R17PS00201_Marble_Bluff_Dam_and_Fish_Passage_Facility_-_Radial_Gate_Rehabilitation.pdf
PDF 3 MB Posted
- Solicitation number
- R17PS00201
About this file
Solicitation No. R17PS000201
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior Bureau of Reclamation Mid-Pacific Region
Invitation for Bid Solicitation No. R17PS00201
Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation
Washoe Project Nevada-California
This page intentionally left blank
Marble Bluff Dam and Fish Passage Facility – Radial Gate Rehabilitation
TOC - 1
TABLE OF CONTENTS
SECTION A - Solicitation, Offer and Award Form (SF 1442)
SECTION B - Pricing Schedule
SECTION C - Specifications/Appendices
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
SECTION F - Deliveries or Performance
SECTION G - Contract Administration Data
SECTION H - Special Contract Requirements
SECTION I - Contract Clauses
SECTION J - List of Documents, Exhibits, and Other Attachments
SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION L - Instructions, Conditions and Notices to Offerors
SECTION M - Evaluation Factors for Award
TOC - 2
TOC - 3
!!!!!!ATTENTION TO BIDDERS!!!!!!
In preparing your bid -----
1. Have you signed the bid? Are all blocks under Offer section of the SF1442 properly filled?
2. Have you included price information in Schedule B to include both page 3 (Columns E and F of Line item 0010) of SF1442 and Schedule B continuation pages? Have you checked your bid for possible mathematical errors?
3. Have you acknowledged receipt of all amendments by one of the methods identified in Block 11 of SF30?
4. Are you submitting your bid on time? If mailed, will it reach the place of bid opening prior to the designated date and hour?
5. Have you submitted the required bid guarantee in accordance with FAR 52.228-1?
6. In addition to above, have you furnished all documents/information requested by the invitation for bids?
a. Section K - Representations, Certifications And Other Statements Of Offerors
b. Section J Attachment 2 - Offeror Responsibility Information
c. Section J Attachment 3 - Subcontracting Percentages Worksheet
7. Have you identified on the face of the envelope containing your bid, the invitation number to which it pertains, and the date and hour of opening?
***ABOVE INFORMATION SHOULD NOT BE CONSIDERED A COMPLETE CHECKLIST
FOR REQUIRED BID PACKAGE CONTENTS. BIDDERS SHOULD REVIEW THE IFB IN
ITS ENTIRETY AND ENSURE THAT THEIR BID PACKAGE MEETS ALL OF THE
REQUIREMENTS MENTIONED IN THIS SOLICITATION. PLEASE DO NOT SUBMIT
ANSWERS TO ABOVE QUESTIONS***
TOC - 4
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Bureau of Reclamation - MP Regional Office
Attn: Erim Celik, Contracting Officer 2800 Cottage Way, Rm. E-1815, Federal Bldg.
Sacramento, California 95825-1898
Erim Celik 916-978-5549
20-C0860 x
04/05/2017
1. SOLICITATION NO.
R17PS00201
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A. Title: Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation
B. Work Site Location: Work is located approximately 46 miles northeast of Reno, Nevada, in Washoe County.
C. Site Visit Information: See Section L, FAR 52.236-27, Site Visit (Construction)
-Alt. 1
D. Estimated Price Range: The estimated cost of this project is between
$500,000.00 and $1,000,000.00
E. Set-Aside Information: This requirement is restricted to Total Small Business concerns using NAICS 237990 and applicable size standard of $36.5 million. FAR Clause 52.219-06, "Notice of Total Small Business Set Aside" applies to this requirement.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 calendar days and complete it within ________________
Section F
5/5/2017
NSN 7540-01-155-3212
x x x x
____0_________ copies to perform the work required are due at the place specified in Item 8 by ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
20626
R17PS00201 Marble Bluff Dam and Fish Passage Facility - Radial Gate Rehabilitation
220 calender days after receiving
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Erim Celik
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
PAGE OF
00010 1 AU
SECTION B Supplies or Services and Prices
FOB: Destination
Marble Bluff Dam and Fish Passage Facility - Radial Gate Rehabilitation (Price Schedule CLINS 1 through 26) See following continuation pages.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Price Schedule B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number.
