Solicitation_No._R17PS01132.pdf

PDF 17 MB Posted

Attached to
Roof Replacement, Nebraska-Kansas Area Office
Solicitation number
R17PS01132
Issued by

About this file

Solicitation No. R17PS01132

View the file

Other files

File Type Posted
Amend__1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 2017 U.S. Department of the Interior Bureau of Reclamation 2021 4th Ave North Billings, MT 59107

Solicitation No. R17PS01132

Nebraska – Kansas Area Office Roof Replacement Kansas River Project Pick-Sloan Missouri River Basin Program Nebraska

U.S. Department of the Interior Bureau of Reclamation 2021 4th Ave North Billings, MT 59107 JULY 2017

THIS PAGE INTENTIONALLY LEFT BLANK.

NEBRASKA – KANSAS AREA OFFICE

ROOF REPLACEMENT

Kansas River Area Pick-Sloan Missouri Basin Program

Nebraska

FOREWORD

Work to be performed under this solicitation is to be performed at the Bureau of Reclamation’s Nebraska – Kansas Area Office in Nebraska. The work is located at 1706 West 3rd, McCook, Red Willow County, Nebraska.

The principal components of work to be performed under these specifications include the following:

• Remove and dispose of existing asphalt roof system and roof drainage components.

• Provide and install new asphalt roof system and roof drainage components.

• Provide warranty of workmanship and materials for all components of the roofing system.

POINT OF CONTACT:

The point of contact is Contract Specialist Darlene Dillon. All questions and correspondence concerning this solicitation shall be directed to the Contract Specialist via email at ddillon@usbr.gov. Phone calls will not be accepted, to ensure all communication will be properly documented for record purposes.

PROPOSAL CLOSING DATE:

See Section “A”: “SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442” immediately following the “TABLE OF CONTENTS.” If the closing date is subject to change, notification will be provided by Amendment to the Solicitation.

METHOD OF SUBMISSION OF PROPOSALS:

See Section L of this Solicitation.

TYPE OF CONTRACT:

This requirement is solicited as an “Request for Quote” (RFQ) using Federal Acquisition Regulation Parts 12, 13 and 36. Results from this solicitation will be an anticipated award of a Firm Fixed Price Contract.

COMPETITION REQUIREMENTS:

This acquisition is restricted to Total Small Businesses.

RECLAMATION SAFETY AND HEALTH STANDARDS (2014 EDITION):

For information regarding the Bureau of Reclamation’s publication “RECLAMATION SAFETY AND HEALTH STANDARDS” (2014 Edition): http://www.usbr.gov/ssle/safety/RSHS/rshs.html) which is applicable to work under this contract. See Clause “WBR 1452.223-81 SAFETY AND HEALTH.

i mailto:MROUSE@USBR.GOV

PRE-BID ORGANIZED SITE VISIT:

A pre-bid organized site visit will be held August 10, 2017 at 10:00 AM, (McCook, NE Timezone), by meeting at Reclamation's Nebraska - Kansas Area Office located at 1706 West 3rd, McCook, Red Willow County, Nebraska. Prospective Offerors should make arrangements by contacting Mr. Mark Rouse at telephone Number (308)345-1031 or email address mrouse@usbr.gov. Attendees are to provide and wear safety boots, hard hats and safety vests.

SAM:

Effective July 29, 2012, any contractor interested in doing business with the Government must register in the system for award management (SAM) database prior to award of a contract or agreement. SAM is a Federal Government owned and operated FREE website that consolidates the Central Contractor Registration (CCR), the Online Representations and Certifications Application (ORCA), and the excluded parties list system (EPLS). The vendor’s DUNS and Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements via the SAM website at https://www.sam.gov/portal/public/sam or by the Federal Service Desk at telephone number 1-866-606-8220.

PAYMENTS:

Payment requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform (IPP) System. The IPP website is https://www.ipp.gov. The contractor must use the IPP website to register, access, and use IPP for submitting requests for payment.

