CODE

(Hour)

PAGE(S)

until 02:00 PM local time 23 Nov 2020

X

A

X B

X C X D

EX

X

G

F 60 - 69

70 - 79

X H 80 - 83 lisa.debolt@navy .mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA

FAR (48 CFR) 53.214(c)

DO-A3 1 83

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N55236 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

NBSD, Bldg 77, Room 108 conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

LISA M DEBOLT (619) 417-1490

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 4

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

5 - 26

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

28 - 30

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 32 - 40 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 41 - 43 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

44 - 58

PART II - CO NTRACT CLAUSES

SOUTHWEST REGIONAL MAINTENANCE CENTER

CODE 410 3755 BRINSER STREET, STE 1

SAN DIEGO CA 92136

(619) 556-4708

(619) 556-2331FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

17 Nov 2020

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N5523621R0005

Section B - Supplies or Services and Prices

NOTE A

Offeror shall complete the "Price Group" and "Estimated Total Price" blocks of each data item on the Contract Data

Requirements List(s), attached hereto.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

1 Lot

LCU 1665

FFP

Prepare for and accomplish emergent repairs on the bow ramp of the LCU 1665 in accordance with Specification Package SSSD 015-21 (Section J, Attachment J-1), as amended.

FOB: Destination

PSC CD: J999

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

1 Lot

Contract Data Requirements List (CDRL)

FFP

The data to be furnished hereunder shall be prepared and submitted in accordance with the CDRL, DD Form 1423, Exhibit A and attached hereto. The CDRLs form a part of the schedule of this solicitation. NOTE "A" applies. Not Separately

Priced (NSP).

PSC CD: J999

NET AMT

See Exhibit A

CLAUSES INCORPORATED BY FULL TEXT

B-227-H001 PROVISIONING TECHNICAL DOCUMENTATION – WITHHOLDING OF PAYMENT

(NAVSEA) (OCT 2018)

(a) For the purpose of paragraph (c) of the "Progress Payments" clause of this contract, if included, the requirement that the Contractor develop and deliver Provisioning Technical Documentation (PTD) is considered to be a "material requirement of this contract," and Contractor failure to make adequate progress in the development of PTD, or to deliver acceptable PTD on a timely basis, may result in reduction or suspension of Progress Payments as provided in said paragraph.

(b) The PTD is considered to be a part of the "Technical Data" specified to be delivered under this contract for the purposes of the "Technical Data--Withholding of Payment" (DFARS 252.227-7030) clause. The terms and conditions of the clause entitled "Limitation On Withholding of Payments (FAR 52.232-9), if included in this contract, shall not apply to withholding of payment for failure to make timely delivery of the PTD or delivery of deficient PTD.

(End of text)

B-231-H002 WORKSITE TRAVEL COSTS (NAVSEA) (OCT 2018)

(a) The contractor shall not charge, and the Government shall not pay, as an allowable cost under this contract, any manhour costs (whether straight-time or overtime) for contractor personnel or subcontractor personnel traveling to or from worksites, including travel to worksites other than the contractor's facility for performance of contract work.

(b) Workers being paid under this contract, as prime contractor personnel or subcontractor personnel, will complete a full shift at the worksite, and no compensation will be paid for travel time before or after the shift.

(c) This requirement pertains only to payments for travel time before or after these workers' regular shifts

(commuting costs), and does not apply to legitimate travel costs incurred during normal working hours, provided that those costs are otherwise reasonable, allocable and allowable and approved in writing by the Government. This requirement does not apply to manufacturer's representatives or Original Equipment Manufacturer (OEM) representatives when specifically required by the Government work specifications.

(d) Additionally, the contractor shall not charge, and the Government shall not pay, any transportation costs under this contract associated with transporting contractor or subcontractor personnel between the contractor's facility (or subcontractor's facility), and any other worksite to perform ship repair, maintenance or modernization.

Transportation costs include, but are not limited to, bus fare, car fare, train fare, or boat fare, paid by the work force, or paid by the contractor on behalf of the work force.

