REMIS RFTOPs.pdf
PDF 6 MB Posted
- Attached to
- Research, Engineering, and Mission Integration Services 2 (REMIS2) Federal contract opportunity
- Solicitation number
- 80JSC023REMIS2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| REMIS2 DRFP Questions and Answers.pdf | ||
| REMIS2 Industry Day Questions and Answers.pdf | ||
| 80JSC023REMIS2 REMIS2 DRFP.pdf | ||
| Attachment L-6 PRE-AWD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST.pdf | ||
| Attachment J-9 JSC Wage Determination 15-5233.pdf | ||
| Attachment L-5 Cost Price Template.xlsx | XLSX spreadsheet | |
| Attachment L-3 Past Performance Relevancy Matrix.xlsx | XLSX spreadsheet | |
| Attachment L-7 Business Systems Reviews and Status Information Template.xlsx | XLSX spreadsheet | |
| Attachment L-8 Prime and Subcontractor Identification and SOW Division of Work Listing.xlsx | XLSX spreadsheet | |
| REMIS2 Industry Day Charts.pdf | ||
| REMIS2 DSOW.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought Notice: 80JSC023REMIS2
Example Task Order Request for Proposals from the
Research, Engineering, and Mission Integration Services (REMIS) Contract
Table of Contents BioMole Gateway Payload Concept Specs Keyence Microscope Animal Care Facility Plant Water Management Ring Sheared Drop Electro-Oxidation Membrane Evaporator Flow Paths Galley Fridge Rodent Research Flight Kits Pore Formation Mobility Investigation KSC Multi Use Advanced Plant Habitat Umbilical Interface Assembly
REMIS-C1-TO-017-BioMole National Aeronautics and Space Administration Date: 4/1/2022
Johnson Space Center Houston, Texas
REMIS
CLIN 1
Request For Task Order Proposal
(RFTOP) Rev 2 Perform Mission Integration and Operations for BioMole
Funding Organization: JSC/OZ Task Order Manager (TOM): /OZ Contractor Representative(s): OFI Type of Task Order: FFP Base Period of Performance: TO Award Date to 9/5/2024 Place of Performance: OFI Total Price: OFI
1.0 INTRODUCTION/SCOPE
The International Space Station (ISS) Program is requesting the REMIS Contractors to prepare a Task Order Proposal (TOP) for providing Mission Integration and Operations (MI&O) for the biomolecular science facility known as “BioMole” (reference Attachment 1, “NASA Provided Hardware for use on this Task Order” for the list of BioMole facility hardware provided by
NASA).
BioMole is an Intravehicular Activity (IVA) lab support facility that will be used by various payloads/experimenters to support life science investigations on the ISS that require identification of gene nucleotide sequences. For deployment on ISS, BioMole will be stored until needed and then aisle deployed using work surfaces and/or securing hardware to hold components during use.
The scope of this Task Order (TO) is to perform the MI&O tasks required to execute science objectives in the BioMole facility on-board the ISS Vehicle, utilizing the flight hardware provided by NASA. NASA will provide delivery of the hardware to orbit. The offeror can assume that the flight hardware is certified to operate on ISS.
Logical follow-on orders and activities tightly coupled with this initial order may be ordered exclusively from the awardee of this initial order by the Government, at the Government’s discretion without any additional competition.
2.0 SCIENCE USERS ASSIGNED
The following table will be filled out as missions are assigned in the execution of the TO post-award.
User Assignments Target Flight Year Target Flight Principal Investigator
(PI) Name Cost ($)
Payload (PL) 1
PL 2
PL 3
PL 4
PL 5
PL 6
PL 7
PL 8
TOTAL COST
3.0 PAYLOAD MISSION PRICES
3.1 Price per Payload per Contract Year
Offeror’s proposals shall provide a response to the price per Contract Year as defined in the table below. For proposal purposes, offerors shall assume two payloads for CY22, four payloads for CY23, and two payloads for CY24.
As missions are assigned, the contractor will be responsible for identifying when resupply of limited life items and consumables are required. The contractor will also be responsible for the procurement and reflight certification of needed limited life items (e.g. Oxford Nanopore Flow Cells and consumables (e.g. pipette tips)). Additionally, the contractor will be responsible for procurement and certification of other experiment specific science materials such as reagents (swab kits, sequencing kits, PCR kits, etc.) that are required to support the science requirements of that mission.
For the purposes of this RFTOP, the contractor should assume reagents and limited life items are Toxicity Level 0. Additionally, science payload materials should be assumed to contain items with the following BioSafety Levels (BSL): two BSL-0, two BSL-1, two BSL-2M, and two BSL-2H. Contractor should assume an average of three sessions required per payload.
CY5 ($) Option Year 1
(CY6) ($)
Option Year 2
(CY7) ($)
Payload OFI OFI OFI
3.2 Materials Table
As missions are assigned in the execution of this task order, the price of science materials that are required to support the science requirements will be added based on the specific requirements of that mission.
Payload Number
Material Price ($)
Milestone Date
Payload (N) materials’ costs will be actuals
MM/DD/YYYY
(N+1) materials’ costs will be actuals
MM/DD/YYYY
TOTAL
4.0 TASKS/REQUIREMENTS
The Contractor shall complete the following tasks/requirements:
1. The Contractor shall perform the Mission Integration and Operations (MI&O) Support for BioMole as defined in the REMIS contract Statement of Work (SoW) section C.5.0.
Note: The Contractor shall assume that no sustaining engineering tasks are required to be performed for the NASA provided Hardware and Software specified in Attachment 1, “NASA Provided Hardware for use on this Task Order”, unless specifically noted in this RFTOP. Should the NASA provided hardware become non-usable, the contractor shall utilize existing NASA BioMole facility on-orbit spares.