Contractor assistance with enrollment can be obtained by contacting the IPP production helpdesk via email at ippgroup@bos.frb.org or at telephone number 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with their proposal.

ii https://www.sam.gov/PORTAL/PUBLIC/SAM/ http://www.ipp.gov/ mailto:IPPGROUP@BOS.FRB.ORG

Nebraska – Kansas Area Office

Roof Replacement

Table of Contents

00 01 10 - 1

TABLE OF CONTENTS

PART 1– THE SCHEDULE

SECTION A – SOLICITATION, OFFER and AWARD, STANDARD FORM 1442

SECTION B – SCHEDULE

SECTION C – DESCRIPTION / SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 14 10 Use of Site

01 33 00 Submittals

01 35 10 Safety Data Sheets

01 35 20 Safety and Health

01 35 30 Contractors Onsite Safety Personnel

01 42 10 Reference Standards

01 46 00 Quality Procedures

01 51 00 Temporary Utilities

01 55 00 Vehicular Access and Parking

01 56 10 Protection of Existing Installations

01 60 00 Product Requirements

01 74 00 Cleaning and Waste Management

01 78 30 Project Record Documents

DIVISION 02 – DIVISION 06

Not Used

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 31 10 Asphalt Shingle Roofing System

DIVISION 08 – DIVISION 50

Not Used

DIVISION 51

51 09 96 Photographic Log

DIVISION 52 – DRAWINGS

52 00 00 Drawings

Table of Contents

00 01 10 - 2

DIVISION 53

Not Used

SECTION D – NOT USED

SECTION E – INSPECTION OR PERFORMANCE

E.1 52.236-5 Material and Workmanship

E.2 52.246-12 Inspection of Construction

E.3 52.246-21 Warranty of Construction

SECTION F – DELIVERIES OR PERFORMANCE

F.1 52.211-10

F.2 52.242-14 Commencement, Prosecution, and Completion of Work

Suspension of Work

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 WBR 1452.201-70 Authorities and Delegations

G.2 DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice

Processing Platform (IPP)

SECTION H – SPECIAL PURCHASE ORDER REQUIREMENTS

H.1 GP-7 Site Security

SECTION I – PURCHASE ORDER CLAUSES

I.1 52.252-2

I.2 52.204-18

I.3 52.222-55

I.4 52.225-9

I.5 52.228-13

I.6 52.232-5

I.7 52.232-27

I.8 52.236-2

I.9 52.236-7

I.10 52.236-12

I.11 52.236-13

I.12 52.236-14

I.13 52.236-21 ALT II

I.14 52.236-26

I.15 52.243-5

I.16 52.252-6

I.17 WBR 1452.228-70

I.18 WBR 1452.223-80

I.19 WBR 1452.223-81

Clauses Incorporated by Reference

Commercial and Government Entity Code Maintenance

Minimum Wages Under Executive Order 13658

Buy American – Construction Materials

Alternative Payment Protections

Payments Under Fixed-Price Construction Contracts

Prompt Payment for Construction Contracts

Differing Site Conditions

Permits and Responsibilities

Cleaning Up

Accident Prevention

Availability and Use of Utility Services

Specifications and Drawings for Construction – ALT II

Preconstruction Conference

Changes and Changed Conditions

Authorized Deviations in Clauses

Liability Insurance – Department of the Interior

Asbestos-Free Warranty

Safety and Health – Bureau of Reclamation

Table of Contents

00 01 10 - 3

I.20 WBR 1452.223-82 Protecting Federal Employees and the Public from Exposure to Tobacco Smoke in the Federal Workplace – Bureau of Reclamation I.21 WBR 1452.231-81 Equipment Ownership and Operating Expense – Bureau of Reclamation I.22 WBR 1452.232-81 Payment for Mobilization and Preparatory Work I.23 WBR 1452.236-8 Other Contracts (Deviation) I.24 WBR 1452.236-84 Preservation of Cultural Resources –Bureau of Reclamation I.25 WBR 1452.237-80 Security Requirements – Bureau of Reclamation, Alt III I.26 WBR 1452.243-80 Modification Proposals – Bureau of Reclamation, Alt III

PART III

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

ATTACHMENT NUMBER 0001 Department of Labor General Decision Number: NE170079

PART IV

SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS

OR OFFERORS

K.1 52.204-8 Annual Representations and Certifications

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

L.1 52.204-7 System for Award Management L.2 52.201-16 Commercial and Government Entity Code Reporting L.3 52.211-1 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29