Section C - Descriptions and Specifications

CONTRACT LINE ITEM DESCRIPTION

ITEM 0001 Prepare for and accomplish the emergent repairs on the bow ramp of the LCU 1665 in accordance with

Specification Package SSSD 015-21 (Section J, Attachment J-1), as amended, and as specified herein and in accordance with standard items, work item specifications, drawings, test procedures, and other detailed data provided by the Government listed in Section J.

ITEM 0002 Contract Data Requirements List (Exhibit A).

(a) NAVSEA STANDARD ITEMS have been furnished to each MSRA and ABR contractor under separate cover for retention.

(b) The current NAVSEA standard items applicable to work items of this specification are listed in the Index of

Specifications, contained in the Specification Package (Attachment J-1) of Section J.

(c) Category I Standard Items are applicable to all items without further reference. Category II Standard Items are part of this specification when invoked and/or referenced in individual work items.

PLACE OF PERFORMANCE

(a) Work on the Vessel under this contract shall be performed at: Contractor’s facility

(b) Drydocking shall be accomplished at: Contractor’s facility

(c) All other work shall be accomplished at: Contractor’s facility

Contractor’s facility shall be located within a 125 mile radius of 32nd Street, Naval Base San Diego, CA.

DELIVERY / REDELIVERY SCHEDULE

The Government agrees to deliver the vessel to the Contractor at Naval Amphibious Base Coronado no later than the following “Commencement Date.” The Contractor agrees to redeliver the Vessel to the Government at Naval

Amphibious Base Coronado on the following “Completion Date.”

CLIN VESSEL COMMENCEMENT DATE COMPLETION DATE

0001 LCU 1665 15 DEC 2020 19 FEB 2021

0002 LCU 1665 15 DEC 2020 19 FEB 2021

Dates specified above represent the availability dates of the Vessel.

LCU 1665 must be delivered and mission-ready no later than 19 FEB 2021.

C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)

(a) Department - means the Department of the Navy.

(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the

Department of the Navy or his duly appointed successor.

(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.

(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National

Stock Number (NSN) respectively which shall be defined as follows:

(1) National Item Identification Number (NIIN). The number assigned to each approved Item

Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.

(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.

C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) (OCT 2018)

Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.

C-211-H004 HEAVY WEATHER PLAN (NAVSEA) (OCT 2018)

(a) In order to ensure that Naval vessel(s), material and Government property are protected during destructive weather such as gales, storms, hurricanes, high winds, heavy snow, ice and high water, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69 dated 18 November 2016. A copy of Standard Item (SI) 009-69 can be obtained from via the internet by going to:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard

Items (NSI) tab then select the applicable FY standard item link and then select SI 009-69. In accordance with SI 009-

69, the Contractor shall furnish to the cognizant Regional Maintenance Center (RMC), a copy of such HWP, and shall make such changes in the plan as the RMC considers necessary and reasonable to protect and care for vessel(s), material and Government property.

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/

(b) In the event the RMC directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such

Government direction.

C-211-H005 PLANT PROTECTION (NAVSEA) (OCT 2018)

(a) In accordance with NAVSEA STANDARD ITEM (SI) 009-72, (8/31/2018) the Contractor shall develop, maintain, and implement, as necessary, a Plant Protection Plan (TBD) which prescribes the actions and procedures and assigns responsibilities for actions to be taken to provide adequate protection of the ship(s) and the materials and equipment to be installed therein. A copy of SI 009-72 can be obtained from the purchasing office representative listed in Section G of the contract or via the internet by going to http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard

Items (NSI) tab then select the applicable FY standard item link and then select SI 009-72.

(b) The Contractor shall establish and maintain, for its plant and the work in process under this contract, physical security boundaries and other security measures to provide safeguards against hazards, including unauthorized entry, malicious mischief, theft, espionage, sabotage, and terrorism to U.S. Naval Vessels and their crews, in accordance with SI 009-72 and Attachment A thereto. The Contractor shall also provide reasonable safeguards against vandalism and fire.

(c) The Contractor shall meet the requirements of Force Protection Condition NORMAL (as defined in SI 009-72) at all times. In addition, and in accordance with SI 009-72, the Contractor shall meet the requirements of increased levels of Force Protection as may be required or approved by the Contracting Officer, or when notified by the

Supervisor, for the protection of its plant and the work in process under this contract against any threats including terrorism, espionage, sabotage, and enemy action.