(2) AU- Activity Unit: AU – Activity Unit is used solely for the purposes of allowing progress payments under the Department of Interior’s Financial & Business Management System (FBMS). This line represents the total value for the pricing proposal.
Price Schedule
B - 2
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232-
Mobilization and Preparatory Work
For the lump sum of $
2 Section H Tribal Employment Rights Ordinance (TERO)
For the lump sum of $
3 01 31 30 Contract Document Management System
For the lump sum of $
4 05 50 00 Miscellaneous Metalwork For the lump sum of $
5 09 96 20 Spot Repair and Full Overcoat Radial Gate Hoist Machinery
For the lump sum of $
6 09 96 20 Spot Repair and Full Overcoat Pipe Guardrail
1350 Lin ft $ $
7 09 96 20 Blast and Coat New Pipe Guardrail and Pipe Guardrail Gate
100 Lin ft $ $
8 09 96 20 Blast and Recoat Interior of Hydraulic Control Cabinet #9
For the lump sum of $
9 09 96 20 Blast and Recoat Conduit Associated with Electrical Work
For the lump sum of $
10 09 97 02 Blast and Recoat Radial Gate
For the lump sum of $
11 09 97 02 Blast and Recoat Fish Lock Drain Gate 10
For the lump sum of $
12 09 97 02 Blast and Recoat Fish Lock Drain Pipe Exterior
For the lump sum of $
13 09 97 02 Blast and Recoat Fish Lock False Floor and Frame
For the lump sum of $
Price Schedule
B - 3
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
14 26 04 10 Electrical Equipment Modification, Removal, and Disposal
For the lump sum of $
15 26 05 10 Conductors and Cables For the lump sum of $
16 26 05 33 Raceways and Boxes For the lump sum of $
17 26 05 90 Wiring Checkouts and Operational Tests
For the lump sum of $
18 26 12 16 Dry Type Transformer For the lump sum of $
19 26 24 24 Distribution Panelboards For the lump sum of $
20 26 29 15 Combination Motor Starter for Turbine Pump
For the lump sum of $
21 26 29 15 Combination Motor Starter for Auxiliary Turbine Pump
For the lump sum of $
22 26 29 15 Combination Motor Starter for Dope Tank Hoist
For the lump sum of $
23 26 42 10 Radial Gate Galvanic Anode Cathodic Protection System
For the lump sum of $
24 26 42 11 Fish Lock Drain Pipe Galvanic Anode Cathodic Protection System
For the lump sum of $
25 35 23 50 Radial Gate Fabrication and Modification
For the lump sum of $
26 41 22 32 Refurbishment of Radial Gate Hoist
For the lump sum of $
TOTAL FOR PRICE SCHEDULE $_________________
END OF SECTION
C-1
SECTION C - Specifications
Section C consists of the specifications. Specification 20-C0860 has been attached to this solicitation.
C-2
End of Section
D-1
SECTION D - PACKAGING AND MARKING
There are no clauses in this section.
D-2
E-1
SECTION E - INSPECTION AND ACCEPTANCE
E.1 52.236-5 MATERIAL AND WORKMANSHIP APR 1984
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
(b) The Contractor shall obtain the Contracting Officer’s approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting Officer’s approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor’s expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.
(c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
E.2 52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
E-2
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.
The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction.
However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
F-1
SECTION F - DELIVERIES OR PERFORMANCE
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND APR 1984
COMPLETION OF WORK
The Contractor shall be required to
(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 220 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
F.2 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION SEP 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,200 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F.3 52.242-14 SUSPENSION OF WORK APR 1984
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
F-2
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
G-1
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 This contract shall be administered by the Mid-Pacific Regional Office, 2800 Cottage Way, Sacramento, California 95825-1898.