L.4 52.211-2 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) L.5 52.214-34 Submission of Offers in the English Language L.6 52.214-35 Submission of Offers in U.S. Currency L.7 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work L.8 52.222-23 Notice of Requirements for Affirmative Action to Ensure Equal Employment Opportunity for Construction L.9 52.225-10 Notice of Buy American Requirement – Construction Materials L.10 52.236-27 Alt I Site Visit (Construction)-Alternate I L.11 52.252-5 Authorized Deviations in Provisions L.12 WBR 1452.215-71 Use and Disclosure of Proposal Information-Department of the Interior

Table of Contents

00 01 10 - 4

L.13 WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule

Line Item

L.14 ET 02-20 Authorized Workers Notice to Potential Bureau of

Reclamation Contractors

SECTION M – EVALUATION FACTORS FOR AWARD

M.1 GP-4 Basis for Award

M.2 WBR 1452.225-82 Notice of World Trade Organization Government Procurement

Agreement Evaluations-Bureau of Reclamation

END OF CONTENTS

PART I - THE SCHEDULE

This page intentionally left blank.

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

CODE

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040326500

R60

7. ISSUED BY

Bureau of Reclamation

Great Plains Region

Regional Office

2021 4th Ave. North Billings MT 59107

8. ADDRESS OFFER TO

DOI- Bureau of Reclamation,Great Plains Region Regional Office GP-5000: Contract Specialist Darlene Dillon 2021 4th Ave. North Billings, MT 59107

Darlene Dillon 406-247-7820

107/27/2017

R17PS01132

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Nebraska - Kansas Area Office Roof Replacement, Kansas River Project Pick-Sloan Missouri River Basin Program, Nebraska

Type of Solicitation: Request for Quote

The estimated price range is between $100,000 and $250,000.

The North American Industry Classification System (NAICS) code is 238160 Roofing Contractors, which has an associated Small Business size of $15 million.

Taxpayer Identification Number (TIN):________________________________

Data Universal Number System (DUNS):_________________________________

Commercial and Government Entity Code:_______________________________

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See Paragraph F.1 )

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO (If "YES", indicate within how many calendar days after award in Item 12b.)

180 calendar days and complete it within 10 ________________ calendar days after receiving

08/30/2017

NSN 7540-01-155-3212

x x x x

___________________ (hour) local time

_______________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .

STANDARD FORM 1442 (Rev. 4-85) Prescribed by GSA FAR(48 CFR) 53.236-1(d) copies to perform the work required are due at the place specified in Item 8 by

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Gerri Voto-Braun

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

X

U.S. Department of Treasury The Invoice Processing Platform (IPP) https://www.ipp.gov

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

R17PS01132

00010

SECTION B Supplies or Services and Prices FOB: Destination

NKAO Roof Replacement

(Price Schedule CLINS 1 through 3)

See following continuation pages.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

1 AU $______________________

Schedule B - 1

CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES

NEBRASKA – KANSAS AREA OFFICE

ROOF REPLACEMENT

PICK-SLOAN MISSOURI BASIN PROGRAM

NEBRASKA

B.1 SCHEDULE

(a) Offers will be considered for award on the following schedules, but no offer will be considered for award on only a part of the schedules.

(b) All offers are subject to the terms and conditions of this solicitation.

(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(d) Definitions:

(1) CLIN – Contract Line Item Number

SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.23

2-81

Mobilization and preparatory work

For the lump sum of $

2 07 31 10 Removal of Existing Roof Material

For the lump sum of $

3 07 31 10 Furnish and Install Asphalt Shingle Roofing System.

For the lump sum of $

TOTAL FOR SCHEDULE $_________________

END OF SCHEDULE

SECTION C – SPECIFICATIONS

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at 1706 West 3rd, McCook, Red Willow County, Nebraska

1.02 PRINCIPAL COMPONENTS OF WORK

A. Remove and dispose of existing asphalt roof system and roof drainage components.

B. Provide and install new asphalt roof system and roof drainage components.

C. Provide warranty of workmanship and materials for all components of the roofing system.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.04 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

B. Quality Assurance: Inspection and tests performed by Government to ensure compliance with the terms of the contract.

C. Quality Control: Activities performed by Contractor to ensure work conforms to contract requirements.

D. Contractor Quality Testing: Specified tests to be performed by the Contractor.

1. The Government may use the test results for Quality Assurance.

2. The Contractor may use the test results as part of Contractor quality control.

a. The Government anticipates that these tests will be part of the Contractor’s quality control program; however, the tests do not relieve the

Summary of Work 01 11 00 - 2

Contractor of providing adequate quality control measures in accordance with the clause at FAR 52.246-12, Inspection of Construction.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer

2. COR: Contracting Officer’s Representative

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedules for other items of work.

