REQUEST FOR PROPOSAL SUMMARY – CITY OF BEAVERTON SEWER RELOCATION PROJECT
This Request for Proposal (RFP) addendum is issued by the City of Beaverton, Oregon Public Works Department for the relocation of the Firestone sewer lateral and abandonment of the existing sewer main along SW Canyon Road to SW Cedar Hills Boulevard. The project involves relocating the Firestone sewer lateral to connect to the sewer main on SW Cedar Hills Boulevard via a new manhole using a combination of trenchless and open-trench construction methods, followed by abandonment of the existing sewer main along SW Canyon Road and removal of two existing cleanouts and one sewer manhole. Deliverables include mobilization, work zone traffic control, erosion control, 4-inch sanitary sewer lateral installation, 48-inch manhole installation, filling abandoned structures, concrete sidewalk panel and commercial concrete bay repair, and trench resurfacing with grind and inlay. The RFP was released on July 22, 2026, with a response deadline of August 20, 2026, at 2:00 p.m. The estimated Notice to Proceed date is September 21, 2026. All work must be performed between 9:00 p.m. and 5:00 a.m. and comply with ASTM standards, OSHA regulations, City of Beaverton standards, Clean Water Services standards, and ODOT pavement restoration guidelines. The contract may be renewed for up to one additional one-year term at the City's discretion.
Proposals will be evaluated based on background and experience (20 percent), project approach and schedule (10 percent), and cost (70 percent). Prevailing wage rates apply to all workers performing the contract work, as determined by the Oregon Bureau of Labor and Industries for Region 2, effective as of July 22, 2026. The City is conducting this procurement as an Informal Solicitation under Beaverton Purchasing Code Section 47-0290, with the expectation of awarding a single contract to a single vendor. Award consideration is at the City's sole discretion, and the City reserves the right to withdraw any items from consideration or decline to enter into a contract with any proposer. The City has established an aspirational goal of 15 percent utilization of state-certified COBID (Certification Office for Business Inclusion and Diversity) companies and requests that contractors identify any COBID certifications held. Proposers must submit electronically through the City's portal, obtain a City business license, complete IRS Form W-9, maintain specified insurance requirements, and comply with all federal, state, and local civil rights and nondiscrimination laws.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
CIP 6150
RELOCATION OF SEWER LATERAL AND ABANDONMENT OF
SEWER MAIN – SW CANYON RD TO SW CEDAR HILLS BLVD
City of Beaverton
12725 SW Millikan Way
Beaverton, OR 97005-1678
RELEASE DATE: July 22, 2026
DEADLINE FOR QUESTIONS: undefined
RESPONSE DEADLINE: August 20, 2026, 2:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/beavertonoregon https://secure.procurenow.com/portal/%7bproject.government.code%7d
City of Beaverton
REQUEST FOR PROPOSAL
Relocation of Sewer Lateral and Abandonment of Sewer Main – SW
Canyon Rd to SW Cedar Hills Blvd
I. Introduction and Background II. Scope of Work
III. Proposal Content and Format IV. Proposer's Special Instructions V. Proposal Submittals
VI. Proposal Evaluation & Contract Award VII. Beaverton Equity Procurement Program Information
Attachments:
A - 20201109 ODOT Pavement Restoration Guideline
B - CIP 6150 Sewer Lateral Relocation and Sewer Abandoment Project Plan
Request For Proposal #CIP 6150 Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
1. 1. ............................................... Introduction and Background
1.1. 1.1. ............................................................................................. Summary
This project consists of relocating the Firestone sewer lateral to connect to the sewer main on SW Cedar
Hills Blvd via a new manhole, using a combination of trenchless and open-trench construction methods.
Following the lateral relocation, the existing sewer main along SW Canyon Rd will be abandoned, and the two existing cleanouts and sewer manhole located on SW Canyon Rd will be removed. Please note that prevailing wage rates apply to this project.
1.2. 1.2. .......................................................................................... Background
SW Canyon Rd (Hwy 8) falls under ODOT jurisdiction; therefore, this project will adhere to all applicable
ODOT standards, rules, and regulations. A sewer permit and an ODOT permit have already been obtained by the City.
