This document is a quote tabulation for the Linn County Road Department's Pre-Level & Overlay Work on Bond Road (Project M2503), featuring bid submissions from seven different paving contractors: North Santiam Paving, Knife River, RiverBend Materials, KNL Industries, Wildish, Double Eagle Paving, O.A.M., and Settje Sons Paving. The project involves roadway improvements with four primary pay items: mobilization, temporary traffic control, driveway paving, and hot mix asphalt concrete (HMAC or WMAC), with a total estimated quantity of 699 tons of asphalt. The bid opening was scheduled for Wednesday, April 9th at 1:00 P.M. PDT, with contractors submitting varied unit rates and total costs for each line item.

The quote tabulation includes a comprehensive comparison of each contractor's pricing, with total project costs ranging from $78,798.00 to $129,840.00, excluding the LCRD (Linn County Road Department) estimate of $95,131.00. The document provides a detailed breakdown of unit rates for each pay item across different contractors, revealing significant variation in pricing strategies. The LCRD estimate suggests budgetary expectations, with line items for mobilization at $5,500.00, temporary traffic control at $3,250.00, driveway paving at $3,200.00, and HMAC/WMAC at $83,181.00, totaling $95,131.00 for the entire project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M2503

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $3,000.00 $3,000.00 $4,797.80 $4,797.80 $4,000.00 $4,000.00 $5,000.00 $5,000.00

Temporary Traffic Control 1 LS $2,100.00 $2,100.00 $5,259.85 $5,259.85 $4,000.00 $4,000.00 $6,500.00 $6,500.00

Driveway Paving 4 Each $600.00 $2,400.00 $796.94 $3,187.76 $850.00 $3,400.00 $1,500.00 $6,000.00

HMAC or WMAC 699 Tons $102.00 $71,298.00 $97.91 $68,439.09 $107.50 $75,142.50 $100.00 $69,900.00

TOTALS: $78,798.00 $81,684.50 $86,542.50 $87,400.00

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $6,600.00 $6,600.00 $3,200.00 $3,200.00 $7,228.00 $7,228.00 $3,000.00 $3,000.00

Temporary Traffic Control 1 LS $6,100.00 $6,100.00 $5,141.00 $5,141.00 $6,075.00 $6,075.00 $12,000.00 $12,000.00

Driveway Paving 4 Each $500.00 $2,000.00 $746.00 $2,984.00 $1,200.00 $4,800.00 $750.00 $3,000.00

HMAC or WMAC 699 Tons $110.00 $76,890.00 $119.52 $83,544.48 $130.98 $91,555.02 $160.00 $111,840.00

TOTALS: $91,590.00 $94,869.48 $109,658.02 $129,840.00

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5,500.00 $5,500.00

Temporary Traffic Control 1 LS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,250.00 $3,250.00

Driveway Paving 4 Each $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $800.00 $3,200.00

HMAC or WMAC 699 Tons $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $119.00 $83,181.00

TOTALS: $0.00 $0.00 $0.00 $95,131.00

KNL Industries, Inc.

Settje Sons Paving

LCRD Estimate

Pre-Level & Overlay Work

Bond Road

Wednesday, April 9th 1:00 P.M. PDT

Linn County Road Department

Wildish Double Eagle Paving O.A.M.

North Santiam Paving Knife River RiverBend Materials