Removal of In-Ground Vehicle Lifts and Concrete Slab Restoration.pdf
PDF 203 KB Posted
- Solicitation number
- 26-02
- Issued by
- Los Angeles County, California
About this file
This Request for Information (RFI) #26-02 is issued by Monterey-Salinas Transit District (MST) for the removal of in-ground vehicle lifts and concrete slab restoration at MST's CJW Operations and Maintenance Facility located at 443 Victor Way in Salinas, California 93907. The scope of work encompasses full demolition of in-ground vehicle lifts, proper disposal of all components including hydraulic fluids, engineered backfill, and concrete slab restoration to support future use with mobile lifting equipment. The project requires contractors to obtain all necessary permits, perform site verification, identify and isolate utilities, drain and dispose of hydraulic fluids, saw-cut and remove concrete to access lift systems, remove lift cylinders, casings, hydraulic lines and fittings, and restore concrete slabs to match existing conditions with a minimum 4,000 PSI strength. A non-mandatory but strongly encouraged site visit is scheduled for Thursday, June 4, 2026 at 10:30 A.M. Questions must be submitted by Monday, June 8, 2026 at 12:00 P.M., and statements of information are due Thursday, June 18, 2026 at 2:00 P.M. through MST's Bonfire eProcurement Portal. Interested contractors must be registered as MST vendors and submit responses electronically; hard copy submissions will not be accepted.
This solicitation is informational in nature and does not commit MST to enter into a contract or obligate payment for proposal preparation costs. MST reserves the right to cancel the solicitation, issue a subsequent Invitation for Bids, or postpone the opening. Contractors must provide a statement of information including company details, contractor's license number, Department of Industrial Relations registration number, years in business, estimated project duration with major milestones and substantial completion date, identification of long lead items and potential schedule impacts, and information on required licensing. All submitted proposals become MST's exclusive property and will become public record upon contract award, except for elements marked as trade secrets under California Government Code 6254.7. Contractors must provide a minimum one-year workmanship warranty and ensure compliance with OSHA, environmental requirements, and all applicable federal, state, and local regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information
#26-02
For Removal of In-Ground Vehicle Lifts and
Concrete Slab Restoration for the
Monterey-Salinas Transit District
RFI #26-02 Schedule
Issue Date: Thursday, May 28, 2026
Site Visit: Thursday, June 4, 2026 at 10:30 A.M.
Question Submission Deadline: Monday, June 8, 2026 at 12:00 P.M.
Submittal Deadline: Thursday, June 18 at 2:00 P.M.
Monterey-Salinas Transit
19 Upper Ragsdale Drive, Suite 200
Monterey, CA 93940
Request for Information For
Removal of In-Ground Vehicle Lifts and
Concrete Slab Restoration for the
Monterey-Salinas Transit District
Notice Inviting Statements of Information
Monterey-Salinas Transit District (MST) is soliciting statements of information from qualified firms for the removal of in-ground vehicle lifts and concrete slab restoration, as described in more detail in the scope of work herein. The location for this project is MST’s CJW Operations and Maintenance Facility located at 443 Victor Way in Salinas, CA 93907. Work shall include full demolition, proper disposal of all components, engineered backfill, and concrete slab restoration to support future use with mobile lifting equipment.
Please note that the sole purpose of this solicitation is for MST to gather information for this project. This does not commit MST to enter into a contract, nor will a contract will not be awarded as a result of this solicitation. MST may issue a subsequent Invitation for Bids in the future to complete the work described herein. At that time, the Invitation for Bids may be made public and may also be sent to firms that submitted statements of information in response to this solicitation.
Statements of Information must be uploaded to MST's Bonfire eProcurement Portal at https://mst.bonfirehub.com/portal/?tab=openOpportunities by Thursday, June 18, 2026 at
2:00 p.m. PST. Hard copy submissions of submissions will not be accepted.
If you have any questions related to the procurement process, please contact:
Monterey-Salinas Transit
19 Upper Ragsdale Drive, Suite 200
Monterey, CA 93940
Attention: Steven Bruno, Purchasing Agent
Phone: 831-264-5884
Email: sbruno@mst.org
History and Overview of MST
Monterey-Salinas Transit District (MST) was created by state law AB644 and formed July 1, 2010. MST succeeds Monterey-Salinas Transit Joint Powers Agency formed in 1981 when the City of Salinas joined the Monterey Peninsula Transit Joint Powers Agency which was formed in 1972.
https://mst.bonfirehub.com/portal/?tab=openOpportunities mailto:sbruno@mst.org
Current members of MST are the Cities of Carmel, Del Rey Oaks, Gonzales, Greenfield, King City, Marina, Monterey, Pacific Grove, Salinas, Sand City, Seaside, Soledad, and the
County of Monterey. A board of directors with a representative from each member jurisdiction governs the agency and appoints the General Manager.
MST serves a 159 square-mile area of Monterey County, Northern San Luis Obispo County, and Southern Santa Cruz County. MST’s 36 routes serve an estimated 437,325 population within the County of Monterey.
For more information about MST, log onto http://www.mst.org/.
SOLICITATION TIMELINE
All submissions must be received by MST NO LATER THAN 2:00 P.M. on Thursday, June
18, 2026. MST will deem a submission as non-responsive and will not accept a submission past this time. Statements of information must be submitted through Monterey-Salinas Transit’s
Bonfire eProcurement portal. If you are not already registered, please do so at www.mst.org/procurement and select “Become a Vendor.”
If you have any questions regarding this solicitation, please submit them via MST’s Bonfire Portal no later than 12:00 P.M. on Monday, June 8, 2026. An addendum to this RFI will be issued answering any questions received by the deadline.