1.3. 1.3. ............................................................................ Contact Information
Danica Ruud, PE
Project Engineer
12725 SW Millikan Way
Beaverton, OR 97005-1678
Email: druud@beavertonoregon.gov
Phone: (971) 482-8292
Department:
Public Works - Engineering
Department Head:
Tim Elsea
PW Director
1.4. 1.4. ............................................................................................... Timeline
The City reserves the right to modify this schedule at the City’s discretion. Proper notification of changes will be made to all interested parties.
Advertisement and Release of Proposals July 22, 2026
Deadline for Submission of Proposals August 20, 2026, 2:00pm
Estimated Notice to Proceed Date September 21, 2026 mailto:druud@beavertonoregon.gov tel:(971)482-8292
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
2. 2. ...................................................................... Scope of Work
2.1. 2.1. ................................................................................. Schedule of Work
The City expects the Proposer selected for award of contract to start work as soon as a contract is signed, if contract is needed.
The City anticipates all work will be completed on or before NO VALUE.
2.2. 2.2. ..................................................................................... Scope of Work
Scope of Work
Summary
The City of Beaverton, OR is seeking qualified contractors to undertake the relocation of the Firestone sewer lateral and the abandonment of the existing sewer main along SW Canyon Rd. The project involves connecting the Firestone sewer lateral to the sewer main on SW Cedar Hills Blvd via a new manhole, utilizing a combination of trenchless and open-trench construction methods. Following the successful relocation of the lateral, the existing sewer main along SW Canyon Rd will be abandoned, and the two existing cleanouts and sewer manhole located on SW Canyon Rd will be removed.
Detailed Specifications
A. Relocation of Sewer Lateral
1. Utilize trenchless construction methods (e.g., pipe bursting, directional drilling) to minimize surface disruption where feasible.
2. Employ open-trench construction methods where trenchless methods are not feasible.
3. Install new manhole in SW Cedar Hills Blvd. Connect existing main and new lateral to new structure.
4. Ensure all new sewer lateral connections meet the following standards:
▪ American Society for Testing and Materials (ASTM) standards for sewer pipes and fittings.
▪ Occupational Safety and Health Administration (OSHA) standards for trench safety.
▪ City of Beaverton/Clean Water Services Standards for sewer construction.
5. Conduct pressure testing and inspection of the new sewer lateral to ensure compliance with all relevant standards and specifications.
B. Abandonment of Existing Sewer Main
1. Disconnect and fill the existing sewer main along SW Canyon Rd with controlled low-strength material to abandon the pipe.
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
2. Remove the two existing cleanouts and sewer manhole located on SW Canyon Rd.
3. Backfill and compact the excavated areas to restore the surface in accordance with ODOT standards and specifications.
i. Concrete sidewalk repair, driveway repair and asphalt pavement repair to ODOT standards.
4. Ensure all abandonment activities comply with the following standards:
▪ ASTM standards for sewer pipe abandonment.
▪ OSHA standards for excavation and trench safety.
▪ City of Beaverton Public Works Standards for sewer abandonment.
▪ ODOT Standard Specifications
C. Pavement Restoration
1. All pavement and concrete restoration work shall be performed in accordance with ODOT standards.
2. All pavement and concrete restoration shall comply with the following:
▪ ODOT pavement and sidewalk standards
▪ ODOT Standard Specifications
D. Traffic Control
1. The Contractor shall submit a traffic control plan for review and approval by the City Traffic
Engineer prior to the start of work.
2. The Contractor shall be responsible for providing all traffic control measures and for supplementing them as needed if the approved traffic control plan proves insufficient
3. All work shall be performed between the hours of 9:00 PM and 5:00 AM.
Service Requirements
A. Contractor must obtain all necessary permits and approvals from the City of Beaverton and other relevant authorities before commencing work. City of Beaverton has already obtained the
ODOT permit and sewer permit.
B. Contractor will submit a traffic control plan that must be approved by the City before work can commence.
C. Contractor must provide a detailed project schedule, including milestones and completion dates, for approval by the City of Beaverton.
