Receiving Dock Replacement Scope of Work
This Scope of Work document pertains to the Department of Mental Health (DMH) in Illinois for the replacement and reconstruction of receiving dock infrastructure at the Alton Mental Health Center (AMHC). The project encompasses the complete replacement or reconstruction of three receiving docks located at the Willow Building, Storeroom, and Forensic Center facilities. The work includes demolition of existing dock structures as necessary, reconstruction of dock platforms, installation of new concrete stairs and handrails or repair of existing structures, installation of dock bumpers, restoration of adjacent concrete sections, and adjustments to dock height and angles to ensure proper truck interface and operational functionality. The scope of work establishes the technical requirements and performance standards that contractors must meet to complete this capital improvement project.
The document serves as the foundational specification document for bidders to understand the full extent of work required, enabling accurate cost estimation and project planning. While specific response dates, bid submission deadlines, site visit schedules, and award timelines are not detailed in this scope of work document, contractors utilizing this specification should reference the associated contract opportunity posting for complete bidding information, financial terms, and project schedule requirements. The scope of work represents the technical backbone of the procurement, detailing the physical work required at each dock location to bring the receiving facilities to current operational standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| standard terms.pdf | ||
| RMU150~77.docx | DOCX document | |
| Self-Performance Requirements~9.docx | DOCX document | |
| standard illinois certifications~2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Alton Mental Health Center B-54505
SCOPE OF WORK
Receiving Dock Replacement – Three Buildings Willow Building • Storeroom • Forensic Center Dock Reconstruction • Concrete Stairs & Handrails • Bumper Installation • Concrete Restoration • Height & Angle Adjustments
| Project Locations |
| Three Receiving Docks – Willow Building, Storeroom, Forensic Center |
| Project Type |
| Receiving Dock Replacement / Reconstruction |
| Primary Scope |
| Full dock reconstruction; concrete stairs & handrails; dock bumpers; concrete section restoration; height and angle adjustments as required |
| Document Status |
| Preliminary Scope – For Budgeting / Bidding Purposes |
1. Project Overview This Scope of Work defines the requirements for the complete replacement / reconstruction of three (3) receiving docks located at the Willow Building, Storeroom, and Forensic Center. Work includes demolition of existing dock structures as required, reconstruction of dock platforms to the specified dimensions, installation of new concrete stairs and handrails (or repair of existing), installation of dock bumpers, restoration of adjacent concrete sections, and specific height and angle adjustments to ensure proper truck interface.
The completed work shall provide safe, durable, code-compliant receiving docks suitable for ongoing material handling and delivery operations, with proper vehicle clearance, pedestrian access via stairs and handrails, and impact protection via dock bumpers.
*Attendance at the mandatory pre-bid meeting is required prior to submitting a bid.
Dock Dimensions Summary
| Location |
| Length |
| Depth |
| Height |
| Willow Building |
| 32 ft 6 in |
| 9 ft 7 in |
| 43 in |
| Storeroom |
| 12 ft 7 in |
| 8 ft 7 in |
| 32 in |
| Forensic Center |
| 18 ft 0 in |
| 8 ft 0 in |
| 46 in |
2. General Requirements (All Docks) The following requirements apply to all three dock locations unless otherwise noted in the individual dock sections.
2.1 Demolition
1. Remove existing dock structures, platforms, ramps, and associated components as required to accommodate new construction
1. Remove existing stairs, handrails, and bumpers designated for replacement or repair
1. Saw-cut and remove damaged concrete sections identified for restoration
1. Protect adjacent building structure, overhead doors, walls, and finishes during demolition
1. Remove all debris from the site daily; dispose of materials in accordance with applicable regulations
1. Leave work areas broom-clean at the end of each workday
2.2 New Dock Construction
1. Construct new reinforced concrete dock platforms to the dimensions specified for each location
1. Dock structures shall be constructed for anticipated truck and material loads.
1. Provide proper foundations, reinforcement, expansion joints, and drainage details
1. Concrete shall meet or exceed local structural and durability requirements
1. Provide smooth, level working surfaces suitable for material handling equipment and pedestrian traffic
1. Coordinate dock elevation and edge details with existing building floor elevations and overhead door thresholds
2.3 Dock Bumpers
1. Furnish and install new dock bumpers at all three docks
1. Bumpers shall be heavy-duty rubber or laminated dock bumpers sized and rated for commercial truck impact
1. Mount bumpers securely to the dock face at appropriate height and spacing to protect both the dock structure and delivery vehicles
1. Provide all necessary anchors, brackets, and hardware for a complete, durable installation
1. Basis-of-design: commercial-grade laminated rubber dock bumpers or approved equal
2.4 Concrete Restoration
1. Restore damaged or deteriorated sections of concrete adjacent to or associated with each dock
1. Prepare substrates by removing loose or unsound concrete, cleaning, and applying bonding agents as required
1. Repair with compatible structural repair mortar or concrete matching existing strength and finish
1. Provide proper curing and protection of repaired areas
2.5 Codes & Standards
1. All work shall comply with applicable building codes, including structural, accessibility (ADA), and life-safety requirements
1. Stairs and handrails shall meet current code requirements for rise/run, handrail height, and extensions to function properly with height of the dock
3. Willow Building Dock Location-specific requirements for the Willow Building receiving dock.
3.1 Dimensions
1. Length: 32 feet 6 inches
1. Depth: 9 feet 7 inches
1. Height: 43 inches (above grade or truck-bed reference as determined by design)
3.2 Height Adjustment
1. Evaluate existing truck interface; trucks currently sit too high when backed up to the dock
1. Adjust dock height slightly as required to achieve proper truck-bed alignment for safe and efficient loading/unloading. If proper alignment is unachievable, then a dock lift may be installed
1. Final height shall be confirmed during mandatory pre-bid meeting onsite based on typical delivery vehicle bed heights which are generally estimated between 40” to 50”
3.3 New Concrete Stairs & Handrails
1. Furnish and install a new set of concrete stairs on the side of the dock
1. Stairs shall provide safe pedestrian access between grade and dock level
1. Furnish and install new handrails on both sides of the stairs (or as required by code)
1. Handrails shall be commercial-grade, corrosion-resistant (galvanized steel, aluminum, or stainless steel), meeting code height, and extension requirements
1. Provide proper footings, landings, and connections to the dock structure
3.4 Concrete Section Restoration
1. Restore sections of concrete identified as damaged or deteriorated in the dock and adjacent areas
1. Coordinate restoration with new dock construction and stair installation to achieve a continuous, durable surface
4. Storeroom Dock Location-specific requirements for the Storeroom receiving dock.
4.1 Dimensions
1. Length: 12 feet 7 inches
1. Depth: 8 feet 7 inches
1. Height: 32 inches
4.2 Stairs & Handrail Repair
1. Repair existing concrete steps serving the Storeroom dock
1. Repair or replace handrail as required to restore full structural integrity to meet code compliance for safe operation
1. Repairs shall match existing configuration where feasible while meeting current code requirements for rise/run and handrail standards
1. Replace any severely damaged treads, risers, or structural components; patch and refinish remaining sound concrete
4.3 Dock Bumpers
1. Install new dock bumpers as described in Section 2.3
5. Forensic Center Dock Location-specific requirements for the Forensic Center receiving dock.
5.1 Dimensions
1. Length: 18 feet 0 inches
1. Depth: 8 feet 0 inches
1. Height: 46 inches
5.2 Angle Adjustment for Ramp Approach
1. Trucks back down a ramp to approach this dock; the dock face / approach angle requires adjustment
1. Evaluate the existing approach geometry and truck turning/backing path
1. Adjust dock orientation, face angle, or approach apron as required so that trucks can square up properly and achieve safe, level engagement with the dock
1. Coordinate any approach paving or concrete work with the dock reconstruction
1. Final geometry shall be confirmed by design based on site survey and typical vehicle dimensions
5.3 Stairs & Handrail Repair
1. Repair existing concrete steps serving the Forensic Center dock
1. Repair or replace handrail as required to restore full structural integrity, code compliance, and safe use
1. Repairs shall meet current code requirements for rise/run and handrail standards
5.4 Dock Bumpers
1. Install new dock bumpers as described in Section 2.3
6. Materials, Quality & Workmanship
1. All concrete work shall be performed by contractors familiar with structural and site concrete construction
1. Reinforcing steel shall conform to ASTM standards; placement shall follow approved shop drawings
1. Formwork, placement, finishing, and curing shall follow ACI guidelines and manufacturer recommendations
1. Handrails and metal fabrications shall be fabricated and installed to commercial standards with proper corrosion protection
1. Dock bumpers shall be from a commercial manufacturer and installed per manufacturer instructions
1. Provide samples or product data for owner approval prior to procurement of bumpers, handrail finishes, and any exposed architectural concrete finishes
7. Testing, Inspection & Closeout
1. Verify that dock heights and angles achieve proper truck interface; adjust as necessary before final acceptance
1. Verify stairs and handrails meet code and are secure
1. Verify dock bumpers are properly mounted and functional
1. Provide operation and maintenance information for any manufactured components (bumpers, handrail systems)
1. Leave all work areas clean and free of debris upon completion
8. Assumptions & Exclusions
8.1 Assumptions
1. Existing site access and staging areas will be made available for construction equipment and materials
1. Utility locates will be performed prior to excavation; any conflicts will be coordinated with the owner
1. Existing building structure and foundations adjacent to the docks are adequate or will be addressed if deficiencies are discovered during design or demolition
1. Typical delivery vehicle types and bed heights will be provided by the owner or surveyed during mandatory pre-bid meeting to confirm final dock elevations
1. Work may be sequenced to maintain partial operational capability at each facility if continuous receiving operations are required
1. Weather protection and temporary measures during construction are the responsibility of the contractor
8.2 Exclusions
1. Interior building renovations or modifications beyond the dock interface
1. Overhead door replacement or repair (unless damaged by the dock work)
1. Site paving, striping, or landscaping beyond restoration of areas disturbed by the dock and stair work
1. Full redesign of approach roads or ramps beyond the angle adjustment described for the Forensic Center dock
9. Deliverables
1. Shop drawings for reinforcing, handrails, and fabricated components
1. Product data and samples for dock bumpers and handrail finishes
1. Basic drawings showing final dimensions, elevations, and details
1. Warranty documentation for materials and workmanship
10. Notes All work shall be performed in accordance with applicable codes, standards, and regulations, including but not limited to the International Building Code, ACI concrete standards, accessibility standards (ADA / ICC A117.1), and local amendments.
Contractor shall coordinate all work with facility operations to minimize disruption to ongoing receiving and security functions at each location.