G.2 WBR 1452.242-80 POSTAWARD CONFERENCE—BUREAU JUL 1993
OF RECLAMATION
(a) Prior to the Contractor starting work, a post-award conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.
(b) The conference will be held at the Mid-Pacific Regional Office, 2800 Cottage Way, Sacramento, California 95825-1898.
(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.
(d) The Contractor shall include any associated costs for attendance at the conference, in its offer.
G.3 DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS SEP 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, G-2 risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the
COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.4 DOI AAAP-050 NOTICE TO CONTRACTORS DEC 2015
CONTRACTOR PERFORMANCE
ASSESSMENT REPORTING SYSTEM
1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report.
Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.csd.disa.mil/
G-3
e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
G.5 DOI-AAAP 0028 ELECTRONIC INVOICING AND PAYMENT
REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP) APR 2013
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform System (IPP). The IPP website address is:
https://www.ipp.gov.
“Payment requests” means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request shall comply with the applicable Prompt Payment clause included in the contract, the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts, or the requirements identified in FAR 52.232-27, Prompt Payment for Construction Contracts, and include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of the this clause.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone
(866) 973-3131.
No attachments are required to be uploaded to IPP.gov.
https://www.ipp.gov/
G-4
Prior to submitting an invoice to IPP.gov, the contractor is strongly encouraged to coordinate with the designated Contracting Officer’s Representative (COR), for review and verification of any measured quantities for payment and for compliance with the applicable progress payment requirements of this contract. Failure to do so, may cause a delay in approval and/or rejection of submitted invoices.
Pursuant to the payment terms contained in this contract, the contractor shall prepare and submit requests for payments (invoices) by following the instructions as described below:
1. To ensure timely processing of invoices under the contract/agreement, the contractor must submit all invoices to the following e-mail address:
constructionbranchinvoices@usbr.gov
2. A proper invoice shall be submitted by email concurrent with submission to IPP and shall include the information as required by the payment terms and conditions contained in this contract.
3. The subject line of the email shall be formatted to read as follows:
Contract Number_Invoice Number_Contracting Officer’s last name Example: R17PC00001_Invoice No. 1_Smith
4. The Invoice shall be attached to the email and named using the following format:
Contract Number_Contractor Name-Invoice Number-Invoice Amount
(example: R17PC00001_World Test, Inc.-Inv No. 1-$5,678.00
5. Invoices shall not include information that would compromise Personally Identifiable Information, such as full social security numbers, dates of birth, etc.
6. The final invoice shall be submitted and will be approved in accordance with the payment terms and conditions contained in the contract, after all, if any, settlement actions are complete. The contractor must clearly identify the last payment as the “Final Invoice”.
Emailed Support documents must include, but are not limited to, the following documents:
a. Construction Invoice (Attachment J-4)
b. Monthly Certificate of Labor Conformance (Attachment J-4)
c. Subcontractor / Supplier Payment Summary (Attachment J-4)
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
mailto:constructionbranchinvoices@usbr.gov
H-1
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1 Intermediate Milestones and Limitations
The information provided below refers to the time period specified in FAR Clause 52.211-10 located in Section F of this solicitation.
Special Instructions to Contractor – Special Limitations to the Work Period The information provided below refers to the time period specified in FAR Clause 52.211-10 located in Section F of this solicitation and provides additional limits to the time allowed for the Offeror to perform this work.
1) The information provided below refers to the time period specified in FAR Clause 52.211-10, located in Section F of this solicitation.
a. Work on in water structures may only be performed between July 1 and December 31.
b. The Contractor shall complete all work on in water structures by December 31.
H.2 Tribal Tax This project is subject all Tribal Ordinances as adopted by Title 8 for the Pyramid Lake Paiute Tribal Council of the Pyramid Lake Indian Reservation. Please see the TERO/Indian Preference Law and compliance plan information provided in Section J of this solicitation.
H.3 ET 02-20 AUTHORIZED WORKERS NOTICE TO SEP 2002
POTENTIAL BUREAU OF RECLAMATION CONTRACTORS
(a) Definitions.
