fbo_Sheet 3 of 5.pdf

PDF 8 KB Posted

Attached to
STEWARDSHIP AND ERFO ROAD 3278
Solicitation number
R6-12-09-298472
Issued by

About this file

Sheet 3 of 5

View the file

Other files

File Type Posted
fbo_Sheet 2 of 5.pdf PDF
fbo_Sheet 5 of 5.pdf PDF
fbo_Sheet 1 of 5.pdf PDF
fbo_Project Specifications.pdf PDF
SF 24.pdf PDF
fbo_Sheet 4 of 5.pdf PDF
fbo_Project Specification List.pdf PDF
fbo_09-298472_Packet to complete and return.pdf PDF
fbo_09-298472_Road 3278 Solicitation Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESTIMATE OF QUANTITIES 3278 STEWARDSHIP/ERFO PROJECT SHEET

OF

ROAD NUMBER 3278

PROJECT LENGTH (MILES) 1.65

ITEM NO. DESCRIPTION UNIT QUANTITIES

15101 Mobilization Lump Sum ALL

30318 Roadway reconditioning, roadbed, compaction method B Mile 1.65

32203 Aggregate base, grading C, compaction B CY* 118

40401 Hot asphalt concrete mixture Ton 1407.2

WORK DESCRIPTION

M.P. 0.00 BOP: Junction with County Road 5130 Indian Creek

M.P. 0.44

Place shoulder rock (Item 32203).

M.P. 0.60

Place shoulder rock (Item 32203).

M.P. 0.85 Begin placement of shoulder rock (Item 32203).

M.P. 1.65

End placement of shoulder rock (Item 32203).

Place and compact 3" depth Hot asphalt concrete mixture 100' ahead and back. Match to existing subgrade including 1-4' curve widening. Construct transition zones at each end (Pay Item 40401).

RP (reference point): Live stream with culvert.

Begin Roadway reconditioning (Item 30318).

Begin placement and compacion of 3" depth Hot asphalt concrete mixture. Construct transition zone (Pay Item 40401).

End Roadway reconditioning (Item 30318).

End placement and compacion of 3" depth Hot asphalt concrete mixture. Construct transition zone (Pay Item 40401).

EOP

Place and compact 3" depth Hot asphalt concrete mixture 100' ahead and back. Match to existing subgrade including 1-2' curve widening. Construct transition zones at each end (Pay Item 40401).

GENERAL NOTES:

RP (reference point): Live stream with culvert.

1) Waste Area : 6' Maximum height of material, 1V:2H slopes, shape to drain.

2) Work includes all turnouts and curve widening.

3) All water rights and permits are the responsibility of the contractor.

Use ODOT HMAC 1/2" dense, Level II asphalt mix designation with PG 64-22 asphalt cement. Includes all excavation and transition zone construction.

Commercial source. Contractor sampling and testing included.

Shoulder rock. Commercial source. Contractor sampling and testing included.

Scarify potholes and irregularities to a 6" maximum depth.

REMARKS

* Denotes Contract Quantities

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Includes equipment cleaning, fire equipment and traffic control.