

H

IC

K N

E S

S

C O

O R

D W

9/

9/

" UON

4"

2" 5/8"

/1 6"

/1 6"

WALL WHERE SHOWN IN

PLAN

DOOR

JAMB ANCHOR

SEALANT TYP. BOTH SIDES,

FULL PERIMETER

5/8" GWB EA. SIDE

H.M. DOOR FRAME

WALL THICKNESS

COORD W/

9/16" 9/16"

2" 5/

8"

1 15/16"1 15/16"

DOOR

JAMB ANCHOR

METAL TRACK

SEALANT TYP. BOTH SIDES,

FULL PERIMITER

5/8" GWB EA. SIDE

METAL STUD BOX HEADER

H.M. DOOR FRAME

F

FLUSH

D O

O R

H E

IG

H

T

AS SCHEDULE

DOOR WIDTH

TYPE 1

(HM - DOOR)

DOOR WIDTH

2" T

Y P

D O

O R

H E

IG

H

T

6" D

O O

R S

TO

P

DOOR TYPE DOOR FRAME TYPE LEGEND

EPY EPOXY FLOORING

EX EXISTING

HW HARDWARE SET (FINISH OR BUILDER'S HARDWARE)

P PAINT (EXTERIOR AND INTERIOR; TRANSPARENT,

SEMI-TRANSPARENT, AND OPAQUE FINISHES)

RB RESILIENT BASE (RUBBER OR VINYL WITH FACTORY

FORMED INSIDE AND OUTSIDE CORNERS)

HM HOLLOW METAL

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

MEP ENGINEER:

HUITT-ZOLLARS, INC.

500 W. 7th St. Ste. 300 Fort Worth, Texas 76102 817-335-3000 POC: Joel Colwell jcolwell@Huitt-Zollars.com

ARCHITECT:

CB DESIGN GROUP

421 KING STREET

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

POC: PAUL W. BRIDGES

PROFESSIONAL SEAL:

Olin E. Teague VA Medical Center 1901 Veterans Memorial Drive Temple, TX 76504

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

12/20/2021

674-20-01

JSAL

A/E DESIGN SERVICES TO

REPLACE AHUs BLDG. 204

(COVID UNIT, WARDS 6J-6K)

100% BID SET SUBMISSION

ICRA PLAN - AREA K

GC302

-2

-0

G C

/2

/2

.p d f

1/8" = 1'-0"A15

6TH FLOOR ICRA PLAN - AREA K

DOOR NO.

ROOM

NAME

DOOR FRAME DOOR

LABEL FIRE

RATING

HARD

WARE

SET REMARKS

NOMINAL SIZE

TYPE MATL MATL TYPE

SECTIONS

WIDTH HEIGHT THK. JAMB HEAD SILL

6K00AT 3' - 6" 7' - 0" 1 3/4" F HM HM 1 A7 / GC302 A5 / GC302 DR: 45 HW-5 TEMP. ICRA DOOR

6K00BT 3' - 6" 7' - 0" 1 3/4" F HM HM 1 A7 / GC302 A5 / GC302 DR: 45 HW-5 TEMP. ICRA DOOR

XC6-4AT 3' - 0" 7' - 0" 1 3/4" F HM HM 1 A7 / GC302 A5 / GC302 DR: 45 HW-5 TEMP. ICRA DOOR

XC6-4BT 3' - 0" 7' - 0" 1 3/4" F HM HM 1 A7 / GC302 A5 / GC302 CR: 45 HW-5 TEMP. ICRA DOOR

DOOR SCHEDULE

M: HM F: P M: HM F: P

M: HM F: P M: HM F: P

M: HM F: P M: HM F: P

M: HM F: P M: HM F: P

1 1/2" = 1'-0"A7

TYP. DOOR JAMB DTL.

1 1/2" = 1'-0"A5

TYP. DOOR HEAD DTL.

CORRIDOR

CORRIDOR

CORRIDOR

CORRIDOR

ALongeau

UP

A

B

C

DN

DN

DN

STORAGE

6J07

STAIR 10

6S-10

PATIENT

6J8

OUTSIDE COURT

TOILET

6J8A

PATIENT

6J9

TOILET

6J6A

PATIENT

6J6

PATIENT

6J10

TOILET

6J09A

WAITING

6J5

PATIENT

6J11

PATIENT

6J12PATIENT

6J4

CORRIDOR

C6-3

TOILET

6J12A

TOILET

6J1A

PATIENT

6J3

MED

6J2

TOILET

6J03A

WAITING

6J13

C&P CHECK-IN

C6-4

COPY

6J1LOUNGE

6J40

UNIT MANAGER

6J39

OFFICE

6J38

STORAGE

6G21A

EMPLOYEE EDU.