IRCA - Immigration Reform and Control Act of 1986 INA - Immigration and Nationality Act INS - Immigration and Naturalization Service SSA - Social Security Administration INS SAVE Program - The INS Systematic Alien Verification for Entitlements Program ESA - Employment Standards Administration (Department of Labor)
(a) Authority. Immigration Reform and Control Act of 1986 (8 USC 1101 as amended) and the Immigration and Nationality Act, Section 274A.
(b) Who is Covered. INA includes provisions addressing employment eligibility, employment verification, and nondiscrimination. These provisions apply to all employers, including government contractors.
(c) Basic Provisions/Requirements. Under IRCA, employers may hire only persons who may legally work in the U.S., i.e., citizens and nationals of the U.S. and aliens authorized to work in the U.S. The employer must verify the identity and employment eligibility of anyone to be hired, which includes completing the Employment Eligibility Verification Form (I-9). Employers must keep each I-9 on file for at least three years, or one year after employment ends, whichever is longer. Detailed guidance on the I-9 is available at the INS web site:
http://uscis.gov/graphics/services/employerinfo/index.htm http://uscis.gov/graphics/services/employerinfo/index.htm
H-2
(d) Employment Verification Pilot Programs. The INS and the SSA are conducting the following programs that provide employers a way to confirm the employment eligibility of their newly hired employees. Any employer located in a pilot state may volunteer to participate in a pilot program. If employers are not located in a pilot state, they would verify employment eligibility by following the procedures currently in place, i.e., by completing Form I-9.
(1) The Basic Pilot is a joint pilot being conducted by the INS and SSA in the States of California, Florida, Illinois, Nebraska, New York, and Texas. This pilot involves verification checks of the SSA and INS databases of all newly hired employees, regardless of citizenship. To receive information on the Basic Pilot program please call the INS SAVE Program toll free at 1- 888-464-4218, or fax your request for information to (202) 514-9981, or write to USINS, SAVE Program, 425 I Street, NW, ULLICO Building 4th Floor, Washington, DC 20536. You may also contact the Social Security Administration by calling (410) 966-1940, or writing to Social Security Administration, Office of Program Benefits Policy, 6401 Security Blvd., 760 Altmeyer, Baltimore, MD 21235.
(2) The INS is conducting the Citizen Attestation Pilot in the States of Arizona, Maryland, Massachusetts, Michigan, and Virginia. The Citizen Attestation Pilot permits participating employers to electronically verify the employment eligibility of newly hired alien employees by using a personal computer with a modem. To receive information on the Citizen Attestation Pilot program please call the INS SAVE Program toll free at 1-888-464-4218, or fax your request for information to (202) 514-9981. Employers may also write to US/INS, SAVE Program, 425 I Street, NW, ULLICO-4th Floor, Washington, DC 20536.
(3) The INS and the SSA are conducting the Machine-Readable Document Pilot in the State of Iowa. The Machine-Readable Document Pilot is identical to the Basic Pilot in all respects, except for the geographic scope of the pilot and for one additional feature. If an employee presents an Iowa's driver's license or identification card containing a machine-readable SSN, the employer will make an inquiry through the confirmation system by using the machine-readable feature. To receive information on the Machine-Readable Document Pilot program please call the INS SAVE Program toll free at 1-888-464-4218, or fax your request for information to (202) 514- 9981. You may also write to US/INS, SAVE Program, 425 I Street, NW, ULLICO-4th Floor, Washington, DC 20536. (e) Employee Rights. The INA protects U.S. citizens and aliens authorized to accept employment in the U.S. from discrimination in hiring or discharge on the basis of national origin and citizenship status. (f) Compliance Assistance. More detailed information, including copies of explanatory brochures and regulatory and interpretative materials, may be obtained from local offices of the Department of Labor's Employment Standards Division, Wage and Hour Division, and the Office of Federal Contract Compliance Programs. (g) Penalties/Sanctions. Employers who fail to complete and/or retain the I-9 forms are subject to penalties. The INS enforces the INA requirements on verification of employment eligibility. The Justice Department enforces the anti-discrimination provisions. As part of their ongoing enforcement efforts, the ESA's Wage and Hour Division and Office of Federal Contract Compliance Programs conduct inspections of the I-9 forms. They report their findings to the INS and to the Department of Justice when they find cases of disparate treatment or unauthorized employment. A debarring official may debar a contractor, based on a determination by the Attorney General of the United States, or designee, that the contractor is not in compliance with the INA. The Attorney General's determination is not reviewable in the debarment proceedings.
