Summary of changes on Mar 5.doc
DOC document 23 KB Posted
- Solicitation number
- Not on record
About this file
Summary of changes on Mar 5 2010.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 1442 MP Mar 7.pdf | ||
| Contract Price Form R1.xls | XLS spreadsheet | |
| Brdg Docs MenloPark-Mech Controls Drft V9 to GSA 022510.pdf | ||
| Questions and Answers Part 2.doc | DOC document | |
| USGS_SIGN_IN_SHEET.pdf | ||
| Questions and Answers.doc | DOC document | |
| Mar 1 Menlo Park Solicitation instructions R1.doc | DOC document | |
| sf24 - bid bond.pdf | ||
| MenloParkPoints.csv | CSV file | |
| MenloParkPoints.pdf | ||
| Contract Price Form R1.xls | XLS spreadsheet | |
| Menlo Park Specifications Revised 030110 MenloPark.pdf | ||
| Mar 1 Menlo Park Agreement R1.doc | DOC document | |
| specs for GSA furnished computers.pdf | ||
| Reps and certs.doc | DOC document | |
| About GP4 Files.doc | DOC document | |
| GSA Order Document Security.pdf | ||
| CAD_standards_R2NY1-k_0Z5RDZ-i34K-pR.pdf | ||
| USGS MP - Feb 28 Amendment.zip | ZIP file | |
| M 1.0 USGS Campus Level Network.pdf | ||
| Specifications_Final_MenloPark.docx | DOCX document | |
| M 1.1 Building Level Network Concept.pdf | ||
| FBO.zip | ZIP file |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARRA USGS Menlo Park HVAC
March 5, 2010 Amendment:
1. Revised Scope of Work is posted. The changes were posted last week, but we believe the actual revised SOW document was omitted. Changes are as follows with changes identified by vertical line in margin:
a. Project 1A, Page 17 – added a sentence to require two training sessions for the lab occupants for the new fume hood controls
b. Project 1A, Page 18 – added a paragraph to describe the existing Phoenix controls in the one lab, but stated the scope remains the same and the existing controls and valves cannot be reused.
c. Project 1A, Page 18 – added that there is one CV exhaust fan (EF-22) that serves one lab, not fume hoods and shall remain CV
d. Project 1A, Page 18 – added the word “arrangement” as there may be two sash’s per fume hood, so it’s an ODP per arrangement
e. Project 1A, Page 18 – added that the electrical power panels for the labs are located in the corridors outside the labs. The new controls shall be feed from normal power, not emergency power.
i. Did you want us to state that there are spares circuits or assume there are spare circuits? I did not include this.
f. Added additional photographs on pages 39 to 49 (18 more photos). Included a note that the above ceiling conditions may not be representative of all lab rooms. Ok?
g. Project 2, Page 51 – added the scope for replacing the 29 pneumatic actuators in Building 15
h. Project 6, Page 55 and 56 – scope change for the BAS Networks.
i. Project 9, Page 62 – clarified that all HW valves are two-way
j. Project 10, Page 66 – added Building One, so they bypass leg balance valves are closed in both Building One and Two
k. Project 15, Page 87 – removed Building 11 from the air-side economizer
l. Project 16, Page 96 – took out building gas and water meters and added Addendum to make consistent with other buildings.
2. Questions and answers are posted.
3. Zip files with enlarged versions of drawings (all previously provided, but difficult to read) are posted. These are secured.
4. We are posting PDF copies of the Building 15 (McKelvey FB) mechanical drawings.
5. Site Visit sign in sheet