(d) At the Supervisor’s discretion, the Contractor and the Supervisor shall negotiate a cost rate agreement applicable to each level of increased Force Protection above the NORMAL level. In addition to material costs, the labor cost rates shall be negotiated using the contractor’s and the Supervisor’s accepted common business practices. The labor and material costs to the Contractor for all safeguards so required or approved shall, to the extent allowable and allocable to this contract, be reimbursed to the Contractor in the same manner as if the Contractor has furnished such safeguards pursuant to a change order issued under the clause of this contract entitled "Changes--Fixed Price" (FAR

52.243-1) or "Changes--Cost-Reimbursement" (FAR 52.243-2), as applicable. Such costs shall not include any allowance on account of overhead expense, except shop overhead charges incident to the construction or installation of such devices or equipment.

(e) Upon payment, in accordance with the Payments provision of this contract, by the Government of the cost to the

Contractor for any device or equipment required or approved under paragraph (c) above, title thereto shall vest in the

Government, and the Contractor shall comply with the instructions of the Contracting Officer respecting the identification and disposition thereof. No part or item of any such devices or equipment shall be or become a fixture by reason of affixation to any realty not owned by the Government.

(f) The plant protection plan and rate agreements required by this requirement shall be completed and implemented, within sixty (60) days of contract award for new construction and prior to ship arrival for conversion, repair or overhaul.

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/

C-211-H008 QUALIFICATION OF CONTRACTOR NON-DESTRUCTIVE TESTING (NDT) PERSONNEL

(a) The Contractor and any Non-destructive Testing (NDT) subcontractor shall utilize for the performance of required NDT, only Level I, II and III personnel currently certified in accordance with NAVSEA Technical

Publication T9074-AS-GIB-010/271, Revision 1 of 11 September 2014. Documentation pertaining to the qualification and certification of NDT personnel shall be made available to the Contracting Officer for review upon request.

(b) These requirements do not apply with respect to nuclear propulsion plant systems and other matters under the technical cognizance of the Office of Navy Nuclear Propulsion (NAVSEA 08). Because of health and safety considerations, such matters will continue to be handled as directed by NAVSEA 08.

C-211-H010 TUG AND PILOT SERVICES (NAVSEA) (OCT 2018)

The Contractor shall provide necessary tug and pilot services to move the vessel(s) from the fairway of the plant to the pier or dock, and upon completion of all work from the pier or dock, to the fairway of the plant.

C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.

None

C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)

The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.

C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)

Approval by the Government as required under this contract and applicable specifications shall not relieve the

Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

C-211-H020 PROTECTION OF THE VESSEL (NAVSEA) (MAR 2019)

(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free

Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.

(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.

(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.

(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.

(End of Text)

C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal (TBD) dated (TBD) in response to

Solicitation No. N5523621R0005.

(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following

"the specifications" in the order of precedence.

C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)

(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within 30 days of discovery:

(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,

(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.

(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and

Above Work and it provides the process for adjudication.

(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.

(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.

C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019)

(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by

COMNAVSEA or his designated representative that such access should be permitted in the best interest of the

United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST

5510.2D.

(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access

Control Plan (ACP) which shall contain as a minimum, the following information:

(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.

(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.

(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.

(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.

(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.

(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.

(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.

(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.

(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.

(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by

Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-

U.S. citizens of hostile and/or communist-controlled countries.

(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved

ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the

CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "Default (Fixed-Price Supply and Service)" (FAR 52.249-8), "Default

(Fixed-Price Research and Development)" (FAR 52.249-9) or "Termination (Cost Reimbursement)" (FAR 52.249-

6), as applicable.

(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.

(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.

(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the

Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S.

Navy personnel who are non-U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.

C-223-H002 SAFETY, HEALTH AND FIRE REQUIREMENTS FOR SHIP REPAIR (NAVSEA) (JAN 2019)

(a) Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.13). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.

(b) SAFETY INSPECTOR/FIRE MARSHAL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety

Representative. This Inspector or Fire Marshal shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.

(c) PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:

(1) Protective hard hats that meet the following specifications:

(i) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American

National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated by the Contractor to be equally effective.

(ii) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National

Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]

(2) Approved type Plano or prescription glasses meeting the following specifications:

(i) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-

1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.