I-1
SECTION I - CONTRACT CLAUSES
I. 1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/vfdiara.htm (DIAR 1452.XXX-XX formatted clauses) https://www.acquisition.gov/far (FAR 52.XXX-XX formatted clauses)
Clause
Title
Date
52.202-1
Definitions
NOV 2013
52.203-3
Gratuities
APR 1984
52.203-5
Covenant Against Contingent Fees
MAY 2014
52.203-6 Restrictions on Subcontractor Sales to the Government SEP 2006 52.203-7
Anti-Kickback Procedures
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
52.203-10
Price or Fee Adjustment for Illegal or Improper Activity
52.203-12
Limitation on Payments to Influence Certain Federal Transactions
OCT 2010
52.203-13
Contractor Code of Business Ethics and Conduct
OCT 2015
52.203-17
Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights
APR 2014
52.204-4
Printing/Copying Double-Sided on Recycled Paper
MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
OCT 2016
52.204-13
System for Award Management
52.204-14
Service Contract Reporting Requirements
52.209-6
Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
I-2
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
JUL 2013
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations
NOV 2015
52.211-18 Variation in Estimated Quantity APR 1984 52.214-26 Audit and Records – Sealed Bidding OCT 2010 52.214-27
Price Reduction for Defective Cost or Pricing Data – Modifications – Sealed Bidding
AUG 2011
52.214-28 Subcontractor Cost or Pricing Data – Modifications – Sealed Bidding
OCT 2010
52.214-29 Order of Precedence – Uniformed Contract Format - Sealed Biding
JAN 1986
52.215-19 Notification of Ownership Change OCT 1997
52.219-6
Notice of Total Small Business Set-Aside
NOV 2011
52.219-8
Utilization of Small Business Concerns
NOV 2016
52.219-14 Limitations on Subcontracting JAN 2017
52.219-28
Post-Award Small Business Program Representation
JUL 2013
52.222-3
Convict Labor
JUN 2003
52.222-4 Contract Work Hours and Safety Standards Act- Overtime Compensation
52.222-6
Construction Wage Rate Requirements
52.222-7
Withholding of Funds
52.222-8
Payrolls and Basic Records
52.222-9
Apprentices and Trainees
JUL 2005
52.222-10
Compliance with Copeland Act Requirements
FEB 1988
52.222-11
Subcontracts (Labor Standards)
52.222-12
Contract Termination – Debarment
52.222-13
Compliance with Construction Wage Rate Requirements and Related Regulations
52.222-14
Disputes Concerning Labor Standards
FEB 1988
52.222-15
Certification of Eligibility
52.222-21
Prohibition of Segregated Facilities
APR 2015
52.222-26
Equal Opportunity
SEP 2016
52.222-27
Affirmative Action Compliance Requirements for Construction
APR 2015
52.222-35
Equal Opportunity for Veterans OCT 2015
I-3
52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014
52.222-37
Employment Reports on Veterans
FEB 2016
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50
Combating Trafficking in Persons
MAR 2015
52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-60 Paycheck Transparency (Executive Order 13673) OCT 2016 52.223-3 Alt I
Hazardous Material Identification and Material Safety Data - Alternate I (July 1995)
JAN 1997
52.223-5
Pollution Prevention and Right-to-Know Information
MAY 2011
52.223-6
Drug Free Workplace
MAY 2001
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
AUG 2011
52.225-13
Restrictions on Certain Foreign Purchases
JUN 2008
52.227-1
Authorization and Consent
DEC 2007
52.227-2
Notice And Assistance Regarding Patent And Copy Infringement
DEC 2007
52.227-4 Patent Indemnity – Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work on a Government Installation JAN 1997 52.228-11 Pledges of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds - Construction OCT 2010
52.229-3
Federal, State And Local Taxes
FEB 2013
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-17
Interest
52.232-23
Assignment Of Claims
52.232-27
Prompt Payment for Construction Contracts
52.232-33
Payment by Electronic Funds Transfer – System for Award Management
JUL 2013
52.232-39
Unenforceability of Unauthorized Obligations