1.02 PROJECT CONDITIONS

A. The Government will control access to the facilities. The Contractor shall coordinate with the Contracting Officer’s Representative (COR) and receive approval prior to accessing any Government facility.

B. The Contractor shall coordinate with the COR to receive approval for use of Government property for staging and storage of construction materials.

C. Project involves working at heights, Contractor shall provide and use appropriate personal protective equipment.

D. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

E. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.

F. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

G. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by the COR.

H. A key is required to enter the fenced area surrounding the office. Due to this restriction, working hours will be 6:00 a.m. to 7:00 p.m. on Monday through Friday. Changes to working hours will require approval of the COR.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Use of Site 01 14 10 - 2

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-2011 United States National CAD Standards, Version 5

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement units: US Customary Units.

C. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

01 33 00 - 2

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

D. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

E. Samples and Color Selection Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Manufacturers product bruchures. Xerographic copes will not be accepted.

4. The Government will select architectural color and pattern after product approval.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.

1. Electronic submittals:

a. In Portable Document Format (PDF).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

2. Submit electronic submittals via email or a thumb-drive based on size:

a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra large. E-mailing of electronic submittals exceeding 10 MB should only occur after transmittal of larger size e-mail has been verified.

b. Address e-mail of electronic submittals less than extra large size to:

1) mrouse@usbr.gov mailto:mrouse@usbr.gov

Submittals 01 33 00 - 3

c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on a thumb-drive.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. Each submittal shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

01 33 00 - 4

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal Response:

1. A response letter from the COR for each submittal will be sent to the Contractor indicating if the submittal is either approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.

1.07 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021, 4th Avenue North, Billings, MT 59101.

2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021, 4th Avenue North, Billings, MT 59101.

PART 2 PRODUCTS

Not Used

01 33 00 - 5

Table 01 33 00A. – List of Submittals **CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent: **

CO COR

1 Payment Protections 52.228-13

Payment Protections Within 10 calendar days after award

CO 1 paper 0

2 Insurance-work on a Government Installation 1452.228-70

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing onsite work

CO 1 paper

1 paper

3 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1 paper 0

4 Equal Opportunity 52.222-26

Information required by Executive Order 112246

(SF-100)

Within 30 days following award

CO 1 paper 0

5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10

Certification that executive compensation and subcontract awards were reported

Within 10days of each report being submitted

CO 1 paper 0

6 Site Security

GP-7

List of all contractor and subcontractor employees

At least 10 days prior to arriving at worksite

COR 0 2 paper

7 Site Security

GP-7

List of all vehicles and equipment to be brought onsite

At least 10 days prior to arriving at worksite

COR 0 2 paper

8 Release of Claims 1452.204-70

Release of Claims (DI-

137) against the Government

After completion of the work and prior to final payment

CO 1 paper 0

9 Labor Standards Data 52.222-11

1) List of subcontractors

2) Statement and acknowledgement Form (SF-1413) for each subcontract

Within 14 days after award of contract

COR 1 paper

1 paper

1 paper + 1 electronic

1 paper + 1

10 Payrolls 52.222-08

Copies of all payrolls Weekly for each week of contract performance

COR 1 paper 2 paper

11 Schedules for Construction Contracts 52.236-15

Practicable schedule Within 5 days of Notice to Proceed on the contract or another period of time as determined by Contracting Officer

COR 1 paper 1 paper + 1

01 33 00 - 6

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent: **

CO COR

12 Schedules for Construction Contracts 52.236-15

Updated schedule showing actual progress

Monthly or as directed by the Contracting Officer

COR 1 paper 1 paper + 1 electronic

01 35 10-1 Safety Data Sheets

Complete LHM and SDS At least 14 days before jobsite delivery of hazardous material

COR 0 1 paper + 1 electronic

01 35 10-2 Safety Data Sheets

Updated LHM and SDS At least 14 days before jobsite delivery of hazardous material not previously listed

COR 0 1 paper + 1 electronic

01 35 20-1 Safety and Health

Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS

COR 0 1 paper + 1 electronic

01 35 20-2 Safety and Health

Weekly Accident Summary Report

First day of each week.