(ii) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]

(3) Safety toe shoes, with built-in protective toe box that meet the following specifications:

(i) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.

(ii) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA

Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]

C-223-H003 EXCLUSION OF MERCURY (NAVSEA) (MAR 2019)

(a) Definitions. As used in this text:

Article means a manufactured item other than a fluid or particle: (i) which is formed to a specific shape or design during manufacture; (ii) which has end use function(s) dependent in whole or in part upon its shape or design during end use; and (iii) which under normal conditions of use does not release more than very small quantities, e.g., minute or trace amounts of a hazardous chemical, and does not pose a physical hazard or health risk to employees.

Boundary of containment means a continuous tight seal (barrier) to prevent the release of functional mercury during normal operation and maintenance. Examples include the exterior of a fluorescent lamp, glass capsule of a mercury switch, and container for mercury reagents. A double boundary of containment consists of two independent seals.

Functional mercury means mercury or mercury compound(s) contained in equipment that is required for the equipment to operate properly, such as that found in mercury switches, fluorescent lamps, flat-panel monitors, thermostats, thermostat probes, small coin type batteries, barometers, and dental amalgams.

Hardware means any article, container, piece of material, individual part, subassembly, assembly, component, or system to which mercury control requirements apply.

Mercury-free means hardware that does not contain functional mercury and is not contaminated by mercury or mercury compounds.

Portable means items that are frequently transported during normal operation. Desk lamps, shop lights, and hand-held instruments are considered portable, while bulbs in stationary light fixtures are not. In general, items that require transport only during maintenance, installation, and removal of the items are not considered portable.

(b) The Contractor, and all subcontractors and vendors, shall ensure that mercury or mercury containing compounds are not intentionally added to, or come in direct contact with, hardware or supplies furnished under this contract.

(1) The Contractor shall ensure that mercury and mercury compounds are not taken onboard naval vessels by Contractor, subcontractor, or vendor personnel except for functional mercury used in batteries, dental amalgams, fluorescent lamps, flat-panel monitors, required instruments, sensors or controls, weapon systems, and chemical analysis reagents specified by the Naval Sea Systems Command (NAVSEA).

(2) Portable fluorescent lamps and portable instruments containing elemental mercury must be shock-proof in accordance with MIL-DTL-901E entitled Requirements for Shock Tests, H.I. (High Impact) Shipboard

Machinery, Equipment, and Systems and have mercury enclosed by a double boundary of containment. Some devices with liquid crystal display (LCD) screens utilize a fluorescent bulb backlight to illuminate the LCD screen.

No additional restrictions or controls apply to devices with LCD screens; however, the Contractor shall remove the

LCD screen and seal it in plastic following any evidence that the backlight failed.

(3) For Submarines, any use of mercury containing items must be approved as required by the Nuclear

Powered Submarine Atmosphere Control Manual (S9510-AB-ATM-010/U) Volume 1.

(4) The Contractor shall ensure that mercury and mercury compounds do not contact hardware surfaces in systems covered by NAVSEA Manual NAVSEA 0989-064-3000 entitled Cleanliness Requirements for Nuclear

Propulsion Plant Maintenance and Construction, submarine air systems, level I systems per NAVSEA Publication

0948-LP-045-7010, NAVSEA Material Control Standard, or the submarine safety program (SUBSAFE) surfaces during maintenance or repair. Such hardware is designated as mercury-free. The Contractor shall ensure that all other hardware that could be structurally degraded by contamination with elemental mercury or reactive mercury compounds is separated from it by sufficient distance, or boundaries of containment that effectively prevents contact in all but the most extreme circumstances.

(5) The Contractor shall check any hardware surfaces in the above systems which are known or suspected to have come in contact with mercury or mercury compounds for evidence of structural degradation and external mercury contamination. The existence of external mercury contamination can be determined following MIL-STD-2041D entitled Control of Detrimental Materials.

(6) The presence of mercury in a product may be determined by checking product labeling on material safety data sheets or safety data sheets. Chemical analysis is not required.

(7) The Contractor shall dispose of any mercury and mercury compounds in accordance with OPNAV

Manual (OPNAV M-5090.1) entitled Environmental Readiness Program Manual of 10 January 2014.