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
D. Contractor must maintain a safe and clean worksite, adhering to all OSHA regulations and City of
Beaverton safety standards.
E. Contractor must coordinate with local utilities to identify and avoid existing underground infrastructure.
F. Contractor must provide regular progress reports to the City of Beaverton project manager.
G. Contractor must conduct a final inspection with the City of Beaverton project manager to ensure all work meets the specified standards and requirements.
Delivery Requirements
A. All materials and equipment required for the project must be delivered to the worksite in a timely manner to avoid project delays.
B. Contractor must provide a secure storage area for materials and equipment on or near the worksite.
C. Contractor must ensure that all deliveries comply with the City of Beaverton's traffic and safety regulations.
D. Contractor must dispose of all waste materials in accordance with local, state, and federal regulations.
E. Contractor must restore all disturbed areas to their original condition or better upon completion of the project.
By adhering to the above scope of work, the City of Beaverton aims to ensure the successful relocation of the Firestone sewer lateral and the abandonment of the existing sewer main along SW Canyon Rd, while minimizing disruption to the community and maintaining the highest standards of safety and quality.
LINK to All City of Beaverton Standard Drawings
LINK to All Oregon Department of Transportation (ODOT) Drawings
LINK to ODOT Standard Specifications https://www.beavertonoregon.gov/2025-engineering-standard-drawings https://www.oregon.gov/odot/engineering/pages/standards.aspx https://www.oregon.gov/odot/Business/Specs/2024_standard_specifications.pdf
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
3. 3. ............................................... Proposal Content and Format
Proposals must address all submission requirements set forth in this RFP, and must describe how the services will be provided. Page limits are noted, when relevant, and assume 81/2 x 11 – inch paper and single-spaced lines. Unless otherwise specified, no particular form is required. In order to be considered for selection and possible contract, the proposal must be complete and include the following. Joint proposals will not be accepted. Proposals that merely offer to provide services as stated in this RFP will be considered non-responsive.
3.1. 3.1. ............................ Proposal Format and Administrative Requirements
Proposals must address all submission requirements and must describe how the services will be provided. Unless otherwise specified, no particular form is required.
3.2. 3.2. .......................................................................... Bidding Requirements
Please submit a bid for the items listed below to complete the project, including a brief description with each item explaining what it covers. All work must comply with the standards set by the City of
Beaverton and the Oregon Department of Transportation. There is no required format for the submission.
• Mobilization
• Work Zone Traffic Control
• Erosion Control
• 4" Sanitary Sewer Lateral
• 48" Manhole
• Filling Abandoned Structures
• 4" Concrete sidewalk panels
• 8" Commercial Concrete Bay
• Trench Resurfacing
• Grind and Inlay
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
4. 4. ............................................. Proposer's Special Instructions
4.1. 4.1. ............................................................................... Proposal Submittal
Submissions in response to the RFP shall be submitted electronically through the City's Portal:
https://procurement.opengov.com/portal/beavertonoregon . Proposals are to be submitted Thursday, August 20, 2026, no later than 2:00 pm.
4.2. 4.2. .......................................................................... Procurement Method
The City is conducting this Informal Solicitation pursuant to pursuant to Beaverton Purchasing Code
Section 47-0290. The City seeks proposals that will enable the City to determine which service provider and solution will best meet the City’s needs. The City expects this Informal Solicitation will result in a single contract with a single vendor for the preferred solution.
4.3. 4.3. ................................................................ Questions and Clarifications
All questions regarding this project proposal shall be submitted through the portal.
4.4. 4.4. ................................................ Business License/Taxpayer ID Number
A Proposer awarded a contract shall obtain a City business license as required by Beaverton Code
Section 7.01 prior to beginning work under this contract and must pay all fees due under the Business
License Law during the term of the contract.
A Proposer awarded a contract shall complete an IRS Form W-9 for the City and provide the City with either the Proposer’s Social Security Number or federal taxpayer ID number. This number is requested pursuant to BPC 47-0770 of the Beaverton Purchasing Code. Social Security numbers provided pursuant to this requirement will be used for the administration of state, federal, and local tax laws.