JUN 2013
52.232-40 Providing Accelerated Payment to Small Business Subcontractors
DEC 2013
I-4
52.233-1 Alt I
Disputes - Alternate I (DEC 1991)
52.233-3
Protest After Award
AUG 1996
52.233-4
Applicable Law For Breach Of Contract Claim
OCT 2004
52.236-2
Differing Site Conditions
52.236-3
Site Investigation and Conditions Affecting the Work
52.236-6
Superintendence by the Contractor
52.236-7
Permits and Responsibilities
NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9
Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
52.236-10
Operations and Storage Areas
52.236-11
Use and Possession Prior to Completion
52.236-12
Cleaning Up
52.236-13 Alt I
Accident Prevention (NOV 1991) – Alternate I
NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Construction Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984
52.236-21 Alt I Specifications and Drawings for Construction (FEB 1997) – Alternate I FEB 1997
52.236-26 Preconstruction Conference FEB 1995 52.242-13
Bankruptcy
JUL 1995
52.243-4
Changes
JUN 2007
52.243-6 Change Order Accounting APR 1984 52.244-6
Subcontracts for Commercial Items
JAN 2017
52.245-1 Government Property – Alternate I APR 2012 52.245-9 Use and Charges APR 2012 52.248-3
Value Engineering – Construction
52.249-2 Alt I
Termination for Convenience of the Government (Fixed-Price) (SEP 1996) – Alternate I
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991
I. 2 DIAR 1452.203-70 RESTRICTIONS ON ENDORSEMENTS- JUL 1996
DEPARTMENT OF THE INTERIOR
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the
I-5 product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
I. 3 DIAR 1452.204-70 RELEASE OF CLAIMS - DEPARTMENT OF JUL 1996
THE INTERIOR
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
I. 4 DIAR 1452.228-70 LIABILITY INSURANCE - DEPARTMENT JUL 1996
OF THE INTERIOR
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
GENERAL LIABILITY
$500,000 per occurrence
AUTOMOBILE LIABILITY
$200,000 each person $500,000 each occurrence $20,000 property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance.
The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
I. 5 DIAR 1452.237-70 INFORMATION COLLECTION – JUL 1996
DEPARTMENT OF THE INTERIOR
If performance of this contract requires the contractor to collect information on identical items from ten or more public respondents, no action shall be taken or funds expended in the
I-6 solicitation or collection of such information until the contractor has received from the Contracting Officer written notification that approval has been obtained from the Office of Management and Budget (OMB) pursuant to the Paperwork Reduction Act of 1980. The Contractor agrees to provide all information requested by the Contracting Officer which is necessary to obtain approval from OMB.
I. 6 52.203-99 PROHIBITION ON CONTRACTING WITH MAR 2015
ENTITIES THAT REQUIRE CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS—
(DEVIATION 2015-02)
(a) The contractor shall not require employees or subcontractors seeking to report fraud, waste, or abuse to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such fraud, waste, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(b) The contractor shall notify employees that the prohibition and restrictions of any internal confidentiality agreements covered by this clause are no longer in effect.
(c) The prohibition in paragraph (a) of this clause does not contravene requirements applicable to Standard Form 312, Form 4414, or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(d)(1) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Resolution Appropriations Act, 2015 (Pub. L. 113-235), use of funds appropriated (or otherwise made available) under that or any other Act may be prohibited, if the Government determines that the contractor is not in compliance with the provisions of this clause.
(2) The Government may seek any available remedies in the event the contractor fails to comply with the provisions of this…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .