Questions & Responses .docx
DOCX document 14 KB Posted
- Attached to
- 6130-EGBA- SUNLIGHT / LeVITA: RN-15-0114
- Solicitation number
- RFP EGBA 2015000114 4
- Issued by
- Garfield County, Denver City, Colorado
About this file
This is a Questions & Responses document for RFP-20105002114 regarding the Sunlight Tower Replacement project. The document addresses three clarifications submitted during the bidding process. The first question confirms that the proposed tower location does not create interference with existing microwave antenna paths. The second question pertains to fall protection equipment specifications outlined in section 4.3.24, clarifying that while no specific manufacturer or model is mandated, fall arrestors manufactured by both DBI Sala and Tuf-Tug are acceptable as they meet the specification requirements. The third question addresses bolt locking mechanisms in section 4.3.11, establishing that lock washers, PAL nuts, and Half Nuts are all acceptable locking devices for tower bolts.
The document provides flexible guidance on equipment and materials selection, indicating that the contracting agency allows bidders discretion in choosing compliant products rather than specifying single manufacturers or models. This approach suggests the agency prioritizes meeting performance and safety standards over prescriptive procurement requirements. No pricing information, set-aside provisions, incumbency details, funding sources, or contract timeline information is included in this Q&A document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Alternates.doc | DOC document | |
| PerfBond.docx | DOCX document | |
| APPENDIX F- Budget Sunlite.doc | DOC document | |
| Appendix B (1).docx | DOCX document | |
| BuildingCodeCompliancePolicy.pdf | ||
| MBond.docx | DOCX document | |
| Appendix D- Specifications.docx | DOCX document | |
| Appendix B (2).docx | DOCX document | |
| RFP-2015000114 Sunlight.docx | DOCX document | |
| Appendix C .docx | DOCX document | |
| Attachment B-SitePlan.pdf | ||
| Attachment C-GroundPlanDet.pdf | ||
| RFP-2015000114 Sunlight MOD1.docx | DOCX document | |
| Bid Bond.docx | DOCX document | |
| Bid Form.docx | DOCX document | |
| Attachment D-GeotechReport.pdf | ||
| Attachment A-approvedstatebldgcode.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP-20105002114
Sunlight Tower Replacement
| Number | |
| Question | |
| Response |
| 1 |
| Does the proposed location of the new tower have any interference with existing microwave antenna paths? |
No
| 2 |
| 4.3.24, Fall Protection, Is there a specific manufacturer and model # that you have in mind for the removable fall arrestors? |
| No, DBI Sala and Tuf-Tug Both manufacture fall protection systems that meet the intent of the specification. |
| 3 |
| 4.3.11, Are lock washers an acceptable locking device for the tower bolts. |
| Yes, lock washers, PAL nuts and Half Nuts are all acceptable locking devices. |