See paragraph 3.8 of

RSHS

COR 0 1 paper + 1 electronic

01 35 20-3 Safety and Health

Crane Operation Certificates

At least 14 days before arriving at worksite

COR 0 2 paper

01 35 20-4 Safety and Health

Other Training Certificates

At least 14 days before arriving at worksite

COR 0 2 paper

01 35 30-1 Contractor’s Onsite Safety Personnel

Qualifications At least 20 days before beginning onsite work

COR 0 2 paper

01 35 30-2 Contractor’s Onsite Safety Personnel

Weekly Safety Inspection Report

At least once each week COR 0 1 paper + 1 electronic

01 56 10-1 Protection of Exisiting Installations

Plan for Protecting Existing Installations

At least 15 days prior to construction

COR 0 1 paper + 1 electronic

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Records

Within 7 days of waste disposal

COR 0 1 paper + 1 electronic

01 74 00-2 Cleaning and Waste Management

Hazardous Waste Manifest (If Necessary)

Within 7 days of hazardous waste disposal

COR 0 1 paper + 1 electronic

01 78 30-1 Project Record Documents

As-built Record of Materials

Within 15 days of completion of work

COR 0 1 paper + 1 electronic

07 31 10-1 Asphalt Shingle Roofing System

Approval Data At least 15 days prior to purchase

COR 0 1 paper + 1 electronic

07 31 10-2 Asphalt Shingle Roofing System

Manufacturer’s Instructions

At least 10 days prior to installation

COR 0 1 paper + 1 electronic

07 31 10-3 Asphalt Shingle Roofing System

Documentation At least 10 days prior to installation

COR 0 1 paper + 1 electronic

07 31 10-4 Asphalt Shingle Roofing System

Warranties Within 5 days following complete installation of system

COR 0 1 paper + 1

Safety Data Sheets

01 35 10 - 1

SECTION 01 35 10

SAFETY DATA SHEETS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 DEFINITIONS

A. LHM: List of Hazardous Materials

B. SDS: Safety Data Sheet.

1.03 APPLICATION

A. For the purposes of this contract, the definition of “materials delivered under this contract” in the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes materials delivered to the Government and all materials expected to be used during contract performance at the jobsite.

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 10-1, Complete LHM and SDS.

C. RSN 01 35 10-2, Updated LHM and SDS:

1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.

1.05 DELIVERY

A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.

PART 2 PRODUCTS

Not Used

Safety Data Sheets

01 35 10 - 2

Safety and Health

01 35 20 - 1

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include the cost of complying with this section in the prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards www.usbr.gov/ssle/safety/RSHS/rshs.html

2. FIST 1-1 (2012) Hazardous Energy Control Program www.usbr.gov/power/data/fist_pub.html

B. Occupational Safety and Health Administration (OSHA)

1. 29 CFR Part 1910 Occupational Safety and Health Standards

2. 29 CFR Part 1926 Safety and Health Regulations for Construction

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Safety Program:

1. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 – Submittals and in accordance with the requirements of Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.

2. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.

3. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.

4. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.

http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.usbr.gov/power/data/fist_pub.html

01 35 20 - 2

5. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation Safety and Health Standards and these specifications.”

6. The Safety Program shall include but not be limited to the following program elements:

a. Emergency Action Plan

1) Detail coordination plan for outside emergency services including response time and a site visit where a rescue requires special capabilities or equipment.

2) This plan shall address detailed emergency contacts and procedures to be used during an onsite emergency.

b. Hazardous Energy Control (lockout/tagout)

1) Include the contractor’s written Hazardous Energy Control Program (HECP)

2) Comply with facility HECP procedures and coordinate activities with Reclamation staff.

c. Electrical Safety

1) Include safe work procedures at the site, electrically qualified persons, grounding techniques, use of mobile generators, construction lighting, power tool safety, and use of personal protective equipment.

d. Job Hazard Analysis

1) Provide a list of proposed JHA’s in the Safety Program for each anticipated work task.

