PBRWS_R16PS00829-Step_1_Amendment_2.pdf

PDF 3 MB Posted

Attached to
Pojoaque Basin Regional Water System Federal contract opportunity
Solicitation number
R16PS00829
Issued by
Department of the Interior Bureau of Reclamation

About this file

PBRWS R16PS00829-Step 1 Amendment 2

View the file

Other files for this federal contract opportunity

Other files attached to Pojoaque Basin Regional Water System, newest first.
File Type Posted
Sol_R16PS00829.pdf PDF
Solicitation_R16PS00829_PBRWS.pdf PDF
PBRWS_R16PS00829-Step_1_Amendment_3.pdf PDF
Sol_R16PS00829_Amd_000003.pdf PDF
Sol_R16PS00829.pdf PDF
Sol_R16PS00829_Amd_000002.pdf PDF
Solicitation_R16PS00829_PBRWS.pdf PDF
PBRWS_R16PS00829-Step_1_Amendment_1.pdf PDF
Sol_R16PS00829_Amd_000001.pdf PDF
Solicitation_R16PS00829_PBRWS.pdf PDF
Sol_R16PS00829.pdf PDF
Solicitation_R16PS00829_PBRWS.pdf PDF
Sol_R16PS00829.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pojoaque Basin Regional Water System R16PS00829-Step 1 Amendment 2 Questions and Answers

1. Document reference: L.12 WBR 1452.215-81 General Proposal Instructions Bureau of Reclamation, Step One – Request for Qualifications, Volume II, Qualification Proposal, Step 1-Factor 2: Project Team Organization and Key Personnel, p. 60 of 75 Question: Per the RFP, resumes of Key Personnel are to be included in Volume II. Please provide a list of key personnel for whom resumes will be required.

Answer: A solicitation replacement page has been attached.

2. Question - Would it be possible to obtain GIS data (preferably shapefiles) of both the minimum construction and the desired construction pipeline features for the project? This will greatly assist us in developing our technical approach (Factor 3).

Answer: This information will be made available to the three most highly qualified offerors to assist in preparation of the Step 2 RFP proposal.

3. Question: Pages 60 & 61 – Step 1 Factor 2 Project Team Organization and Key Personnel requests an Organization Chart that indicates “which firm each key position works for and who they report to”.

Under “Evaluation Factors” for Step 1 Factor 2 (page 72, last paragraph, 4th sentence) “an organizational chart for each firm that is part of the offeror’s project team” is requested. Please clarify if only one (1) Team Organizational Chart is required that shows which firm each key position works for and who they report to within the project team, or if you also require “an organizational chart for each firm”. If an organizational chart for each firm is required, what level of information is desired, i.e., Executive Management, Business Group, Operating Unit, etc.?

Answer: Either one Project Team organization chart that shows which firm each key position works for and who they report to within the project team, or separate organizational charts for each firm that highlights the key personnel on the project team and their supervisor/manager, is acceptable.

4. Question: Under Section L.12 General Proposal Instructions, key personnel resumes and example project descriptions are required to be submitted in the SF330 format (page 60). SF330 Sections E and F are referenced under Section J as Attachment #3. Please clarify that resumes of key personnel (Section E) and example projects (Section F) are the “only” SF 330 requirements for this submittal.

Answer: Offerors shall use the attached SF330 for Step 1 factor 1 and Step 1 factor 2.

5. Question: Please clarify that Volume 1, Business Proposal is not included in the scoring of offerors Step 1 submittal.

Answer: Only step one (RFQ)’s proposals will be evaluated under step one of this solicitation.

6. Question: We recently (in the past few months) requested Project Performance Questionnaires for the USBR’s Cutter Lateral WTP pursuit that we are also referencing in this RFQ. May we re-submit the questionnaires already completed for Cutter or can the contracting officer for this project request them from the Cutter Lateral WTP contracting officer?

Answer: In accordance with the solicitation. Past Performance Questionnaires shall be submitted on the form included in the solicitation (attachment #4 entitled past performance questionnaire).

7. Question: Section 01 11 00 Summary of Work Water Treatment Plant Pilot Study, page 7. When do you anticipate the study will be completed?