(8) If the use of mercury or mercury compounds cannot be avoided, a risk assessment and waiver request, if required, must be performed and submitted per the NAVSEA Hazardous Material Avoidance Process (T9070-AL-

DPC-020/077-2). For systems covered by the NAVSEA Manual NAVSEA 0989-064-3000 entitled Cleanliness

Requirements for Nuclear Propulsion Plant Maintenance and Construction, submit the risk assessment and waiver request, if required to Nuclear Propulsion (NAVSEA 08).

(c) In all cases where mercury or a mercury compound has contacted hardware surfaces required to be mercury-free the Contractor shall immediately provide a report to the NAVSEA Dry Environmental Systems and Hazardous

Materials (NAVSEA 05P5) via the cognizant contract administration safety office. Reports concerning systems covered by NAVSEA Manual 0989-064-3000 must include NAVSEA Nuclear Propulsion Directorate (SEA 08) in the distribution. Reports must be in letter form and include the date and details of the contact, the surfaces contacted, the recovery actions taken, and the status of the affected surfaces.

C-223-H004 MANAGEMENT AND DISPOSAL OF HAZARDOUS WASTE (NAVSEA) (MAR 2019)

(a) General

(1) The Contractor shall comply with the Resource Conservation and Recovery Act (RCRA), the

Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), 10 U.S.C. 7311 and all other applicable Federal, State and local laws, codes, ordinances and regulations for the management and disposal of hazardous waste.

(2) Nothing contained in this special contract requirement shall relieve the Contractor from complying with applicable Federal, State, and local Laws, codes, ordinances, and regulations, including obtaining licenses and permits, giving notices and submitting reports, in connection with hazardous waste management and disposal in the performance of this contract. Nothing contained herein shall serve to alter either party's liability or responsibility under CERCLA.

(3) Materials contained in ship systems are not waste until after removal from the system.

(b) Identification of Hazardous Wastes – Work Item 077-11-001 of this contract identifies the types and amounts of hazardous wastes that are required to be removed by the Contractor, or that are expected to be generated, during the performance of work under this contract.

(c) Generator Identification Numbers

(1) Documentation related to hazardous waste generated solely by the physical actions of ship's force or Navy employees on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law.

(2) Documentation related to hazardous waste generated solely by the physical actions of Contractor personnel shall only bear a generator identification number issued to the Contractor pursuant to applicable law. Regardless of the presence of other materials in or on the shipboard systems or structures which may have qualified a waste stream as hazardous, where the Contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator identification number issued to the

Contractor.

(3) Documentation related to hazardous waste generated by the combined physical actions of Navy and

Contractor personnel shall bear a generator identification number issued to the Contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law.

(4) Notwithstanding paragraphs (c)(1) - (c)(3) above, hazardous wastes are considered to be co-generated in cases where: (a) the Contractor merely drains a system and such drainage creates hazardous waste or (b) the

Contractor performs work on a system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste. Documentation related to such co-generated waste shall bear a generator identification number in accordance with the provisions of paragraph (c)(3) above.

(5) In the event of a failure by the parties to agree to the assignment of a generator identification number to any hazardous waste as set forth in paragraphs (c)(1) through (c)(4) above, the Government may direct which party or parties shall provide generator identification numbers for the waste and such number(s) shall be used on all required documentation. Any disagreement with this direction shall be a dispute within the meaning of clause of this contract entitled "Disputes" (FAR 52.233-1). However, the Contractor shall not stop any work but shall continue with performance of all work under this contract as specified in the "DISPUTES" clause.

(6) Hazardous Waste Manifests - For wastes described in (c)(2), (c)(3), and (c)(4) above (and (c)(5) as applicable), the Contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the Manifest is required for disposal. The Contractor shall obtain Project Manager (PM) or

Shipbuilding Specialist (SBS) concurrence with the categorization of wastes under paragraphs (c)(3) and (c)(4) above before completion of the manifest. Manifests prepared pursuant to paragraph (c)(1) above shall be presented to the PM or SBS for completion after the hazardous waste has been identified.