2) A detailed JHA shall be completed onsite prior to starting each work task. Work will not begin on the phase of the work until a JHA is acceptable to the Onsite Government Representative.

3) Activities involving hazardous materials shall have the appropriate Material Safety Data Sheet(s) attached to the JHA.

e. Hearing Conservation

1) Include a task- and site-specific hearing conservation plan.

2) Identify the type of hearing protection and verify that workers are in a Hearing Conservation Program.

f. Personal Protective Equipment (PPE)

1) Include a detailed plan for each task that specifies which personal protective equipment shall be used for all construction activities.

Safety and Health 01 35 20 - 3

2) The employer must ensure that the PPE is verified by the manufacturer for the intended use and protection.

3) Provide appropriate PPE at no cost to the employees

g. Hazard Communication

1) Include a written Hazard Communication plan. .

2) The safety and health practices, procedures, and protective equipment used for new and existing products shall be based upon the health hazards identified in the MSDS.

h. Fall Protection and Prevention

1) Detail safe work procedures, training and engineering controls for work in elevated areas where employees are exposed to a fall.

2) The Contractor shall use engineered fall protection systems, fall restraint, and/or fall arrest systems for work in elevated areas. Warning line and safety monitoring systems are not permitted.

i. Scaffolding Safety and Design

1) Include a scaffolding plan indicating what type of scaffolding will be used at the site and provide drawings, design specifications, manufacturer information, fall protection procedures and falling object protection.

j. Crane, Hoisting and Rigging Safety:

1) Include operator and rigging safety, materials handling, signaling and communication procedures.

2) All Operators, Riggers and Signalpersons shall be qualified in accordance with OSHA 1926 Subpart CC. Crane Operators shall be certified by an accredited crane operator testing organizations such as NCCCO or equivalent.

3) Reclamation requires an onsite verified load test in accordance with RSHS Appendix F prior to use of cranes.

k. Protection of the Public.

1) Signs and Barricades:

1) Specific to project needs.

C. RSN 01 35 20-2, Weekly Accident Summary Report:

1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.

2. Submit on the first day of every week.

D. RSN 01 35 20-3, Crane Operation Certificates

01 35 20 - 4

1. Qualifications for all riggers and signalpersons.

2. Crane Operator Qualifications:

a. Certifications for all crane and hoist operators.

b. Medical Qualifications to operate a crane in accordance with RSHS Section 19.5.

c. Annual crane inspection certifications. Inspected by a third party qualified crane inspector.

E. RSN 01 35 20-4, Other Training Certificates

1. First Aid/CPR certifications for onsite foremen and/or safety personnel.

2. Proof of fall protection and prevention training for employees who work in elevated areas.

3. Proof of Lockout/tagout training for all employees who will work in any area protected by lockout/tagout and hazardous energy control procedures.

4. Training certifications and experience for scaffolding competent person if applicable.

1.04 SAFETY AND HEALTH

A. Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.

B. Provide and maintain a work environment and procedures that will:

1. Safeguard the public, Government personnel, and Contractor employees from Contractor operations and activities that are unsanitary, hazardous, or dangerous to health and safety

2. Avoid interruptions of site operations and delays in project completion dates.

3. Control costs in contract performance.

C. Provide appropriate safety barricades, signs, and warnings. Erect or label all limited approach and arc flash hazard boundaries for exposed energized equipment. Coordinate these activities with Reclamation electricians.

D. Comply specifically with all requirements contained in RSHS Section 3- Contractor Requirements.

E. Investigate and report all accidents, incidents and near misses in accordance with RSHS Section 3.7.

F. When the Contractor fails or refuses to promptly correct a compliance directive, the Contracting Officer may issue an order to stop all or any part of the work.

01 35 20 - 5

1. When satisfactory corrective action is taken, an order to resume work will be issued.

2. The Contractor shall not be entitled to extension of time or to claim for damage or to additional compensation by reason of ether the directive or the stop order.