Answer: The “POJOAQUE BASIN REGIONAL WATER SYSTEM WATER TREATMENT PLANT PILOT STUDY, PILOT STUDY RESULTS REPORT” was submitted to Reclamation on July 30, 2016. This report will be added to the list of citations in the final PWS and will be made available to the three most highly qualified offerors to assist in preparation of the Step 2 RFP proposal.

8. Question: Section 01 11 00 Summary of Work 1.02 Definitions – can you provide a copy of the “Pojoaque Basin Regional Water System Feasibility Design Report” dated November 2015. We could not find it on the USBR project website. This report is not referenced in Section 51 00 00 Information Available to Offerors.

Answer: The citation for this report will be added to the final PWS. Reclamation 2015. Bureau of Reclamation, “Feasibility Design Report, Pojoaque Basin Regional Water System Feasibility Design Report, Albuquerque Area Office, Upper Colorado Region”, Denver, Colorado, October 2015. This report has been classified “For Official Use Only” and will only be made available to the three most highly qualified offerors to assist in preparation of the Step 2 RFP proposal.

9. Question: Page 64 of 1017 requests the Step 1- Factor 2: Project Team Organization and Key Personnel.

Please confirm the list of Key Personnel.

Answer: A corrected solicitation replacement page has been attached.

10. Question: Page 65 of 1017 states that The offerors are required to submit a fully completed “Resumes of Key Personnel Proposed for This Contract” document to address the education and experience of the proposed personnel. Please provide the educational and minimum experience for the key personnel.

Answer: A corrected solicitation replacement page has been attached.

11. Question: If a Reclamation PPQ was submitted within the last 3 months to Reclamation in Salt Lake City, may we reference that PPQ rather than request a duplicate this quickly of our clients?

Answer: In accordance with the solicitation. Past Performance Questionnaires shall be submitted on the form included in the solicitation (attachment #4 entitled past performance questionnaire).

12. Question: How long do you anticipate the solicitation period will be for Step 2. In other words, how many days from official posting of solicitation to when it is due?

Answer: We anticipate the solicitation period for step 2 will be 45 days.

13. Document reference: Solicitation R16PS00829 PBRWS, Section L.12, Page 60 of 75, Step 1-Factor 1 Design Builder Profile/ Experience. For each of the three experience requirements, the requirements state, “for New Construction and/or Construction Projects with features similar to the intake structure, water treatment plant, and/or ancillary facilities required for this project.”

Question: Does this mean that every project submitted under Factor 1 must contain all of these features or can a proposer submit projects that have some of the features, such as a water treatment plant without a pipeline or a pipeline project without a water treatment plant, as long as all features are included within the five (5) submitted projects?

Answer: Projects can be submitted that have some or all of the features to be included in the PBRWS. The offeror must decide what experience to provide which will meet the minimum requirement for this factor. An offeror providing experience which exceeds the minimum acceptable level may achieve a higher rating. Conversely, if an offeror provides less than the minimum acceptable level may achieve a lower than acceptable rating.

Pojoaque Basin Regional Water System

Pre-Proposal Site Visit August 23, 2016

RECLAMATION

Managing Water in the West

Presentation Topics

• Pojoaque Basin Regional Water System (PBRWS)

–Brief Project History –Project Description –Project Schedule –Design-Build Scope of Work –Project Challenges

• Settlement Agreement reached on the Aamodt litigation in

–Resolves water rights claims of the Nambé, Pojoaque, San Ildefonso, and Tesuque Pueblos and other residents of the Pojoaque Basin

• Claims Resolution Act of 2010 (P.L. 111-291), Title VI ratifies and authorizes the Aamodt Litigation Settlement

• Secretary of the Interior and other governmental parties signed the Aamodt Settlement Agreement on March 14, 2013

Project History

Aamodt Litigation Settlement Act

• The Act authorizes Reclamation to plan, design, construct and obtain environmental compliance for the Pojoaque Basin Regional Water System

(PBRWS)

• The PBRWS is to be built in “substantial compliance” with the September 2008 Engineering Report prepared by HKM Engineering

• The Act establishes several deadlines, including completion of all “conditions precedent” by September 15, 2017 and completion of the PBRWS by June 30, 2024

Aamodt Litigation Settlement Act

“The Secretary shall issue a 100% project design within 90 days of completion of the environmental compliances described in section 616 for the Regional Water System that -- (1) is consistent with the Engineering Report; and (2) includes a description of any Pueblo Water Facilities.”

PBRWS Project Purpose & Need

• The purpose is to reliably provide a firm, safe supply of treated drinking water for distribution in the Pojoaque Basin in compliance with the Settlement Act.

• The need is to reduce reliance on groundwater in the Pojoaque Basin and to allow the Settlement Pueblos to receive a portion of the water provided under the Settlement Act.

• Capable of delivering up to 4,000 acre-feet (af) per year of consumptive use water to:

–Nambé, Pojoaque, San Ildefonso, & Tesuque Pueblos (2,500 af)

–Non-Pueblo residents of the Pojoaque Basin (up to 1,500 af)

• Provide fire protection flows where feasible

• Construction begins after conditions precedent have been met and Record of Decision is signed (2018)

Proposed Regional Water System

• PBRWS Components include:

– Firm and Reliable Water Supply

–Water Collection System (4 alternatives under consideration)

–Raw Water Transmission

–Water Treatment Plant

–10 new Water Distribution Tanks

–8 Pump Stations

–approx. 160 miles of Transmission and Distribution Pipelines

PBRWS Intake Structure

• Four options under consideration

1. Side Channel Diversion 2. Horizontal Collector Wells

PBRWS Intake Structure

• Four options under consideration

3. Parallel Interceptor Drain 4. Infiltration Galleries Installed perpendicular to river

Back-filled Trenches

Fishing Pond

Otowi Bridge

Installation of perforated stainless steel pipe

Backfilling trench and displacing biopolymer slurry

• Reclamation authorized $5 million to perform OM&R during construction

• PBRWS must be completed by June 30, 2024 or

Settlement may be voided

• Upon completion, title to their respective portions of the PBRWS will be transferred to the four Pueblos, the County Water Utility, and the Regional Water Authority (RWA)

PBRWS Project Schedule Feasibility

Design

Draft Environmental Impact Statement (EIS)

Design Data Collection

Final Design

Construction

Operations and

Maintenance

Final EIS and Record of Decision

2012 2014 2015 2016 2017 2018 2024

Land Acquisition

PBRWS EIS

• Public Draft EIS with preferred alternative available:

November 2016

• Final Draft EIS and Record of Decision: December

2017 – January 2018

PBRWS – Work Completed and In Progress Feasibility Design Report

Completed December 2015

Design Data Collection

Feasibility Design

Development

Existing Utilities

Pilot Studies

(WTP, HCW,

ASR)

* Geotechnical

Facility DesignSurveys

Facility Placement

Design Criteria

Feasibility and

* Final Water

Demand Studies

Feasibility-Level Cost Estimates

* In Progress

Note: the requirements contained in this Performance Work Statement

(PWS)

supersede the descriptions, requirements, and specifications contained in the FDR

• Combination of Design-Build (DB) and Design-Bid- Build (DBB) project delivery methods

• Final designs to be completed within 90 days of ROD (April 2018)

–San Ildefonso and North Pojoaque by DB Contractor –Nambe, South Pojoaque, Tesuque and Bishop’s Lodge

Extension by Reclamation’s Technical Service Center (TSC)

Final Designs for the

• The two design teams and AAO will work together through a partnering agreement

• Both portions of the PBRWS are intended to be operated together, as a single regional water system.

• The DB Contractor shall coordinate with Reclamation’s design-bid-build team to meet this objective.