(7) For purposes of paragraphs (c)(2) and (3) herein, if the Contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the State in which the availability will be performed, the Contractor shall notify the PM or SBS within 3 business days of receipt of written notification by the

State. After obtaining PM or SBS approval, the Contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located. For purposes of paragraph (c)(1) herein, if the work is being performed at a contractor facility and the Government cannot obtain a separate generator identification number for the State, the Government shall use the Contractor site generator identification number and shall cite in the remarks block a Navy generator identification number. In both instances described above, the Contractor shall prepare the Uniform Hazardous

Waste Manifest described in paragraph (c)(6) above and present it to PM or SBS for completion.

C-223-W002 ON-SITE SAFETY REQUIREMENTS (NAVSEA) (OCT 2018)

(a) The contractor shall ensure that each contractor employee reads any necessary safety documents within 30 days of commencing performance at any Government facility. Required safety documents can be obtained from the respective safety office. Contractors shall notify the Safety office points of contact below to report completion of the required training via email. The email shall include the contractor employee’s name, work site, and contract number.

(b) It is expected that contractor employees will have received training from their employer on hazards associated with the areas in which they will be working and know what to do in order to protect themselves. Contractors are required to adhere to the requirements of 29 CFR 1910, 29 CFR 1926 and applicable state and local requirements while in Government spaces. The contractor shall ensure that all on-site contractor work at the Government facility is in accordance with any local safety instructions as provided via the COR. The contractor shall report all work-related injuries/illnesses that occurred while working at the Government site to the COR.

(c) Contractors whose employees perform work within Government spaces in excess of 1000 hours per calendar quarter during a calendar year shall submit the data elements on OSHA Form 300A, Summary of Work Related

Injuries and Illnesses, for those employees to the safety office, via the COR by 15 January for the previous calendar year, even if no work related injuries or illnesses occurred. If a contractor’s injury/illness rates are above the Bureau of Labor Statistics industry standards, a safety assessment may be performed by the Safety Office to determine if any administrative or engineering controls can be utilized to prevent further injuries/illnesses, or if any additional

Personal Protective Equipment or training will be required.

(d) Any contractor employee exhibiting unsafe behavior may be removed from the Government site. Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.

(e) The Safety Office points of contacts are as follows:

Andres Quinones, Code 106B, (619) 556-1056; andres.quinones@navy.mil

C-227-H009 ACCESS TO DATA OR COMPUTER SOFTWARE WITH RESTRICTIVE MARKINGS (NAVSEA)

(JAN 2019)

(a) Performance under this contract may require that the Contractor have access to technical data, computer software, or other sensitive data of another party that contains restrictive markings. If access to such data or software is required or to be provided, the Contractor shall enter into a written agreement with such party prior to gaining access to such data or software. The agreement shall address, at a minimum, (1) access to, and use of, the restrictively marked data or software exclusively for the purposes of performance of the work required by this contract, and (2) safeguards to protect such data or software from unauthorized use or disclosure for so long as the data or software remains properly restrictively marked. In addition, the agreement shall not impose any limitation upon the Government or its employees with respect to such data or software. A copy of the executed agreement shall be provided to the Contracting Officer. The Government may unilaterally modify the contract to list those third parties with which the Contractor has agreement(s).

mailto:andres.quinones@navy.mil

(b) The Contractor agrees to: (1) indoctrinate its personnel who will have access to the data or software as to the restrictions under which access is granted; (2) not disclose the data or software to another party or other Contractor personnel except as authorized by the Contracting Officer; (3) not engage in any other action, venture, or employment wherein this information will be used, other than under this contract, in any manner inconsistent with this requirement; (4) not disclose the data or software to any other party, including, but not limited to, joint venturer, affiliate, successor, or assign of the Contractor; and (5) reproduce the restrictive stamp, marking, or legend on each use of the data or software whether in whole or in part.

(c) These restrictions on use and disclosure of the data and software also apply to information received from the

Government through any means to which the Contractor has access in the performance of this contract that contains restrictive markings.

(d) The Contractor agrees that it will promptly notify the Contracting Officer of any attempt to gain access to any information with restrictive markings. Such notification shall include the name and organization of the individual, company, or Government representative seeking access to such information.

(e) The Contractor shall include this requirement in subcontracts of any tier…

This is the start of the file's text. The full file is on GovTribe.