QUESTIONS AND ANSWERS NO 2.docx
DOCX document 903 KB Posted
- Attached to
- BOILER UPGRADE U. S. EMBASSY MADRID
- Solicitation number
- 19SP5026Q0012QUESTIONSANDANSWERS2
- Issued by
-
Department of State US Embassy Madrid
About this file
This is a Questions and Answers document for Solicitation 19SP5026Q0012 regarding a Boiler Upgrade project at the U.S. Embassy Madrid. The document addresses 12 clarification questions from prospective offerors regarding project scope, specifications, and performance requirements. The project will be executed in two phases: Phase 1 (approximately 35 days in late June) will involve installation of a magnetic filter and heat water collector, and Phase 2 (approximately 25 days in September) will address flooring installation, with a total estimated performance period of 60 days. Key technical specifications include the requirement for two magnetic filters (one per boiler) for the Domestic Hot Water (DHW) return pump system, all stainless steel components (AISI 316L), installation of temporary DHW production heat pump equipment with piping and electrical connections, and floor resin replacement in a designated zone beneath the hot water tanks. Additional work includes dismantling of 40 mm PPR piping, reconnection of the DHW system circuit with shut-off valves and insulation, and installation of a bypass between tanks. Service must be maintained continuously throughout the project duration. Supporting documentation including photographs of conduits, drawings of the sub-basement area, and a marked plan for the floor resin replacement zone are referenced as attachments to Amendment 1 of the solicitation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS NO. 2 – SOLICITATION 19SP5026Q0012
QUESTION 1: If work is to be done in phases, please include performance period for each phase.
ANSWER: The project is proposed to be completed in two phases: the first phase will take place in late June for the installation of the magnetic filter and heat water collector; the second phase will be conducted in September for the flooring installation.
· Phase 1: Magnetic filter and heat water collector: 35 days
· Phase 2: Floor: 25 days This change will be incorporated to Amendment 1 of the solicitation.
QUESTION 2: Please confirm estimated performance period.
ANSWER: 60 days
QUESTION 3Please provide photos of conduits by hot water tanks.
ANWSWER: See pictures below This will be included in Amendment 1 to the solicitation as Attachment ·7
QUESTION 4: Please provide drawing of sub-basement area.
ANSWER: Attachment #6 – DRAWINGS has been incorporated into Amendment 1 to the solicitation.
QUESTION 5: How many filters are required for DHW return pump? Prospective offerors recommend that one filter per boiler is installed.
ANSWER Two filters (one per boiler) will be required. Statement of work will be modified to reflect this change. This will be part of Amendment 1 to the solicitation.
QUESTION 6: Does the floor area under hot water deposits need to be repaired/refinished?
ANSWER Yes, we must install the flooring underneath the tanks.
QUESTION 7: Is the filter only magnetic or also a sludge separator?
ANSWER The filter is only magnetic.
QUESTION 8: Can you define the floor resin replacement zone?
ANSWER The attached plan shows the marked area.
QUESTION 9: Can you confirm that everything is stainless steel?
ANSWER Yes, as stated in the SOW, stainless steel components are required. (See below excerpt of SOW: "Reconnection of DHW System Circuit - Unit for reconnection and installation of new piping and the existing DHW heat exchanger, including shut-off valves, fittings, and insulation. Executed in AISI 316L stainless steel, including bypass between tanks.")
QUESTION 10: From which zone should the piping be dismantled?
ANSWER From the 40 mm PPR piping.
QUESTION11 Is it necessary to perform the bypass?
ANSWER Yes, this is stated in the SOW (see below excerpt: "Temporary Domestic Hot Water (DHW) Production Heat Pump: Rental and installation of a heat pump system for temporary DHW production during the remodeling works in the room. Installed indoors and near the storage tanks, complete with piping, valves, and temporary electrical connection.")
QUESTION 12 Is it necessary to maintain service?
ANSWER Yes, service must be maintained at all times.