3. Failure of the Contracting Officer to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.

G. Maintain accurate record of and report to the CO the following occurrences during performance of this contract:

1. Death.

2. Occupational disease.

3. Traumatic injury to employees or the public.

4. Property damage in excess of $2,500.

H. Disputes regarding safety and health issues will be settled in accordance with RSHS Section 3.

I. The Contractor shall be responsible for providing medical and emergency assistance in a timely manner that is consistent with recognized emergency protocols.

1. In instances where local emergency responders are not readily available, the responsibility to provide emergency services shall default back to the Contractor.

J. The Contractor shall be responsible for insuring that Subcontractors comply with the requirements set forth in this specification, written programs, the regulatory standards and the industry standards incorporated by reference in the RSHS and OSHA standards.

K. Where there is conflict between the standards, the more stringent or restrictive shall be utilized.

L. The Contractor shall fully participate in the Contractor Safety Program Review meeting, according to RSHS Section 3.4.1. The Contractor Safety Program Review meeting will take place before the start of construction.

1. Include subcontractor management representatives.

2. The Safety Personnel shall be present, in order to discuss in detail the Safety Program and Plans.

M. The minimum work crew at any time on the construction site shall consist of no less than two (2) people.

PART 2 PRODUCTS

01 35 20 - 6

PART 3 EXECUTION

Contractor’s Onsite Safety Personnel

01 35 30 - 1

SECTION 01 35 30

CONTRACTORS ONSITE SAFETY PERSONNEL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for the other items of work.

1.02 REFERENCES

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards www.usbr.gov/ssle/safety/RSHS/rshs.html

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 – Submittals

B. RSN 01 35 30-1, Qualifications:

1. Contractor’s Onsite Safety Representative

C. RSN 01 35 30-2, Weekly Safety Inspection Report

1.04 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative:

1. Competent supervisory employee with safety and health related training, experience and duties on similar construction products.

2. The Onsite Safety Representative shall have completed an OSHA authorized 30 hour course for construction safety within the last 5 years.

3. Include resume, description of safety representative responsibilities on similar construction projects, and copies of training certifications of the individual proposed as the onsite safety representative.

4. The safety representative shall be acceptable to the COR and can have other duties.

1.05 APPLICATION

A. Contractor’s Onsite Safety Representative authorities, duties, and responsibilities:

01 35 30 - 2

1. Responsible for effectively implementing the Contractor’s Safety Program.

2. The Safety Representative shall coordinate all emergency response activities.

3. Recommend controls for observed hazards or predicted hazards

4. Full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Lead weekly safety meetings at the jobsite.

6. Onsite, at the point of work, during any and all construction activities.

7. Assemble, review, and sign each Job Hazard Analysis (JHA).

8. Verify the correct use of respiratory protection and personal protective equipment.

9. Conduct and prepare weekly safety inspections in conjunction with the onsite government representative listing noted deficiencies, their abatement dates, follow up action. The report shall be available for review onsite.

10. Prepare weekly accident summary report.

11. Provide direct oversight and assemble a detailed report of all incident reviews, near-misses, accidents, and emergency response or rescue actions.

1.06 QUALITY ASSURANCE

A. Contractor’s Onsite Safety and Health Representative:

1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the CO.

2. Should the Contractor’s onsite safety representative’s effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time safety professional at no additional cost to the Government.

PART 2 PRODUCTS

Not Used

01 35 30 - 3

Contractor’s Onsite Safety Personnel 01 35 30 - 4

Reference Standards 01 42 10 - 1

SECTION 01 42 10

REFERENCE STANDARDS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.

B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.

1.03 JOBSITE REFERENCE STANDARDS

A. Maintain at fabrication site, access to referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the Government.

B. Maintain onsite, access to referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.]

1.04 AVAILABILITY

A. Code of Federal Regulations (CFR):

1. Available online, authorized by the National Archives and Records Administration (NARA) and the Government Printing Office (GPO), at http://www.gpo.gov/fdsys/search/home.action

B. Federal Specifications, Standards, and Commercial Item Descriptions; and Military Specifications:

1. Copies of Federal Specifications, Standards, and Commercial Item Descriptions may be obtained from GSA Federal Supply Service, see the provision at FAR 52.211-1, Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.