2. The Contractor shall perform these unique or modified REMIS SoW requirements:
o The Contractor shall develop and deliver a Concept of Operations for the full implementation of BioMole onboard the ISS, to include the interface to the science community and ISS interfaces.
o The Contractor shall support operation and checkout of total capabilities of BioMole Flight Hardware and Software, ensure delivery of the telemetry data to the Principal Investigator (PI), and maintain insight into the systems comprising BioMole hardware and software required to support the science investigations.
o NASA will maintain the on-orbit software configuration of MinION (part of the BioMole facility hardware [reference Attachment 1, “NASA Provided Hardware for use on this Task Order”]). The contractor shall maintain the appropriate ground software version/configuration of the MinION real-time DNA and RNA sequencing device to match the on-orbit version.
o The Contractor shall perform integrated hazard analysis and process this hazard analysis through the safety panel, as required to address any on-orbit hazards associated with the scope of this TO. This includes, continuing to update the hazard analysis and conduct delta safety reviews, as required for each specific investigation.
o The Contractor shall procure all the materials and parts required to contain, transport, and launch the required science specific materials and limited life items.
Note: Science objectives will most likely require the use of NASA cold stowage resources, and those resources shall be provided as Government Furnished Service and identified in the TOP (reference Section 9.0, “GOVERNMENT OWNED SERVICES AND FACILITIES”).
o The Contractor shall develop and maintain the crew training products for science unique activities of BioMole for the duration of this Task Order and share those training products with the PI for review and approval.
o The Contractor shall provide the capability to procure and process reflight certification for life limited items and consumables, and procure and certify other science materials such as reagents (swab kits, sequencing kits, PCR kits, etc.).
o The Contractor shall deliver all required SSP 57000 integrated verification products via the VERITAS system. The Contractor may use their verification process for the performance/functional requirements independent of SSP 57000.
4.1 BIOMOLE MANAGEMENT
The Contractor shall provide the overall management of BioMole including integrating the science requirements and developing the implementation of those requirements with the ground and/or flight hardware and software.
The Contractor shall perform milestone reviews, customer briefings and technical interchanges with the science community requiring the use of BioMole.
4.2 PRINCIPAL INVESTIGATOR (PI) INTEGRATION
The Contractor shall perform the integration functions required for the PI’s use of BioMole. The specific proposed methodology shall be contained in the TOP.
5.0 DELIVERABLES AND DELIVERY SCHEDULE
In accordance with the REMIS Contract, the Contractor shall utilize their process defined in REMIS-PM-01, Commercialization Approach, to deliver all products and deliverables defined below following Task Order award.
The Contractor shall deliver their draft Concept of Operations as their technical solution to this
RFTOP.
Table 1 – DRDs/Additional Information
No. Item 1 DRD REMIS-PM03, “Government Property Management Plan,” is required for this
Task Order.
Table 2 – Reviews/Support
No. Item 1 Kick-off meeting. A joint kick-off meeting shall be held within 30 days of authorization to proceed (ATP) between the contractor and the NASA investigation team (contractor can coordinate with Task Order Monitor for appropriate invite list).
2 Contractor proposed science and experiment verification tests (SVTs and EVTs) to ensure the BioMole facility can meet PI science requirements and objectives. Ground EVTs would require contractor procured facility hardware.
3 Contractor proposed coordination meetings with the PIs that will utilize BioMole in order to facilitate science integration.
4 Contractor performs mission specific training (ground and/or on-orbit, as deemed required by contractor). If ground training is required, contractor performs that training using contractor procured hardware.
5 Contractor proposed reviews to support safety approval.
6 PI sample integration.
7 Contractor proposed reviews to support flight readiness that includes PI/PD approval and concurrence that all science requirements have been integrated and fulfilled.
8 Contractor support of on-orbit operations based on an operations support plan that encompasses scope defined in the REMIS contract Statement of Work (SoW) section C.5.4.
Table 3 – Data
No. Item 1 Concept of Operations
Initial due with TOP delivery Final due at ATP+30 days
2 Operations inputs delivered to the real-time operations process.
3 Provide the science data from BioMole to the PI location per the science requirements.
4 Contractor proposed safety data and associated products needed to close Hazard
Reports delivered to ISS Hazard database.
5 Contractor proposed verification products delivered to VERITAS.
6 CoFR Statements delivered per SSP 52054 OZ CoFR Plan.
7 Flight Certification – kept at contractor facility for the duration of the task order.
Delivered to government at completion of the task order.
8 Certification data required to refly or certify additional science materials.
6.0 PLACE OF PERFORMANCE
The Contractor may perform tasks under this TO at any location of their choosing. Therefore, please specify your proposed place of performance in your TOP.
If ground crew training is deemed to be required, that training shall be performed at the Johnson Space Center.
7.0 TOP PRODUCTS
All REMIS TOP products shall be developed in accordance with REMIS-MA-01, “Task Order Plan” unless otherwise specified. If any elements from REMIS-MA-01 are not required, please indicate as such.
For this FFP TO, the Offeror shall provide their proposed cost/price and fee. The cost/price proposal shall provide a summary of cost, by each Contract Year, detailing the proposed labor, hours, and material cost and fee, divided between the Prime and all proposed Subcontractors and teammates. The level of detail provided must correlate to the basis of your technical inputs.
The contractor shall electronically submit the following products in response to this RFTOP to the REMIS Contractor SharePoint site not later than 4:00 pm Central Time on April 25, 2022. Any questions to this RFTOP must be submitted not later than 4:00 pm Central Time on March 31, 2022. Please submit any questions to with a subject title of: “CUI: BioMole RFTOP Question”.
Questions from contractors will be reviewed to determine if a revised RFTOP is needed to provide clarifications. If a RFTOP revision is necessary, an update to the proposal due date will be provided as part of the RFTOP revision if additional time is deemed necessary by the Government. Questions and answers will not be provided back to any contractors.