4.5. 4.5. ............................ Contract Administrator and Single Point of Contact
The Contract Administrator will be Danica Ruud, PE, who can be reached by telephone at (971) 482-8292 or by e-mail at mphillips@beavertonoregon.gov.
4.6. 4.6. ...................................................................... Insurance Requirements
Contractor will be expected to meet the insurance requirements of the city when entering a contract, and a sample contract will be provided.
4.7. 4.7. ............................................................................. Multi-Year Contract
At the conclusion of the first contract term, the contract may be renewed under similar terms for up to one (1) additional one-year terms at the option of the City.
4.8. 4.8. ............................................................................... Nondiscrimination
The consultant agrees that, in performing the work called for by this proposal, the consultant shall comply with all federal, state, and local civil rights and rehabilitation laws prohibiting discrimination because of race, sex, national origin, religion, age or disability, and shall comply with all applicable provisions of ORS 279C.500 through 279C.565.
https://procurement.opengov.com/portal/beavertonoregon
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
4.9. 4.9. ..........................................................................Minimum Wage Rates
Each worker in each trade or occupation employed in the performance of the Contract, either by the
Contractor, subcontractor or other person doing or contracting to do or contracting for the whole or any part of the work on the Contract must be paid no less than the applicable state prevailing wage rates, or the applicable federal prevailing wage rates. This project is not subject to federal prevailing wage rates.
The state prevailing wage rates to be paid under the state prevailing wage rate law are set out in the
Bureau of Labor and Industries (“BOLI”) publication entitled “Prevailing Wage Rates for Public Works
Contracts in Oregon” (Region 2) dated July 5, 2026, and all applicable amendments subsequently issued and dated, up to and including Wednesday, July 22, 2026. The BOLI prevailing wage rate publication is available at: https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
BOLI staff is available to assist in determining the applicable wage rates by calling (971) 673-0839.
https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
5. 5. .............................................................. Proposal Submittals
Substantive Requirements
The following information is requested to allow the City to evaluate the Proposer's responsibility and responsiveness to perform work described under the “Scope of Work” heading. If a contract is awarded, City shall award the contract to the responsible Proposer whose proposal it determines in writing to be the most advantageous to the City based on the evaluation process and evaluation factors described in
Section 5 of this RFP, any applicable preferences described in ORS 279A.120 and 279A.125 and, when applicable, the outcome of any negotiations authorized by the RFP. Other factors may not be used in the evaluation.
5.1. 1. ................................................................................................ Proposal* Please refer to the Scope of Work & Proposal Content and Format.
*Response required
5.2. 2. .............................................. First-Tier Subcontractor Disclosure Form* Please download the below documents, complete, and upload.
• First-Tier_Subcontractor_Di...
*Response required
5.3. 3. ....................................................... Authorized Signatory Name & Title* *Response required
5.4. 4. ... Is your firm currently certified by the State of Oregon COBID office?* ☐ Yes
☐ No
*Response required
5.5. 5.If yes, what Certifications do you hold and provide certification number.
5.6. 6. .................................... ATTESTATION of COMPLIANCE with TAX LAWS* By confirming, the authorized signatory, hereby attest that:
A. I am an authorized agent of Bidder/Proposer, and I have full authority from Bidder/Proposer to submit this attestation and accept the responsibilities stated herein.
B. I have knowledge regarding payment of taxes of Bidder/Proposer, and to the best of my knowledge, Bidder/Proposer is not in violation of any Oregon tax laws, including, without limitation, ORS 305.620 and ORS chapters 316, 317 and 318.
C. Bidder/Proposer shall provide written notice to City within two business days of any change to its compliance with tax laws.
☐ Please confirm https://procurement.opengov.com/portal/beavertonoregon/projects/286503/document?section=2761985 https://procurement.opengov.com/portal/beavertonoregon/projects/286503/document?section=2761980 https://government-project.s3.us-west-2.amazonaws.com/286503/cbf48bfb-4548-4983-97db-b5c422fb3bcc_First-Tier_Subcontractor_Disclosure_Form.pdf
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
*Response required
5.7. 7. ..... By confirming, the authorized signatory verifies that they are a duly authorized officer of the company, and that their confirmation attests that information provided in response to this Request for Proposal Solicitation is accurate.*
Request For Proposal CIP 6150 Relocation of Sewer Lateral and Abandonment of Sewer Main – SW
Canyon Rd to SW Cedar Hills Blvd
☐ Please confirm
*Response required
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
6. 6. ................................. Proposal Evaluation & Contract Award
6.1. 6.1. ............................................................................... Evaluation Criteria
Below are the evaluation criteria that will be used to evaluate the proposals:
1. Background and Experience – [20%]
2. Project Approach and Schedule – [10%]
3. Cost - [70%]
6.2. 6.2. .................................................................................... Contract Award
The City may award one contract or multiple contracts, as a result of this procurement. Upon completion of the evaluation process, the selection committee will advise the Proposers of its number one selection via email to all proposers.
6.3. 6.3. ........................................................................... Award Consideration
Whether to award a contract shall be determined by the City in its sole and absolute discretion to be in its best interest. The City reserves the right to withdraw any and/or all items from award consideration.
6.4. 6.4. ................................................................... No Contractual Obligation
The City is not obligated because of the submission of a proposal to enter into a contract with any
Proposer and has no financial obligation to any Proposer arising from this Informal RFP.
Title: Relocation of Sewer Lateral and Abandonment of Sewer Main – SW Canyon Rd to SW Cedar Hills Blvd
7. 7. ........... Beaverton Equity Procurement Program Information
7.1. 7.1. ............................................................................ Program Description
The City is dedicated to increasing opportunities for enterprises that have been certified by the State of
Oregon, through the Certification Office for Business Inclusion and Diversity (COBID). A directory of these state-certified firms is available at www.oregon4biz.com/certification.
The City has an aspirational goal of a 15% utilization of COBID certified companies in its overall dollar value of contracting and purchasing activities.
https://www.oregon4biz.com/certification
| 1. 1. Introduction and Background |
| 1.1. 1.1. Summary |
| 1.2. 1.2. Background |
| 1.3. 1.3. Contact Information |
| 1.4. 1.4. Timeline |
| 2. 2. Scope of Work |
| 2.1. 2.1. Schedule of Work |
| 2.2. 2.2. Scope of Work |
| 3. 3. Proposal Content and Format |
| 3.1. 3.1. Proposal Format and Administrative Requirements |
| 3.2. 3.2. Bidding Requirements |
| 4. 4. Proposer's Special Instructions |
| 4.1. 4.1. Proposal Submittal |
| 4.2. 4.2. Procurement Method |
| 4.3. 4.3. Questions and Clarifications |
| 4.4. 4.4. Business License/Taxpayer ID Number |
| 4.5. 4.5. Contract Administrator and Single Point of Contact |
| 4.6. 4.6. Insurance Requirements |
| 4.7. 4.7. Multi-Year Contract |
| 4.8. 4.8. Nondiscrimination |
| 4.9. 4.9. Minimum Wage Rates |
| 5. 5. Proposal Submittals |
| 5.1. 1. Proposal* |
| 5.2. 2. First-Tier Subcontractor Disclosure Form* |
| 5.3. 3. Authorized Signatory Name & Title* |
| 5.4. 4. Is your firm currently certified by the State of Oregon COBID office?* |
| 5.5. 5. If yes, what Certifications do you hold and provide certification number. |
| 5.6. 6. ATTESTATION of COMPLIANCE with TAX LAWS* |
| 5.7. 7. By confirming, the authorized signatory verifies that they are a duly authorized officer of the company, and that their confirmation attests that information provided in response to this Request for Proposal Solicitation is accurate.* |
| 6. 6. Proposal Evaluation & Contract Award |
| 6.1. 6.1. Evaluation Criteria |
| 6.2. 6.2. Contract Award |
| 6.3. 6.3. Award Consideration |
| 6.4. 6.4. No Contractual Obligation |
| 7. 7. Beaverton Equity Procurement Program Information |
| 7.1. 7.1. Program Description |
File details come from the government source that posted it. Updated .