Final Designs for the

• Temporary and Permanent Easements will be Acquired by Reclamation (Tribal Lands, Private Lands)

• Construction easement widths vary

• Anticipate using NMDOT utility installation permits for construction along state highway rights of way

• Reclamation will perform required cultural resource treatment and/or mitigation prior to construction of each PBRWS facility and pipeline segment

Construction of the

DB and DBB Portions of the PBRWS

• 8 Pumping Stations

• 14 Existing Water

Storage/DistributionTanks

• 9 New Tanks

• Water Supply Intake System

• Raw Water Transmission

• Water Treatment Plant

• Potable Water Transmission

• Pueblo and Non-Pueblo

Distribution

DB Portion of the PBRWS (Design Stage 1)

• 3 Pumping Stations and 2 Forebay Tanks

• 6 Existing Tanks

• 3 New Storage/DistTanks

• Water Supply Intake System

• Raw Water Transmission

• Water Treatment Plant

• Potable Water Transmission

• Pueblo and Non-Pueblo

Construction of the Regional Water System (continued) Construction to be completed in 3 Phases

• Phase 1 includes DB design except for deferred distribution

• Phase 2 includes TSC design except deferred distribution

• Phase 3 includes installation of deferred distribution lines from phases 1&2

Design & Construction Schedule

Design-Bid-Build (Stage 2 Design, Construction Phase 2)

Design-Build (Stage 1 Design, Construction Phase 1)

FY 2016 2017 2017 – Apr 2018 2018 2019 2020 2021 2022 2023 2024 2025

Develop Phase 3 Alignments & Serv Agrt for Final Designs and Specs

Final Designs 90d after ROD Construct Transmission System, Tanks Nambe, Tesuque, Bishop’s Lodge

Close out

Constr uction contra cts

O&M During Construction

FY 2016 2017 2017 – Apr 2018 2018 2019 2020 2021 2022 2023 2024 2025

Develop Phase 3 Alignmnts & PWS for DB Contract

Award DB Contract

Final Designs 90d after ROD

Construct diversion, WTP, Transmission, Tanks San Ildefonso, Pojoaque

Close‐ out DB Contct O&M During Construction

FY 2016 2017 2017 – Apr 2108 2018 2019 2020 2021 2022 2023 2024 2025

Develop Phase 3 Alignments & Serv Agrt for Final Designs and Specs

Final Designs 90d after ROD Construct Deferred Distribution Lines

Closeout Final Construction and OM&R Contracts

Construction Phase 3 – Deferred

Design-Build Performance Work Statement (PWS) Scope of Design-Build Contract – Design Stage:

• All features hydraulically dependent up to, and including, the forebay tank for Nambé Pumping Plant and up to, and including, the forebay tank for South Pojoaque Pumping Plant.

• The design of these two forebay tanks shall be coordinated with the TSC DBB design team.

• Any necessary design data collection (e.g. additional geotechnical investigations, water compatibility)

Design-Build PWS Scope of Design-Build Contract – Design Stage (continued):

• One water treatment plant (WTP)

• One source water collection system

• One raw water pipeline,

• Three pumping plants (1 to lift raw water from the

Rio Grande to the WTP, 1 to lift treated water from the WTP to the system, and 1 at Pojoaque Industrial Park)

(continued):

• Two new forebay tanks (at Nambé Pumping Plant and South Pojoaque Pumping Plant)

• Three new water storage/distribution tanks (El

Rancho, Pojoaque Industrial Park, and White Sands) incorporate associated existing facilities such as selected wells, distribution tanks and pipelines to service the DB project area

• Note: The Pojoaque Industrial Park water storage/distribution tank also serves as the forebay tank for the Pojoaque Industrial Park Pumping Plant

(continued):

• Design SCADA and communications system for DB and DBB portions of the PBRWS in coordination with the TSC design team, provide technical requirements for SCADA and communications for the DBB portion

Scope of Design-Build Contract - Construction Phase:

• Raw water intake, raw water transmission line, water treatment plant, three new water storage/distribution tanks, three pumping plants and transmission lines

• Distribution lines that can be installed in same trench as the transmission lines and some key distribution lines for the Pueblo de San Ildefonso and northern portions of Pojoaque Pueblo

• Connect to 6 existing water distribution/storage tanks

Scope of Design-Build Contract - Construction Phase (continued):

• Install SCADA components and communications equipment needed to operate the DB portion of the PBRWS, including the master control station

• Permits needed to construct

• Includes startup, acceptance testing, commissioning and performance testing

Scope of Design-Build Contract – Post Construction Phase:

• Six months of demonstration testing and extended demonstration testing

• Contractor shall be the Public Water System certified operator of record for the WTP and conveyance system during this time period.