The Contractor shall electronically submit the following products in response to this RFTOP:
1. Technical, price, and schedule data per DRD REMIS-MA-01.
a. The technical data shall include Concept of Operations.
b. The schedule delivered as part of the TOP shall be of sufficient detail to ensure that the technical team reviewing the proposals clearly understands the total approach being proposed by the offeror. The schedule shall include a representative example of each payload type with associated milestone plan (reference Section 11.0).
c. As part of the price data, a basis of estimate for the TO with sufficient detail such that key tasks are identified, skill sets scheduled for tasks are identified, assumptions and corresponding time duration.
d. Technical data shall be provided in Microsoft Word.
e. Schedule data shall be provided in Adobe PDF.
f. Price data shall be provided in Microsoft Excel.
2. The offeror shall provide their travel required to support all requirements in this task order based on their proposed Commercial Approach.
3. All costs should be a part of the proposal.
4. For this RFTOP, offerors shall assume the BioMole facility will already be available on-orbit.
5. Page Limits:
a. The technical data, inclusive of the Concept of Operations and the contractor’s proposed implementation of their commercial approach to be utilized, shall be limited to 20 pages.
• A cover page, table of contents, and list of acronyms may be included at the contractor’s discretion and will not count against the page limit.
• The “NASA Provided Hardware for use on this Task Order” list (Attachment 1) will also not count against the page limit.
• However, any Government Services or Facilities tables will count against the page limit for this RFTOP.
b. There are no page limits on the price and schedule data.
c. A page is defined as one side of a sheet, 8 1/2" x 11,” with at least one inch margins on all sides, using not smaller than Times New Roman 12 point type. Foldouts count as an equivalent number of 8 1/2" x 11" pages.
d. Pages submitted in excess of the limitations specified in this provision will not be evaluated by the Government.
8.0 DELIVERY INSTRUCTIONS
8.1 Hardware and Software Delivery
Authorized Government personnel shall accept all products delivered via DD Form 250 or 1149.
The Contractor shall deliver any flight hardware and software using the appropriate shipping and handling processes for flight hardware to the Cargo Mission Contractor at the Johnson Space Center for ISS Program launch processing and operations to the following delivery address:
NASA JSC CARGO MISSION CONTRACT 80JSC017C0015
555 FORGE RIVER ROAD
SUITE 150
WEBSTER, TX 77598
8.2 Data Deliveries
The Contractor shall upload all DRD and data deliverables in support of this task to the appropriate REMIS folder in EDMS, unless otherwise specified.
9.0 GOVERNMENT OWNED SERVICES AND FACILITIES
The available NASA provided hardware is listed in Attachment 1, “NASA Provided Hardware for use on this Task Order” and NASA will provide replacements of any of this hardware that becomes non-operational. If the Contractor believes that there are additional existing NASA hardware/software, etc., that can benefit the cost effectiveness of their proposal, the Contractor may propose that hardware/software in their TOP as an update to Attachment 1.
Applicable FAR and NASA FAR Supplement property administration clauses in the base contract are applicable to this TO in addition to any clauses in this TO.
If the Contractor is requesting either Government Service be provided or the use of Government Facilities, include these tables in your TOP. Cold stowage will be provided for contractor use inline with ISS research priorities.
Government Services Requested
Service Requested Purpose of Service Location Requested Duration for Request
Cold Stowage Conditioning of cells and reagents
Transport to ISS and on ISS
As required for the science mission
OFI OFI OFI OFI
Government Facilities Requested
Facility Requested Purpose of Facility Location of Facility Duration for Request
OFI OFI OFI OFI
10.0 PERIOD OF PERFORMANCE
The period of performance for this TO shall be (TO Award) to 9/5/2024.
11.0 MILESTONE PAYMENT PLAN
NASA recommends the following milestone for the work defined within this TO. Contractors shall propose dates for any cell containing OFI and may propose alternative milestones with rationale to support their proposal.
Milestones required prior to supporting On-Orbit Science (note: this is done only once):
Milestone: Price Date: Completion Criteria:
Finalization of the Concept of Operations with
NASA –
$OFI - 70% TO Award Plus 30 days
Insert calendar date at award
Concept of Operations, as approved by the NASA Contracting Officer’s Representative (COR) based on Task Order Manager (TOM) concurrence.
Delivery of the final crew training and crew procedures materials
$OFI - 30% OFI
Insert calendar date at award
Contractor provides documentation in contractor format demonstrating completion, as approved by COR based on the NASA TOM concurrence.
Payload Milestones
Integration of the PI science requirements for the use of BioMole and all its capabilities
30% Contractor provides documentation in contractor format demonstrating completion, as confirmed by the NASA COR.
Verification of the Experiment Unique HW and/or SW and integration of the mission unique aspects
30% Contractor provides documentation in contractor the NASA COR.
Safety Approval to Launch and Operate
20% Contractor provides documentation in contractor format demonstrating completion, as confirmed by the NASA COR.
Completion of mission/experiment unique crew training materials and procedures
10% Contractor provides documentation in contractor the NASA COR.
Delivery of the science data/samples to the PI
10% Acknowledgement from the PI that the Final Data has been delivered to the PI. Contractor provides documentation in contractor format demonstrating completion, as confirmed by the NASA COR.