SITE VISIT
A non-mandatory, but strongly encouraged site visit will be held on Thursday, June 4, 2026 beginning at 10:30 A.M. at 443 Victor Way, Salinas, CA 93907. If you plan on attending the site visit, please RSVP to sbruno@mst.org by 12:00 P.M. on Wednesday, June 3, 2026.
SCOPE OF WORK
I. Permits and Compliance.
a. Obtain all required permits and coordinate inspections.
b. Comply with all applicable federal, state, and local regulations, including OSHA and environmental requirements.
c. Coordinate with facility personnel to minimize operational disruptions.
II. Pre-Demolition Activities.
a. Perform site verification and field measurements.
b. Identify, isolate, and secure all utilities associated with the lifts.
c. Drain, contain, and properly dispose of all hydraulic fluids and regulated materials.
d. Submit a site-specific safety plan prior to mobilization.
III. Demolition and Removal.
a. Saw-cut and remove concrete as required to access lift systems.
http://www.mst.org/ http://www.mst.org/procurement mailto:sbruno@mst.org
b. Remove and dispose of:
i. Lift cylinders and casings; and
ii. Hydraulic lines, fittings, and associated components.
c. Haul off and dispose of all debris at approved facilities.
d. Ensure complete removal of underground components with no voids remaining.
IV. Concrete Slab Restoration.
a. Install formwork and reinforcement to match existing slab conditions.
b. Place concrete to:
i. Match existing slab thickness and strength (minimum 4,000 PSI unless otherwise specified);
ii. Match existing finish, slope, and elevation; and
iii. Provide a level surface suitable to support new mobile lifts.
c. Finished slab shall meet industry flatness and levelness tolerances (FF/FL or as required by equipment manufacturer).
d. Saw-cut and align control joints with existing slab layout.
e. Cure concrete in accordance with industry standards.
f. Apply concrete sealer to all new concrete surfaces after curing is complete. Sealer shall be commercial/industrial grade and suitable for heavy-duty vehicle maintenance shop environments.
V. Site Restoration and Cleanup.
a. Restore all work areas to original or better condition.
b. Remove all construction debris, materials, and equipment.
c. Leave site clean, safe, and operational.
VI. Quality Assurance.
a. All work shall be performed by qualified personnel experienced in in-ground lift removal.
b. Contractor shall ensure proper compaction and slab performance to prevent settlement or cracking.
c. Provide a minimum one (1) year workmanship warranty.
VII. Safety Requirements.
a. Maintain a safe work environment at all times.
b. Provide barricades, signage, and protection around open excavations.
c. Coordinate with facility staff for safe movement of personnel and vehicles.
VIII. Project Schedule.
a. Submit a detailed project schedule prior to mobilization.
b. Coordinate sequencing of work to minimize disruption to facility operations.
c. Contractor shall provide an estimated project duration and completion timeline as part of the proposal submission, including anticipated start date, major project milestones, and substantial completion date. Contractor shall also identify any long lead items or schedule impacts that may affect project completion.
IX. Deliverables.
a. Copies of permits and inspection approvals.
b. Disposal manifests for regulated materials.
c. Compaction test results (if required).
d. Project closeout documentation.
X. Exclusions.
a. Unless otherwise noted, this proposal excludes:
i. Hazardous material remediation beyond standard hydraulic fluid disposal;
ii. Structural upgrades beyond limits of lift removal areas; and
iii. Unforeseen subsurface conditions.
ATTACHMENTS
The following attachments are hereby made part of this Invitation for Bids:
Appendix A – CJW Bay 1 Lift Photos
Appendix B – CJW Bay 2 Lift Photos
Appendix C – CJW Bay 3 Lift Photos
Appendix D – CJW Hydraulic Tank Photos
SUBMITTAL REQUIREMENTS
Interested construction companies/firms must submit Statement of Information. The Statement of Information shall include:
• Construction company name, address, email address, and phone number.
• Contractor’s license number.
• Department of Industrial Relations (DIR) registration number.
• Years in business.
• Estimated project duration and completion timeline, including major project milestones, and substantial completion date. Contractor shall also identify any long lead items or schedule impacts that may affect project completion.
• Information on the type of license needed to perform the work described herein.
RIGHTS OF MST
This RFI does not commit MST to enter into a Contract, nor does it obligate MST to pay for any costs incurred in preparation and submission of proposals or in anticipation of a contract.
MST may investigate the qualifications of any firm under submitting a statement of information, require confirmation of information furnished by the firm, and require additional evidence of qualifications.
MST reserves the right to:
1. Cancel this solicitation at any time for any reason at MST’s sole discretion.
2. Issue subsequent Invitation for Bids.
3. Postpone opening for its own convenience.
4. Remedy technical errors in the RFI process.
The proposals received become the exclusive property of MONTEREY-SALINAS TRANSIT
DISTRICT. At such time as a contract award is made by MST, all proposals submitted in response to this RFI shall become a matter of public record and shall be regarded as public records, with the exception of those elements of each proposal which are trade secrets as the term is defined in California Government Code 6254.7 and which are so marked as “TRADE
SECRET,” “CONFIDENTIAL,” OR “PROPRIETARY.” MONTEREY-SALINAS TRANSIT
DISTRICT shall not in any way be liable or responsible for the disclosure of any such records or portions thereof, including, without limitation, those so marked if disclosure is deemed required by law or by an order of a court. Proposals that indiscriminately identify all or most of the proposal as exempt from disclosure without justification may be found technically unacceptable.