• Includes training of RWA and Tribal operations and maintenance personnel and technical support

This contract DOES NOT include:

• Hook up of meters or service lines to individual water customers

• Long-term operations and maintenance of the

PBRWS

• Cultural Resources monitoring, treatment or mitigation

• Land Acquisition

Performance Requirements:

• Divert, treat, and deliver from 99.5 acre-feet up to

4,000 acre-feet of drinking water annually

• Maintain water quality that meets safe drinking water act standards

• Ensure finished water produced by the WTP is compatible with the groundwater supply produced by all existing wells selected for use as emergency/supplemental water supply

–Existing well water quality data available in October 2016

Performance Requirements (continued):

• Contractor must follow all identified best management practices and environmental commitments, including incorporating cultural resource protection measures in their work plans and notifying Reclamation of any unexpected discoveries or damage to cultural resources or historic properties.

• Minimize drinking water supply outages to homes, public facilities and businesses

• Minimize length of time that people are unable to access their homes, public facilities and businesses

• Each project feature and each segment of transmission and distribution pipeline must have an associated and tracked cost and “final ownership” identifier to facilitate transfer of the PBRWS upon declaration by the Secretary that the PBRWS is substantially complete (both DB and DBB portions)

• Others listed in the PWS

PBRWS Project Challenges

• Available budget, statutory deadlines

• PBRWS facilities and alignments not final until ROD

• Water age, disinfection by-products rule

• Wide range of production rates from initial operations to full demand

• Narrow roadways in residential areas congested with existing underground utilities and irrigation infrastructure

• Several river crossings and numerous arroyo crossings

PBRWS Project Challenges (continued)

• Unanticipated finds of cultural resources during construction that will cause short-term and long-term work delays which may result in the need to move to a different construction location

• Requirement to prevent damage to historic properties

PBRWS Project Challenges (continued)

• Incorporation of existing facilities and supplemental ground water wells into the PBRWS while minimizing drinking water supply disruptions for Pueblo customers

• Need to partner with four Pueblos, Santa Fe County, Regional Water Authority, NM Department of Transportation, TSC Design Team and AAO Project Management Team during design, construction, and post-construction phases

NEXT:

Lunch on your own

Buses start loading at 1:15 pm Tour begins at 1:30 pm

Solicitation Document No.

R16PS00829-Step 1

Document Title Pojoaque Basin Regional Water System

The tabs shall conform to the Table of Contents to the terms of the proposal and indicate how the proposal conforms to the evaluation factors as shown above. Tabs do not count toward page limits.

(3) Enclosures The enclosures shall include a list of any tables, drawings, charts, and any other enclosures which summarize data or information. The enclosures must be included in the appropriate section and listed in the Table of Contents. The list of enclosures does not count toward page limits.

(4) Executive Summary The Executive Summary shall include a brief discussion of how the required work will be performed and important highlights of the proposal. There is a 10 page limit for the executive summary.

E. TECHNICAL EVALUATION FACTORS

The following information should be provided in the Qualification Proposal to address each factor and subfactor. Factors are listed in descending order of importance. All subfactors are of equal importance.

The Page limit for Volume II is 100 pages.

Step 1-Factor 1: Design Builder Profile/Experience The Offeror shall demonstrate experience by providing evidence of up to five (5) projects completed within the last eight (8) years similar to the scope, complexity, and magnitude of the requirements under this solicitation by completing the Project Information Worksheet for each identified project. These projects are not required to have been completed in New Mexico. The SF-330 is included in Section J, Attachment No. 3: The experience listed shall include:

a. Experience of Designer:

In completing water infrastructure projects of similar size, scope and duration to this project. Experience in Federal, Local Government or Tribal Performance and Private Sector for New Construction and/or Construction Projects with features similar to the intake structure, water treatment plant, and/or ancillary facilities required for this project.

b. Experience of Builder:

In completing water infrastructure projects of similar size, scope and duration to this project. Experience in Federal, Local Government or Tribal Performance and Private Sector for New Construction and/or Construction Projects with features similar to the intake structure, water treatment plant, and/or ancillary facilities required for this project.

c. Experience of Design-Build Team:

In completing water infrastructure projects of similar size, scope and duration to this project. Experience in Federal, Local Government or Tribal Performance and Private Sector for New Construction and/or Construction Projects with features similar to the intake structure, water treatment plant, and/or ancillary facilities required for this project.

