This document is a Questions and Answers record from a mandatory pre-bid walk-through meeting held on August 17, 2016, for DQ DOR17004 UPS-Distribution System project. The walk-through addressed technical specifications and project requirements for the installation of new UPS and PDU equipment to replace existing systems. Current equipment includes deep cell 12V batteries (BAT L-A 12V 284 w/cell Plyprop), with 36 units currently in use and replaced every 4 to 5 years. The new equipment may be installed in an alternative location within the room without requiring demolition work. Vendors are permitted to use elevators for equipment movement, with batteries transported separately. The existing UPS and Liebert units will be removed, while the panel will remain in place. Photography was permitted during the walk-through except for computer equipment. An error in the original document regarding electrical specifications (page 6, section 3g) was corrected to specify 208 - 4 wire plugs, with the updated version posted to VSS.

Bidders should note that background checks are required for both prime contractors and subcontractors, with costs not to exceed the amounts listed in the DQ except in special circumstances. The government does not possess wiring diagrams for the bypass system and is uncertain about specific bypass connections, indicating bidders should conduct thorough site assessments. Old equipment may remain in place until new equipment becomes operational. The government does not have a fixed budget for the FY16 TFAA 7000 UPS and PDU bid and will be responsible for replacement of floor tiles following equipment removal. No specific contract term, renewal options, award date, or response deadline is documented in this Q&A record.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DQ DOR17004 UPS-Distribution System Questions/Answers asked at mandatory pre-bid walk-through 08/17/16 10:00 AM

1. Are we allowed to take photos?

A. Yes,, but not of the computer equipment.

2. Is the current bypass switch on?

A. It is currently off because when it was switched on it short circuited.

3. Are there diagrams of wiring of the ByPass?

A. We do not have diagrams of the ByPass wiring.

4. Is the sole breaker the one labeled UPS-AC Input?

A. Yes.

5. The bypass wraps around and ties in how? Breaker or Input?

A. We believe it ties into the PDU, but are not certain as we did not originally install it.

6. What type of batteries do we currently have?

A. Deep cell 12V.

7. How long do we go before replacing the batteries?

A. We replace them every 4 to 5 years.

8. Are the background checks more than what is listed in the DQ?

A. They should not go above that price but if there are special circumstances it may.

9. Do they do background checks on sub-contractors also?

A. Yes.

10. Does the new equipment have to be where the old equipment currently is?

A. No, the new equipment may be put somewhere else in the room as long as there is no demo.

11. Are they removing the UPS & Liebert only? Does the panel stay?

A. Yes

12. Can they use the elevator to move the equipment?

A. Yes but the batteries will have to be a separate trip.

13. There is an error on pg 6 3g. of the DQ.

A. It should say 208 – 4 wire plugs. This error has been corrected in the document and an updated version is posted to VSS.

14. If we install the new equipment in a new location can the old equipment stay where it is located until the new equipment is up and running.

A. Yes

15. What is the manufacturer and number the batteries? Do you know the weight?

We do not know the weight the batteries are BAT L-A 12V 284 w/cell Plyprop and there are 36 of them.

16. After removal is the vendor responsible for replacement of floor tiles.

A. No, we have extra floor tiles and will work with the landlord to fill the opening.

17. Is there a cost estimate or budget for the FY16 TFAA 7000 UPS and PDU bid?

A. We do not have a fixed budget for this project.