This is a Change Order Request for Participation or Piggyback Contract submitted by the Illinois Department of Natural Resources (IDNR) Office of Law Enforcement (OLE) to the State of Illinois Chief Procurement Office, involving a contract extension with Getac through the Sourcewell cooperative procurement consortium for body-worn camera and in-car video camera systems. The change order requests a one-year contract extension to continue providing body-worn camera systems, in-car video camera systems, miscellaneous mounting and operating hardware, cloud-based digital video storage plans, factory and extended warranty plans, year 2 or 3 body camera system refresh provisions, on-site and remote training and setup sessions, and customer service agreements. The original contract was set to expire on November 7, 2026, and the extension would establish a new completion date of November 7, 2027. The request references the "ILDNR Quote Getac Video 3-26-24" for itemized products, services, quantities, and costs.
The original contract value was $2,599,945.00, with the one-year extension adding $2,836,995.00 in additional costs. IDNR OLE justified the extension based on approximately two years of existing investment in the Getac platform, established operational procedures, evidence management systems, trained personnel including Legal Counsel, and state law requirements mandating body-worn camera usage. The agency determined that transitioning to another vendor would incur significant costs including equipment replacement, evidence migration, retraining, and potential disruption to law enforcement operations and public safety compliance. Sourcewell's renewal of its contract with Getac provided the opportunity to exercise a contemplated one-year extension option already included in the original cooperative agreement, approved by the Agency Purchasing Officer, State Purchasing Officer, and Chief Procurement Officer on dates ranging from November 4-5, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00004570__Getac Contract Extension.pdf | ||
| Illinois DNR Getac Contract Renewal 103026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Request for Participation or Piggyback Contract State of Illinois Chief Procurement Office General Services Change Order Request for Participation or Piggyback Contract v.25.1 Page of Section I - General Information Section II - Change Order Information
1. Provide the original contract description:
2. Provide a detailed description and explanation for the change required:
3. The completion date will be
4. The Cost will be
5. The circumstances said to necessitate this change was not reasonably foreseeable at the time the contract was signed.
The change is germane to the original contract as signed.
APPROVAL SIGNATURES
Agency Purchasing Officer Approval I know and understand the contents of this Change Order Request and attest that all statements are true and correct.
State Purchasing Officer Recommendation Based on my review of the provided information, with the requested change(s) for the following reason(s):
Unified Procurement Program Review and Recommendation Based on my review of the provided information, in the best interests of the State to allow the requested change(s) to the existing contract for the following reason(s):
Chief Procurement Officer Approval Based on my review of the provided information, I determine in the best interests of the State to allow the requested change(s) to the contract for the following reason(s):
6.5.0.20190320.2.935878.932721
| CurrentPage: |
| PageCount: |
| AGENCYDROPDOWN: DNR - Natural Resources |
| TextField1: DNR - UPP - Body Cameras and In Car Camera Systems |
| TextField2: Sourcewell |
| TextField3: GETAC |
| TextField4: 10/29/2024 - 11/07/2026 |
| TextField5: $2,599,945.00 |
| DropDownList1: Participation |
| TextField6: 25-422DNR-DIREC-P-73224 |
| TextField7: 27-422DNR-LAWEN-R-336084 |
| TextField8: To complete the Body Worn Camera Systems, supplies includes complete In-car Video Camera Systems, Miscellaneous mounting, and operating hardware components necessary to operate both the Body Worn and in-car Camera Systems, Cloud-based digital video storage plans, factory and extended warranty plans, year 2 or 3 body camera system refresh provisions, both on-site and remote training/ set up sessions and customer service agreements. Specifically refer to the Getac Quote titled, "ILDNR Quote Getac Video 3-26-24" for an itemized list of products, services, quantities, and associated costs for each. |
| TextField9: IDNR OLE has invested approximately two years implementing Getac body-worn cameras and in-car camera systems statewide. Our existing equipment, evidence management, cloud storage, retention processes, and officer training are all established around the Getac |
platform. Additionally, our Legal Counsel has been trained on the Getac system and utilizes its redaction software to process FOIA and subpoena requests. Sourcewell recently renewed it's contract with Getac for an additional one-year term to provide existing vendors the opportunity to continue their services without disruption. Considering our existing investment, operational needs, and statutory obligations, I believe we have a strong justification for requesting a contract extension with Getac via Sourcewell.
Transitioning to another vendor would involve significant additional costs, including replacing existing equipment, migrating stored evidence, retraining officers and Legal Counsel, and potentially disrupting our established evidence management processes. IDNR OLE is also mandated by state law to utilize body-worn cameras. Given the time required to procure, implement, and train personnel on an entirely new system, transitioning vendors could create significant disruptions to law enforcement operations, negatively impact public safety, and potentially jeopardize our ability to maintain compliance with state requirements.
| CheckBox1: 1 |
| CheckBox2: 0 |
| CheckBox3: 0 |
| DateField1: 2027-11-07 |
| CheckBox4: 1 |
| CheckBox5: 0 |
| CheckBox6: 0 |
| TextField10: $2,836,995.00 |
| : |
| SignatureField1: |
| TextField11: Maurice Mosley |
| DateField2: 2026-11-04 |
| DropDownList2: I agree |
| explanationfield: change aligns with the terms and conditions of the cooperative contract and meets the agency's expanded need. |
| spoSignatureField2: |
| spoprintedname: Colene Underwood |
| DateField3: |
| DropDownList3: it is |
| TextField12: The 1-year extension was contemplated in the cooperative contract, to be exercised upon bi-lateral agreement of the two parties; applying that same extension to the State of Illinois contract allows for uninterrupted usage to continue to meet the agency's ongoing need. |
| SignatureField2: |
| TextField13: Joshua Sergent |
| DateField4: 2026-11-05 |
| DropDownList4: it is |
| TextField15: The agency has an ongoing need for the equipment and services provided by the vendor, and use of the contract by participation that resulted from this cooperative procurement was already approved. |
| SignatureField3: |
| TextField16: Ellen H Daley by Jan E Morrow |
| DateField5: 2026-11-05 |
File details come from the government source that posted it. Updated .