2. Copies of Military Specifications may be obtained from Department of Defense, see the provision at FAR 52.211-2, Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST).

http://www.gpo.gov/fdsys/search/home.action

Reference Standards

01 42 10 - 2

C. Bureau of Reclamation Documents:

1. Reclamation Safety and Health Standards (RSHS) may be downloaded at www.usbr.gov/ssle/safety/RSHS/rshs.html.

a. Hard copies of RSHS, stock number 024-003-00204-6, may be purchased from The Superintendent of Documents at the U.S. Government Printing Office (GPO), phone number 202-512-1800. Hard copies of RSHS are subject to revisions posted on the site shown above.

1) GPO online bookstore:

http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber= 024-003-00204-6.

2. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:

United States Department of Commerce National Technical Information Service 5285 Port Royal Road Springfield, VA 22161 Telephone: 703-487-4650 or 1-800-553-6847

D. Industrial and Governmental Documents:

1. When a reference has a joint designation (e.g. ANSI/IEEE) these specifications generally cite the proponent organization (e.g. IEEE).

2. Addresses for obtaining industrial and governmental (other than Federal and Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in Table 01 42 10A - Addresses for Specifications, Standards, and Codes.

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

AGC Associated General Contractors of America 333 John Carlyle Street, Suite 200 Alexandria, VA 22314 www.agc.org

703-548-3118

AISC American Institute of Steel Construction One East Wacker Drive, Suite 3100 Chicago, IL 60601-2001 www.aisc.org

312-670-2400 http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6 http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6 http://www.agc.org/ http://www.aisc.org/

01 42 10 - 3

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

ANSI American National Standards Institute 1819 L. Street, NW.

Washington, DC 20036 www.ansi.org

202-293-8020

APA/EWA APA-The Engineered Wood Association P.O. Box 11700 Tacoma, WA 98411-0700 www.apawood.org

253-565-6600

ASME American Society of Mechanical Engineers 3 Park Avenue New York, NY 10016-5990 www.asme.org

800-843-2763

ASTM ASTM International P.O. Box C700 100 Barr Harbor Drive West Conshohocken, PA 19428-2959 www.astm.org

610-832-9585

AWS American Welding Society 550 NW LeJeune Road Miami, FL 33126 www.amweld.org

800-443-9353 305-443-9353

NACE NACE International 1440 South Creek Drive Houston, TX 77084 www.nace.org

281-228-6200

NEMA National Electrical Manufacturers Association 1300 N 17th Street, Suite 1847 Rosslyn, VA 22209 www.nema.org

703-841-3200

NFPA National Fire Protection Association One Batterymarch Park P.O. Box 9101 Quincy, MA 02269-9101 www.nfpa.org

800-344-3555 617-770-3000 http://www.ansi.org/ http://www.apawood.org/ http://www.asme.org/ http://www.astm.org/ http://www.amweld.org/ http://www.nace.org/ http://www.nema.org/ http://www.nfpa.org/

01 42 10 - 4

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

NRCA National Roofing Contractors Association 10255 W. Higgins Road Suite 600 Rosemont, IL 60018-5607 www.nrca.net

(847) 299-9070

(847) 299-1183

OSHA U.S. Department of Labor Occupational Safety & Health Administration 200 Constitution Avenue, NW Washington, DC 20210 www.osha.gov

(800) 321-6742

SSPC SSPC: The Society for Protective Coatings 40 24th Street, 6th Floor Pittsburgh, PA 15222-4656 www.sspc.org

800-837-8303 412-281-2331

UL Underwriters Laboratories, Inc.

333 Pfingsten Road Northbrook, IL 60062-2096 www.ul.com

847-272-8800

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

http://www.nrca.net/ http://www.osha.gov/ http://www.sspc.org/ http://www.ul.com/

Quality Procedures 01 46 00 - 1

SECTION 01 46 00

QUALITY PROCEDURES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. Government Contract Quality Assurance: (from FAR 46.101) Various functions, including inspection, performed by the Government to determine whether a contractor has fulfilled the contract obligations pertaining to quality and quantity.

B. Contractor Quality Assurance / Quality Control (QA/QC): Activities performed by the Contractor to ensure work conforms to contract requirements.

1. The…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .