ESTIMATE OF QUANTITIES 3278 STEWARDSHIP/ERFO PROJECT SHEET
OF
ROAD NUMBER 3278
PROJECT LENGTH (MILES) 1.65
ITEM NO. DESCRIPTION UNIT QUANTITIES
15101 Mobilization Lump Sum ALL
30318 Roadway reconditioning, roadbed, compaction method B Mile 1.65
32203 Aggregate base, grading C, compaction B CY* 118
40401 Hot asphalt concrete mixture Ton 1407.2
WORK DESCRIPTION
M.P. 0.00 BOP: Junction with County Road 5130 Indian Creek
M.P. 0.44
Place shoulder rock (Item 32203).
M.P. 0.60
Place shoulder rock (Item 32203).
M.P. 0.85 Begin placement of shoulder rock (Item 32203).
M.P. 1.65
End placement of shoulder rock (Item 32203).
Place and compact 3" depth Hot asphalt concrete mixture 100' ahead and back. Match to existing subgrade including 1-4' curve widening. Construct transition zones at each end (Pay Item 40401).
RP (reference point): Live stream with culvert.
Begin Roadway reconditioning (Item 30318).
Begin placement and compacion of 3" depth Hot asphalt concrete mixture. Construct transition zone (Pay Item 40401).
End Roadway reconditioning (Item 30318).
End placement and compacion of 3" depth Hot asphalt concrete mixture. Construct transition zone (Pay Item 40401).
EOP
Place and compact 3" depth Hot asphalt concrete mixture 100' ahead and back. Match to existing subgrade including 1-2' curve widening. Construct transition zones at each end (Pay Item 40401).
GENERAL NOTES:
RP (reference point): Live stream with culvert.
1) Waste Area : 6' Maximum height of material, 1V:2H slopes, shape to drain.
2) Work includes all turnouts and curve widening.
3) All water rights and permits are the responsibility of the contractor.
Use ODOT HMAC 1/2" dense, Level II asphalt mix designation with PG 64-22 asphalt cement. Includes all excavation and transition zone construction.
Commercial source. Contractor sampling and testing included.
Shoulder rock. Commercial source. Contractor sampling and testing included.
Scarify potholes and irregularities to a 6" maximum depth.
REMARKS
* Denotes Contract Quantities
Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
Includes equipment cleaning, fire equipment and traffic control.