Step 1-Factor 2: Project Team Organization and Key Personnel Offerors are required to complete the document “Resumes of Key Personnel Proposed for this Contract” which addresses the education, qualifications, certifications, and relevant experience for each Key Personnel. The document is included in Section J, Attachment No. 3:

(SF-330) Each Resume document shall not exceed 4 pages.

a. Resumes of Key Personnel The offerors are required to submit a fully completed “Resumes of Key Personnel Proposed for This Contract” document to address the education and experience of the proposed personnel. One worksheet shall be completed for each key personnel. Failure to include a fully completed worksheet for each of the positions below shall affect the overall rating of the Offeror’s proposal. Additional key personnel may be proposed by the Offeror.

(a) Design-Build Project Manager(s)/Director (Minimum level of experience--10 years’ experience, current PE license)

Amendment 2 replacement page Clause L.12

Solicitation Document No.

R16PS00829-Step 1

Document Title Pojoaque Basin Regional Water System

(b) Principal Designer (Minimum level of experience--7 years’ experience, current PE license)

(c) Construction Manager (Minimum level of experience--5 years’ experience)

(d) Water Treatment Process Engineer (Minimum level of experience--5 years’ experience, current PE license)

(e) Sub-surface Intake System Designer (Minimum level of experience--5 years’ experience, current PE license)

b. Key Position Roles and Responsibilities Offerors are required to submit the proposed identified project roles and responsibilities for each proposed position. Required Qualifications and Certifications shall be included in the description. (See SF-330 instructions) At a minimum, the Offerors are required to submit the identified project roles and responsibilities for each below listed position. Required Qualifications and Certifications shall be included in the description.

(a) Design-Build Project Manager/Director (Minimum level of experience--10 years’ experience, current PE license)

(b) Principal Designer (Minimum level of experience--7 years’ experience, current PE license)

(c) Construction Manager (Minimum level of experience--5 years’ experience)

(d) Water Treatment Process Engineer (Minimum level of experience--5 years’ experience, current PE license)

(e) Sub-surface Intake System Designer (Minimum level of experience--5 years’ experience, current PE license)

The offeror shall also provide a:

I. Responsibility Matrix to clearly identify roles and responsibilities between the key positions

II. Personnel Management Plan to show how the positions will be managed throughout all project phases III. Organization Chart(s) indicating which firm each key position works for and who they report to

Failure to include a fully completed SF-330 shall affect the overall rating of the Offeror’s proposal.

Step 1-Factor 3: General Technical Approach Based on the information presented in Section C, the offerors shall submit the following:

a) Narrative description of the overall work plan. The narrative description shall be concise and complete, addressing the design, construction, and post-construction phases of this project.

b) Milestone schedule for the design, construction, and post-construction phases of this project.

c) General means and methods for executing work, addressing the principal components of the performance work statement.

d) Means and methods for quality control for design.

e) Means and methods for quality control for construction.

f) List of projected risks and mitigation measures for the work required by this project.

Step 1-Factor 4: Past Performance The offeror shall provide past performance questionnaires (PPQs) on all projects identified under Factor 1: Experience and Subfactor 1a, 1b, and 1c. The offeror shall submit the PPQs to their references and have the references complete and return the questionnaires via email to wbennett@usbr.gov by the date and time indicated on the form. The PPQ is included in Section J, Attachment No. 5: Past Performance Questionnaire.

The Government shall consider the information provided by the references, and may also consider information obtained from other sources when evaluating an offerors past performance.

Amendment 2 replacement page

Amendment 2 Q and A KLD
PBRWS Contractor Site Visit Sign-in Sheet 8-23-2016
PBRWS Pueblo Site Visit Sign-in Sheet 8-23-2016
PBRWS DB RFQ Site Visit 23 Aug 2016
Sol R16PS00829 PBRWS SW Step 1 final