12.0 TASK ORDER PLAN (TOP) EVALUATION CRITERIA
The contractor’s TOP per section 7.0 shall be evaluated as indicated below:
Technical Approach 45% Price 40% Schedule 15%
Attachment 1
NASA Provided Hardware for use on this Task Order
Item
Hardware Part # BioMole Facility Hardware Quantity
BioMole On-orbit Spare
Facility Quantity 1 MinION MINION-001 1 1 2 miniPCR16 MINIPCR16-001 1 1 3 20 µL Pipette (one for each:
DNA, RNA, PCG, and other) PIP-20 1 set 1
4 200 µL Pipette (one for each:
DNA, RNA, PCG, and other)
PIP-200 1 set 1
5 1000 µL Pipette (one for each: DNA, RNA, PCG, and other)
PIP-1000 1 set 1
7 Magnetic Stand 1 (single) MBS-1 1 1 8 Magnetic Stand 8 (multi) MBS-8 1 1 9 MinION USB Cable MINIONUSB-001 1 1 10 Calibration Cell CC-001 1 1 11 MiniPCR16 USB Cable MINIPCRUSB-
1 1
12 MiniPCR16 Power Cable MINIPCRPS-001 1 1
Attachment 2
Reference Materials and Applicable Documents
• Oxford Nanopore: https://nanoporetech.com/
• miniPCR bio: https://www.minipcr.com/about/
• And the following example procedures (embedded videos will also be provided):
1.7.001 EHS BIOMOLE - MINIPCR CHECKOUT
1.7.002 EHS BIOMOLE - MINION CHECKOUT
2.7.001 EHS BIOMOLE - PART 1: SURFACE SAMPLING AND DNA
EXTRACTION [HC]
2.7.002 EHS BIOMOLE - PART 2: DNA CLEANUP AND AMPLIFICATION
2.7.003 BIOMOLE - MINIPCR16 STOP AND SAMPLE TUBE REMOVAL
2.7.005 EHS BIOMOLE - PART 3: DNA PREP AND SEQUENCING
2.7.006 EHS BIOMOLE – MINION STOW
REMIS-XXXXX
National Aeronautics and Space Administration Date: xx/xx/xxxx
Johnson Space Center Houston, Texas
REMIS
CLIN 1
Request For Task Order Proposal
(RFTOP) Rev 1 Development of Gateway Payload Enclosure
Concept and Specification
Funding Organization: MSFC/HP30 Task Order Manager: /HP30 Contractor Representative(s): OFI Type of Task Order: Firm Fixed Price Base Period of Performance: TO Award Date to 9/30/2022
Base Total Price: OFI
The Gateway Program is requesting the REMIS Contractors to prepare a Task Order Proposal (TOP) for development of a Gateway Payload Enclosure Concept, Concept of Operations, and Requirements Specification.
The Gateway is NASA’s pressurized space station orbiting the moon, and will support science experiment hardware—payloads—during periods of crewed and uncrewed operations. NASA is considering providing government furnished equipment (GFE) enclosures to payload developers to house their powered payload hardware. The task order will be for the development of the concept and requirements for a GFE payload enclosure.
• The Gateway Payload Enclosure is intended to contain powered payload experiment hardware and to serve as the mounting interface between a single payload and the Gateway Payload Bank.
• The Payload Bank is a module-mounted coldplate that provides mechanical, thermal, power, and data interfaces for payloads mounted to it.
• The Payload Bank is capable of accommodating up to eight individual payloads at a time, and there is anticipated to be one Payload Bank present in the initial Gateway configuration, with more to be added as future Gateway elements are launched and integrated with the vehicle.
• The Payload Enclosures will:
• Be used for a variety of payloads over the lifetime of Gateway, including physical sciences, human research, biology and biotechnology, technology, earth and space sciences, education/outreach, etc.
• Developers of these payloads will be responsible for designing/building their hardware to be compatible with the GFE payload enclosure if they do not opt to design their own enclosure
• Provide the mechanical, thermal, power, and data interfaces between the Payload Bank and the science hardware and electronics within the Enclosure. There are no fluid interfaces such as gas venting and water supply.
• Provide a front face that will accommodate payload controls/displays
• Be capable of being hard-mounted during launch
• For deployment on Gateway, the Payload (enclosure with experiment hardware inside) is being integrated into a Gateway Payload Bank outside of this RFTOP.
Logical follow-on orders and activities tightly coupled with this initial order, such as the design, manufacture, test, and delivery of the Payload Enclosure, may be ordered exclusively from the awardee of this initial order by the Government, per the Optional Tasks at the end of this task order, at the Government’s discretion. However, the Government retains the right to not pursue the Optional Tasks in this task order for any reason.
2.0 Documents
2.1 APPLICABLE DOCUMENTS
Document # Title GP 10037 Gateway Payload Interface Definition Document (IDD)
Note: there are no additional drawings or technical data available at this time.
3.0 CONTRACT VALUE
Placeholder for Contracting Officer to insert table tracking contract value, total cost and fee updates as TO is revised.
4.0 TASKS/REQUIREMENTS
The Contractor shall complete the following tasks/requirements:
1. The Contractor shall create and deliver a baseline Gateway Payload Enclosure Requirements Specification Document, for a Payload Enclosure compatible with the Gateway Payload Bank and meeting the requirements of GP10037, Gateway Payload Interface Definition Document.
o GP 10037 – Payload Interface Definition Document (PIDD), which documents the requirements for Gateway Payload Bank interfaces and other requirements for launch and use on Gateway, will be provided to the contractor.
2. The Contractor shall develop and deliver a Concept of Operation for the following:
o Integrating payload hardware into the Payload Enclosure and assembling for test/delivery o Ground installation of the Payload Enclosure to the Payload Bank for launch (on-orbit installation is specified in GP10037) o Crew manipulation of the Payload Enclosure using a handle(s)
3. The Contractor shall conduct Trade Studies to determine:
o Whether the Payload Enclosure interface with the Payload Bank coldplate can have an interchangeable coldplate or a thermally conductive baseplate on the rear face, or whether there should be two models of payload enclosure (one with a coldplate, one with a baseplate)
4. The Contractor shall develop and deliver a conceptual mockup and/or Computer Aided Design (CAD) model of the proposed Payload Enclosure concept.
5.0 DELIVERABLES AND DELIVERY SCHEDULE
In accordance with the REMIS Contract, the Contractor shall utilize their process defined in REMIS-PM-01, Commercialization Approach, to deliver all products and deliverables defined below following Task Order award.
Specific schedule requirements:
The government requires this work to be completed in FY22.
The Contractor shall deliver their Gateway Payload Enclosure Requirements Specification document and Concept of Operation document to this TO.
The Contractor shall deliver their Trade Study recommendations for the coldplate vs baseplate to this TO.
The Contractor shall provide a conceptual mockup/CAD model of their proposed Gateway Payload Enclosure based on their Requirements Specification and Concept of Operations.
Table 1 – DRDs/Additional Information
No. DRDs (List the specific DRDs, if any, that are required for this RFTOP) 1 DRD REMIS-PM03, “Government Property Management Plan,” is required for this
Task Order.
2 DRD REMIS-S1-01, “Engineering Technical Documentation” is required for this
Task Order.
Table 2 – Reviews/Support
No. Item 1 Kick-off meeting. A joint kick-off meeting shall be held within 15 calendar days of authorization to proceed (ATP).
2 Monthly status reviews, when there is not a midpoint review, for contractor to provide updates on project status, previews of deliverables, ongoing accomplishments/issues.
3 Two midpoint reviews wherein contractor provides presentation on project status to date, including open issues, risks and forward path to project completion.
Midpoint Review #1 to be held ~end of April 2022 Midpoint Review #2 to be held ~end of June 2022 Draft Requirements Specification Document, draft Concept of Operations, and Trade Study Recommendations to be delivered at second Midpoint review.
4 Final review wherein contractor provides presentation on project deliverables. Final Requirements Specification Document, Concept of Operation, and Conceptual mockup/drawing/model delivered at Final review.
Final Review to be held ~end of September 2022
1 Requirements Specification Document (MS Word):
Draft delivered by second Midpoint Review Final delivered at Final Review
2 Concept of Operation for use of Payload Enclosure, to include:
- Integration of payload to Payload Enclosure
- Ground installation of Payload Enclosure to Payload Bank
- Crew manipulation of Payload Enclosure using required handle(s) Draft delivered by second Midpoint Review Final delivered at Final Review
3 Trade Study recommendations for:
Coldplate vs Conductive Baseplate models Delivered at second Midpoint Review
Table 4 – Hardware and Software
1 Deliver conceptual mockup (material to be chosen by vendor) and/or CAD model (file type STEP) of proposed Payload Enclosure.
please specify your proposed place of performance in your TOP.
7.0 PERIOD OF PERFORMANCE
The period of performance for this TO shall be ATP to 09/30/2022.
8.0 DELIVERY INSTRUCTIONS
8.1 Hardware and Software Delivery
Authorized Government personnel shall accept all products delivered via DD Form 250 or 1149.
The Contractor shall deliver any hardware and software using the appropriate shipping and handling processes to the TO project manager at the following delivery address:
Marshall Space Flight Center Central Receiving Facility, Building 4631
MSFC, AL 35812
Marked for:
ISS Projects Office
MSFC/HP30
Phone #
8.2 Data Deliveries
The Contractor shall upload all DRD and data deliverables in support of this task to the appropriate REMIS folder in EDMS, unless otherwise specified.
9.0 MILESTONE PAYMENT PLAN
NASA recommends the following milestone for the work defined within this TO. Contractors shall propose dates for any cell containing OFI, and may propose alternative milestones with
Milestones required:
Delivery of Trade Study Recommendations
$OFI – 10% Midpoint Review #2
OFI-Insert calendar date at award
Contractor provides recommendations for trade studies specified in Section 5, Table 3, as concurred by the NASA COR.
Delivery of draft Requirements Specification Document and Concept of Operations
$OFI - 50% Midpoint Review #2
OFI-Insert calendar date at award
Contractor provides draft copies of Requirements Specification Document and Concept of Operations, as concurred by the
NASA COR.
Final delivery of Requirements Specification Document and Concept of Operations
$OFI - 30% Final Review
OFI-Insert calendar date at award
Contractor provides final copies of Requirements Specification Document and Concept of Operations, as concurred by the
NASA COR.
Delivery of conceptual CAD model and/or physical mockup
$OFI – 10% Final Review
OFI-Insert calendar date at award
Contractor provides conceptual CAD model (file type STEP) and/or physical mockup of Payload Enclosure, as concurred by the NASA COR.
10.0 OPTIONAL TASKS
This section details optional tasks that may be requested per NASA discretion as part of this TO.
The Contractor shall include the cost, technical, and schedule proposal for these options in their
TOP.
10.1 Tasks/Requirements
Option 1: Trade Study for Payload Enclosure Thermal Filler
The Contractor shall conduct Trade Studies to determine:
• A recommended thermal filler for the enclosure’s coldplate/baseplate surface o Trade shall include filler heat conduction performance after Enclosure removal/reinstall each of four times at Payload Bank type of interface, and whether the filler must be removed and replaced when moving the enclosure from one Payload Bank to another, due to thermal filler thermal performance degradation when reused, and if so, whether the Gateway crew can do so relatively quickly on-orbit.
o Parker THERM-A-GAP 579 must be included in the trade. Other gaskets may be included in the trade at the contractor discretion. Shore 00 hardness not to exceed 30.
Option 2: Design, Build, Verify, Deliver Payload Enclosures
• 2.a – The Contractor shall deliver a finalized design of the single locker sized Payload Enclosure.
o As part of this work, the Contractor shall create and deliver an Interface Control Document for payload developers to install their hardware into the Payload Enclosure.
o The Contractor shall coordinate with the Gateway Program and identify any new requirements to be added to the GP10037 Payload IDD for payload developer and on-orbit use of the Payload Enclosure.
• 2.b – The Contractor shall manufacture and deliver a prototype of the Payload Enclosure.
o The Contractor is responsible for the verification that the payload enclosure is in compliance with the interface requirements established in the Gateway PIDD, and that the “as built” status is in compliance with the Payload Enclosure Requirements Specification.
• 2.c – The Contractor shall manufacture and deliver 1 Flight unit and 1 Ground unit of the Payload Enclosure.
o The Contractor is responsible for the verification that the payload enclosure is in compliance with the requirements established in the Gateway PIDD, and that the “as built” status is in compliance with the Payload Enclosure Requirements Specification.
o In the event stand−alone verification of each of the two mating parts of an interface is not sufficient, and that active participation from the Gateway is necessary to fully verify the compliance with the Gateway PIDD requirements, both the Gateway and the Contractor are jointly responsible for the successful completion of interface verification.
o The Contractor is responsible for all qualification testing. The Contractor shall provide documentation for maintenance and sustaining of the hardware if completed by another Contractor. The Contractor shall deliver the associated supporting documentation (CAD models, drawing package, fabrication and assembly procedures, acceptance test procedures, vendor list etc.) to allow the Government to manufacture future builds.
• If the Contractor believes that there are additional existing NASA facilities or services that can benefit the cost effectiveness of their proposal, they may propose utilizing them in their TOP.
10.2 Deliverables and Schedule
In accordance with the REMIS Contract, the Contractor shall utilize their process defined in REMIS-PM-01, Commercialization Approach, (unless otherwise specified in this TO) to deliver all optional products and deliverables defined below following notification by NASA that the optional tasks are required and are executed on this TO.
Specific schedule requirements:
Option 1: The Contractor shall deliver their thermal filler trade study recommendations to this TO.
For the purposes of this RFTOP, the Contractor may assume the following:
NASA shall notify the Contractor NLT May 31, 2022 that the optional task is required.
The due date for the optional task completion will be notification of task requirement + four months.
Option 2: The Contractor shall deliver their finalized payload enclosure design, payload enclosure prototype, and payload enclosure flight/ground units and associated documentation to this TO.
For the purposes of this RFTOP, the Contractor may assume the following:
NASA shall notify the Contractor that the optional task is required NLT October 31, 2022. The due date for the optional tasks will be:
• Option 2.a – March 31, 2024 or OFI an earlier date
• Option 2.b – October 1, 2024 or OFI an earlier date
• Option 2.c – August 1, 2025 or OFI an earlier date
Table 1 – DRDs/Additional Information
Option 1 No. DRDs
Option 2
1 REMIS-CM-01 Configuration Management Plan 2 REMIS-SI-01 Engineering Technical Documentation 3 REMIS-PM03 Government Property Management Plan
Table 2 – Reviews/Support
1 Kick-off meeting. A joint kick-off meeting shall be held within 10 calendar days of authorization to proceed (ATP).
2 Final review wherein contractor provides presentation on trade study recommendations.
Option 2
No. Item 1 Systems Requirement Review (SRR) 2 Preliminary Design Review (PDR) 3 Critical Design Review (CDR) 4 Program Safety Reviews, as required 5 Acceptance Review
1 Trade Study results and recommendations for Thermal Filler between Payload
Enclosure and Payload Bank Option 2
No. Item 1 Operations and Maintenance Manual (as needed), training materials, and installation instructions in accordance with DRD SI-01 to be delivered with the first manufactured unit
2 Manufacturing and assembly drawings in accordance with DRD SI-01 to be delivered with first manufactured unit
3 Identured Parts List in accordance with DRD SI-01 to be delivered with first manufactured unit
4 Verification Reports and supporting analyses in accordance with DRD SI-01 to be delivered with first manufactured unit
5 Safety Data Sheet to be delivered with the prototype and flight/ground units.
6 DD250 Material Inspection and Receiving Reports (for each delivery) for prototype and flight/ground units.
7 Nonconformances, MRB records, as run qualification and acceptance test procedures, Thermal models, limited life parts list and tracking (if any), material traceability (as required, and to include lot #s)
N/A Option 2
No. Item 1 Final payload enclosure design CAD model (STEP file type) 2 Prototype payload enclosure unit – 1 3 Flight payload enclosure unit - 1 4 Ground payload enclosure unit - 1
10.3 Milestone Payment Plan
NASA recommends the following milestones for the work defined within this TO. Contractors shall propose dates for any cells containing OFI, and may propose alternative milestones with rationale to support their proposal.
If Options are exercised the Period of Performance will not exceed the date found in Section F, Clause F.4, Period of Performance. The delivery of the items awarded will not exceed the limitations of contract clause FAR clause 52.216-22(d) found in Section I.A.6 (d) of the parent contract.
Contract rates that go beyond September 5, 2024 shall be proposed to this RFTOP in the contractors cost proposal; these rates will be negotiated prior to TO award. Any rates or prices necessary to support delivery past the parent contract Period of Performance which are not included in Section J-9 Fully Burdened Rates of the contractors REMIS contract will need to be supported for reasonableness.
Milestones required:
Delivery of thermal filler trade study recommendations
$OFI -
100%
Optional Task
ATP + 4
months
Contractor provides recommendations for optional
Insert calendar date at award trade study specified in Section X, as concurred by the NASA COR.
Option 2
Successful completion of payload enclosure design SRR
$OFI - 10% OFI
Insert calendar date at award
NASA Approval upon successful completion of the SRR
Successful completion of payload enclosure design PDR
$OFI - 20% OFI
Insert calendar date at award
NASA Approval upon successful completion of the PDR
Successful completion of payload enclosure design CDR
$OFI - 20% OFI
Insert calendar date at award
NASA Approval upon successful completion of the CDR
Delivery of final payload enclosure design documentation
$OFI - 10% March 31, 2024 or OFI an earlier date
NASA acceptance, successful verification closure, and NASA acceptance of all deliverable products.
Delivery of payload enclosure prototype and any supporting hardware, documentation per the Deliverables/Schedule listed in Section X above
$OFI - 10% October 1, 2024 or OFI an earlier date
NASA acceptance, successful verification closure, and NASA acceptance of all deliverable products. Acceptance of contracted hardware and documentation will be via signed
DD250.
Delivery of payload enclosure flight and ground units and any supporting hardware, documentation, etc. per the Deliverables/Schedule listed in Section X above
$OFI - 20% August 1, 2025 or OFI an earlier date
NASA acceptance, successful verification closure, and NASA acceptance of all deliverable products. Acceptance of contracted hardware and documentation will be via signed
DD250.
Successful completion of Payload Enclosure Acceptance Review
$OFI - 10% August 1, 2025 or OFI an earlier date
NASA Approval upon successful completion of the Acceptance Review
11.0 GOVERNMENT FURNISHED PROPERTY (GFP) and GOVERNMENT OWNED
FACILITIES
The available GFP hardware is listed in Attachment 1, “Government Furnished Equipment List.”
If the Contractor believes that there are additional existing NASA hardware/software, etc., that can benefit the cost effectiveness of their proposal, the Contractor may propose that hardware/software in their TOP as an update to Attachment 1.
Applicable FAR and NASA FAR Supplement property administration clauses in the base contract are applicable to this TO in addition to any clauses in this TO.
If the Contractor is requesting either Government Service be provided or the use of Government Facilities, include these tables in your TOP.
Government Services Requested
Service Requested Purpose of Service Location Requested Duration for Request
Government Facilities Requested
Facility Requested Purpose of Facility Location of Facility Duration for Request
12.0 TOP PRODUCTS
All REMIS TOP products shall be developed in accordance with REMIS-MA-01, “Task Order Plan” unless otherwise specified. If any elements from REMIS-MA-01 are not required, please indicate as such.
Cost Data:
For this FFP TO, the Offeror shall provide their proposed cost/price and fee. The cost/price proposal shall provide a summary of cost, by each Government FY, detailing the proposed labor, hours, and material cost and fee, divided between the Prime and all proposed Subcontractors and teammates. The level of detail provided must correlate to the basis of your technical inputs.
The contractor shall electronically submit the following products in response to this RFTOP to the REMIS Contractor SharePoint site not later than 4:00 pm Central Time on March 9th, 2022. Any questions to this RFTOP must be submitted not later than 12:00 pm (noon) Central Time on February 23rd 2022. Please submit any questions to with a subject title of: “CUI: Gateway Payload Enclosure RFTOP Question”.
Questions from contractors will be reviewed to determine if a revised RFTOP is needed to provide clarifications. If a RFTOP revision is necessary, an update to the proposal due date will be provided as part of the RFTOP revision if additional time is deemed necessary by the Government. Questions and answers will not be provided back to any contractors.
The Contractor shall electronically submit the following products in response to this RFTOP to the NASA REMIS Sharepoint site
1. Technical, cost, and schedule data per DRD REMIS-MA-01.
a. Technical data shall be provided in Microsoft Word.
b. Schedule data shall be provided in Adobe pdf.
c. Cost/Price data shall be provided in Microsoft Excel.
2. Page Limits:
a. The technical data shall be limited to 20 pages and shall include the base TO content and
Options 1 and 2.
b. There are no page limits on the cost and schedule data.
c. A page is defined as one side of a sheet, 8 1/2" x 11,” with at least one inch margins on all sides, using not smaller than Times New Roman 12 point type. Foldouts count as an equivalent number of 8 1/2" x 11" pages.
d. Pages submitted in excess of the limitations specified in this provision will not be
13.0 TASK ORDER PLAN (TOP) EVALUATION CRITERIA
The contractor’s TOP shall be evaluated as indicated below :
Technical Approach 40% Price 60% Schedule: If offeror’s proposed schedule does not meet government requirements to complete the base work of this task order as described in Sections 1-9 by FY22 and the optional work by the schedule/milestones listed in Section 10, the proposal will be considered unacceptable. For the purposes of this RFTOP, Authority to Proceed for the base period is the date of the TO award, which may be assumed to be March 23, 2022.
NASA Provided Hardware for use on this Task Order
Item # Hardware Part # Quantity
REMIS-C1-TO-15-KEYENCE MICROSCOPE
National Aeronautics and Space Administration Date: 03/25/2020
Johnson Space Center Houston, Texas
REMIS
CLIN 1
Request For Task Order Proposal
(RFTOP) Rev C Perform Mission Integration and Operations and Sustaining Engineering for the ISS Fluorescence
Microscope Keyence BZ-X810
Funding Organization: JSC/OZ Task Order Manager: /OZ Contractor Representative(s): OFI Type of Task Order: Firm Fixed Price Base Period of Performance: TO Award Date to 9/5/2022 Option Periods: 9/6/2022 – 9/5/2023 and 9/6/2023 - 9/5/2024
Total Price: OFI
Task Order Proposal (TOP) for providing Mission Integration and Operations (MI&O) and Sustaining Engineering (SE) for the Keyence BZ-X810 Microscope System.
• The Keyence ISS Fluorescence Microscope is IVA lab support equipment that will be used by various payloads/experimenters to support life and physical science investigations on the ISS that require microscopy.
• For deployment on ISS, the Microscope is being integrated into the MSRR (Microgravity Sciences Research Rack) Alpha Storage Area outside of this RFTOP as shown in Attachment 3.
The scope of this Task Order (TO) is to perform the MI&O and SE tasks required to provide the Keyence ground and flight hardware to support science objectives on board the ISS Vehicle.
NASA will provide for the delivery and physical integration of the flight hardware into the MSRR through a different contract mechanism. In addition, NASA has ensured that an initial set of science holders are certified for use on-orbit. A list of these holders is in Attachment 2, and additional information about them is located in the reference material.
Logical follow-on orders and activities tightly coupled with this initial order may be ordered exclusively from the awardee of this initial order by the Government, at the Government’s discretion without any additional competition.
2.0 SCIENCE USERS ASSIGNED
User Assignments Target Flight Principal Investigator (PI) Name
Simple Payload (PL) 1 Simple PL 2 Simple PL 3 Simple PL 4 Simple PL 5 Simple PL 6
Average PL 1 Average PL 2 Average PL 3 Average PL 4 Average PL 5 Average PL 6
Complex PL 1 Complex PL 2 Complex PL 3 Complex PL 4 Complex PL 5 Complex PL 6
The Task Order Manager will make the final decision on the definitions to each payload covered by this Task Order.
Simple Payload: The Simple Payload is a payload that utilizes the basic capabilities of the microscope without any addition of experiment unique equipment. Observational campaigns will be short term in nature. The experiment does not require modifications to the hardware, nor does it utilize chemicals, biological materials, or any other substances assessed as greater than a “marginal” hazard severity per SSP 51721, ‘ISS Safety Requirements Document’, section 4.7.2, ‘Hazardous Materials’.
Average Payload: The Average Payload is typically a life sciences payload that may utilize a wide variety of the microscope’s capabilities to support on orbit processing. This type of payload may require some minor to moderate modifications to existing space flight hardware and typically involves a moderate amount of space flight hardware, as well as experiment unique hardware development to conduct the experiment on orbit. Extended observation times and limited facility scheduling may be required.
Complex Payload: The Complex Payload is typically a physical sciences payload that may utilize a wide variety of the microscope’s capabilities and may require significant hardware modifications or new space flight hardware design and development. This level of payload typically requires significant experiment unique hardware development in addition to the primary space flight hardware provided as standard for the Microscope and requires extensive crew interaction and operations. Extended to long term observations and facility scheduling may be required.
3.0 PAYLOAD MISSION PRICES
Payload Type Price per Payload per Contract Year
CY3 CY4 CY5 Option Year 1 Option Year 2 Simple Payload OFI OFI OFI OFI OFI Average Payload
OFI OFI OFI OFI OFI
Complex
OFI OFI OFI OFI OFI
4.0 TASKS/REQUIREMENTS
The Contractor shall complete the following tasks/requirements:
and Sustaining Engineering (SE) for the Keyence Microscope as defined in the REMIS contract Statement of Work (SOW) sections C.5.0 and C.4.0.
o The Contractor shall develop and deliver a Concept of Operations for the full implementation of the Keyence Microscope onboard the ISS, to include the interface to the science community, ISS interfaces and maintain operability of the hardware.
o The Contractor shall develop and implement the capability to perform command and control of the on-orbit Keyence Microscope from the ground, inclusive of full capabilities that the Keyence Microscope can provide to the science community.
2. The Contractor shall perform these unique or modified REMIS SOW requirements:
o The Contractor shall support initial operation and checkout of total capabilities of the Keyence Microscope Ground and Flight Hardware and Software, provide assistance to the PI with command and telemetry data, and provide necessary insight into the systems and sensors comprising the Keyence Microscope hardware and software required to support the science investigations.
o The Contractor shall operate, monitor, and oversee the Keyence Microscope during operations aboard the ISS.
o The Contractor shall develop and deliver a Flight Certification that states all requirements (science, safety, and verification) have been met and the payload/sample is safe and ready to launch and operate on the ISS for each flight.
Documentation that supports this Flight Certification shall be in the
Contractor’s best practices format and content and will be retained for the duration of the task order.
The Flight Certification Statement shall meet the requirements defined in the OZ CoFR Plan for a payload/sample for launch and on-orbit operations.
o The Contractor shall define and deliver their proposed solution to addressing any on-orbit hazard controls for the experiment and plans to mitigate any hazards.
o The Contractor shall procure all the material and parts required to contain, transport, launch, process, and return the science samples. If Contractor proposes to use NASA Cold Stowage resources, those shall be provided as Government Furnished Service.
o The Contractor shall provide SE services that ensure the Keyence Microscope and associated systems (hardware and software) remain functional as designed and meet the requirements of the science investigators for the duration of this Task Order.
o The Contractor shall maintain the configuration and operability of the Keyence Microscope for the duration of this Task Order.
o The Contractor shall provide engineering support, near real-time on-call support during Keyence Microscope operations, provide engineering analysis, and resolve anomalies and/or failures of Keyence Microscope and associated systems.
Anomaly resolution will require interactions with the Mission Evaluation
Room (MER) and Payload Operations and Integration Center (POIC).
Should hardware modification or repair be required, it will be done as a revision to this TO.
o The Contractor shall provide the capability to procure and certify additional
Keyence sample holders should new requirements by the science community require a new capability that was not identified as part of the initial capability for the Keyence science investigations, as directed by the Contracting Officer. These specific requirements will be documented as a revision to the Task Order.
4.1 MICROSCOPE MANAGEMENT
The Contractor shall provide the overall management of the Keyence including integrating the science requirements and developing the implementation of those requirements with the ground and/or flight hardware and software.
The Contractor shall perform milestone reviews, customer briefings and technical interchanges with the science community requiring the use of the Keyence.
4.2 PRINCIPAL INVESTIGATOR (PI) INTEGRATION
The Contractor shall provide the systems engineering for developing requirements and integration capabilities for PI use of the Keyence.
5.0 DELIVERABLES AND DELIVERY SCHEDULE
In accordance with the REMIS Contract, the Contractor shall utilize their process defined in REMIS-PM-01, Commercialization Approach, to deliver all products and deliverables defined below following Task Order award.
Specific schedule requirements:
The Contractor shall deliver their draft…