CLASSROOM

6G19

OUTDOOR COURT

6G18

STORAGE

6G19A

EQUIP.

6G23

HAC

6G22

COMM

6G21

CONFERENCE

6G32 OEF/ OIF OFFICE

6J29

BREAK

6G30

DICT.

6J33

W.C.

6J32

OEF/ OIF OFFICE

6J31

OEF/ OIF OFFICE

6G24

OEF/ OIF OFFICE

6G25

OEF/ OIF OFFICE

6G26

OEF/ OIF OFFICE

6G27

EED OFFICE

6G28

EED OFFICE

6G29

VISITORS' LOUNGE

6G01

IDC OFFICE

6J16A

IDC OFFICE

6J16B

OFFICE/EXAM

6G16C

OFFICE

6G16D

OFFICE

6G16E

OFFICE

6G16F

OFFICE/EXAM

6G16G

OFFICE

6G16H

INFECTIOUS

DISEASE CLINIC

6G15

INFECTIOUS

DISEASE CLINIC

6G14

ELECTRICAL ROOM

6G13

COMM.

6G20

ELEVATOR LOBBY,

SERVICE

6G12

ELEVATOR LOBBY

6G00

CORRIDOR

C6-1

MENS

6G02

WOMENS

6G03

LOCKERS, WOMEN

6G08

LOCKERS, MEN

6G07

STORAGE

6K42

ICE

6K43

RETHERM

6G11

EMS STORAGE

6G10

EQUIP. STA.

6G06

MECHANICAL

6G09

TRASH

6G05

LINEN

6G04

OFFICE

6K37

OFFICE

6K36

STAFF LOUNGE

6K34

W.C.

6K35

CORRIDOR

C6-11

IDF

6K40

HAC

6K39

OFFICE

6K41

WOMEN'S HEALTH

CHIEF

6K38

S. UTILITY

6K44

C. UTILITY

6K45

MED.

6K00A

NURSE STATION

6K00

CORRIDOR

C6-2

OFFICE

6K3

CLASSROOM

6K4

CLEAN UTILITY

6K19

WAITING

6K23

PATIENT

6K18

PATIENT

6K06B RESERCH LAB

6K06

TOILET

6K17A

TOILET

6K15A

TOILET

6K13A

PATIENT

6K10 PATIENT

6K14

PATIENT

6K15

PATIENT

6K16

PATIENT

6K17

TOILET

6K07A

TOILET

6K08A

PATIENT

6K09

PATIENT

6K08

PATIENT

6K07

MECHANICAL ROOM

6K12

ELECTRICAL

6K11

STORAGE

6J22A

TOILET

6J23A

STORAGE

6J22

VEST.

6J23B

PATIENT

6J23

PATIENT

6J24

PATIENT

6J25

PATIENT

6J26

STORAGE

6J27SOILED UTILITY

6J28

TOILET

6J26A

TOILET

6J25A

VEST.

6J25B

TOILET

6J24A

PATIENT

6J16

PATIENT

6J17

PATIENT

6J18

PATIENT

6J19

PATIENT

6J20

PATIENT

6J21

TOILET

6J20A

TOILET

6J18A

TOILET

6J16A

STAIR 8

5S-8

STAIR 9

6S-9

TOILET

6K28A

PATIENT

6K28

PATIENT

6K29

PATIENT

6K30

PATIENT

6K31

PATIENT

6K32

PATIENT

6K33

TOILET

6533B

TOILET

6K32B

ANTE

6K32A

TOILET

6K31A

TOILET

6K29A

CORRIDOR

C6-10

PATIENT

6K24

PATIENT

6K25

PATIENT

6K26

PATIENT

6K27

TOILET

6K26A

TOILET

6K25A

ANTE

6K33A

6J

6J

6K

6K 6G

PATIENT

6K13

TOILET

6K09A

LIFE SAFETY CODE ANALYSIS

7.1.10 MEANS OF EGRESS RELIABILITY

7.1.10.1 MEANS OF EGRESS SHALL BE CONTINUOUSLY MAINTAINED FREE OF ALL OBSTRUCTIONS OR IMPEDIMENTS TO FULL INSTANT

USE IN THE CASE OF FIRE OR OTHER EMERGENCY.

9.2.1 AIR CONDITIONING, HEATING, VENTILATION DUCTWORK, AND RELATED EQUIPMENT. AIR CONDITIONING, HEATING, VENTILATION

DUCTWORK, AND RELATED EQUIPMENT SHALL BE IN ACCORDANCE WITH NFPA 90A.

18.1.1.1.1 ALTERATION OF EXISTING HEALTH CARE OCCUPANCIES

18.1.1.4.3 REHABILITATION

18.1.1.4.3 (2) MINOR RENOVATION: A MINOR…

This is the start of the file's text. The full file is on GovTribe.